IN THE HIGH COURT OF DELHI AT NEW DELHI
Rajiv Sahai Endlaw, Amit Bansal, JJ.
Manikaran Power Limited - Appellant
Versus
Valuehunt Advisors Llp - Respondent
F.A.O. (Comm) No. 5 of 2021; C.M. Appl No. 33109 of 2020
Decided On : 06-04-2021
Arbitration - Commercial Dispute - Arbitration and Conciliation Act 1996 - Section 34 - Section 37 - Agreement for advisory services - Termination of contract - Dispute over payment - Arbitral award challenged under Section 34 - Appeal under Section 37 - Court's limited scope of interference - Appellant's challenge confined to second invoice amount - Court's refusal to interfere with arbitral award - Costs imposed on appellant
Fact of the Case:
The appellant appealed the dismissal of its Section 34 petition under the Arbitration Act, challenging an arbitral award for payment of Rs. 24,75,000/- with interest to the respondent. The appellant had terminated an agreement for advisory services, leading to disputes and arbitration.
Finding of the Court:
The Court refused to interfere with the arbitral award, citing the limited scope of interference under Section 37. The appellant's challenge was confined to the amount of the second invoice, but the Court found no ground for interference. Costs of Rs. 50,000/- were imposed on the appellant, reduced to Rs. 25,000/- on undertaking to pay within four weeks.
Issues: Dispute over payment under terminated advisory services agreement, challenge to arbitral award under Section 34, limited scope of interference under Section 37, imposition of costs on the appellant.
Ratio Decidendi: The Court's refusal to interfere with the arbitral award was based on the limited scope of interference under Section 37, as the appellant's challenge was confined to a specific amount and did not warrant interference. Costs were imposed on the appellant for the appeal.
Final Decision: The Court refused to interfere with the arbitral award, imposed costs of Rs. 50,000/- on the appellant, reduced to Rs. 25,000/- on undertaking to pay within four weeks, and ordered the release of the deposited amounts to the respondent.
JUDGMENT
Rajiv Sahai Endlaw, J. - This appeal, under Section 37 of the Arbitration and Conciliation Act 1996, impugns the judgment dated 5th December, 2020 of the Commercial Court - 02, Patiala House Court, New Delhi of dismissal of OMP (COMM) 60/2019 under Section 34 of the Arbitration Act, preferred by the appellant with respect to the arbitral award dated 17th December, 2018, of payment of Rs. 24,75,000/- with interest, by the appellant to the respondent.
2. The appeal came up before a Single Judge of this Court on 16th December, 2020, but after several adjournments, was ordered to be placed before the Commercial Appellate Division Bench, which alone under Section 13(1A) of the Commercial Courts Act, 2015 is authorised to hear the appeal. The appeal accordingly came up before a Bench comprising of one of us (Rajiv Sahai Endlaw, J.) sitting with Justice Sanjeev Narula, on 1st February, 2021 when, though notice of the appeal had not been issued till then, but the counsel for the respondent appeared on advance notice.
3. On 1st February, 2021, on enquiry, whether the appellant had deposited the arbitral award amount, this Court was informed that only 25% of the amount had been deposited. While listing the appeal for today for hearing on admission, the appellant was directed to deposit the entire arbitral amount awarded, in the Execution Court, and we are today informed that the entire arbitral award amount has been deposited in the Execution Court. We have heard the counsel for the appellant and the counsel for the respondent appearing on advance notice.
4. The parties entered into an agreement dated 22nd March, 2016, whereunder the respondent agreed to provide advisory services to the appellant for preparation and sanction of a financing package. As per the terms and conditions of the agreement, (i) the appellant agreed to pay nonrefundable engagement fee of Rs. 1,00,000/- to the respondent and which was adjustable against the fee payable at the final milestone; (ii) the appellant further agreed to pay 0.75% of the quantum of working capital facility arranged by the respondent for the appellant, with 25% of the fee amount being payable on receipt of sanction letters and the remaining 75% being payable at the time of first disbursement of the working capital; (iii) if due to any reasons the appellant decided not to proceed with the sanctions or does not involve the respondent in the completion of balance activities , the respondent was nevertheless entitled for the entire success fee; (iv) the clause in the agreement regarding payment of professional fee was to remain valid for a period of four months from the date of signing of the agreement and during which time the respondent was to act as exclusive financial advisor to the appellant; (v) the appellant agreed not to approach directly or indirectly the investors/institutions/bankers or any other parties introduced to it by the respondent, from the date of acceptance of such contract and until a period of 12 months after the expiry of the contract; (vi) the professional fee/expenses were to be paid by the appellant to the respondent within 7 days of respondent raising an invoice; (vii) if at any stage the appellant decided not to go ahead with the project/transaction or defer or abandon the project/transaction, the amount due to the respondent up to that stage was agreed to be paid; and, (viii) in case of early termination, respondent was to remain entitled to receive payment from the appellant for the services performed up to the date of such termination.
5. Besides the aforesaid commercial clauses, the parties also agreed as under:-
"All disputes or differences between the parties arising out of or in connection with execution of the assignment shall be attempted to be settled through mutual negotiation. In the event of such differences or disputes are not settled through mutual negotiations, the differences/disputes shall be referred to arbitration. The arbitration shall be con
Jhang Cooperative Group Housing Society Ltd. vs. PT. Munshi Ram and Associates Pvt. Ltd
Shree Vinayak Cement Clearing Agency vs. Cement Corporation of India
South East Asia Marine Engineering and Constructions Limited vs. Oil India Limited
The judgment emphasizes the limited scope of interference under Section 37 of the Arbitration Act, highlighting the importance of abiding by arbitral awards and the need for commercial parties to hon....
The courts have a limited scope of interference under Section 34 and 37 of the Arbitration Act, and the Arbitral Tribunal's detailed consideration of evidence and claims is final.
The court emphasized that arbitral awards should not be interfered with solely based on disagreements with findings, affirming the limited grounds for appeal under Section 34 of the Arbitration Act.
The court confirmed that judicial interference in arbitral awards is limited to cases of patent illegality or perverse findings, respecting the finality of arbitration.
Point of law: Arbitration Award - It must clearly be understood that when a court is applying the "public policy" test to an arbitration award, it does not act as a court of appeal and consequently e....
The judgment emphasizes the narrow scope of interference with an arbitral award and the principle of waiver in raising new grounds on appeal.
The main legal point established in the judgment is the limited scope of interference under Section 37 of the Arbitration and Conciliation Act, 1996, and the importance of interpreting the contract a....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.