IN THE HIGH COURT OF DELHI AT NEW DELHI
Manmohan, Asha Menon, JJ.
North Delhi Municipal Corporation - Appellant
Versus
M/s Garg Construction Co - Respondent
RFA (Comm) No. 5 of 2021; C.M. Appls No. 10181 of 2021, 10184 of 2021
Decided On : 15-03-2021
Payment Dispute - Contractual Payment Terms - [CPC, Contract Act] - The court discussed the validity of clauses 7 and 9 of the work orders, emphasizing the requirement for reasonable time for payment and the illegality of clauses that postpone consideration indefinitely. The court held that the clauses were unreasonable and contrary to law, and should be read in a manner to instill reasonableness. The court also noted the appellant's attempt to neutralize previous judgments by amending the clauses. The court found no reason to interfere with the impugned order and dismissed the appeal.
Fact of the Case:
The respondent-plaintiff completed work orders for the appellant but faced delayed payment. The appellant cited non-receipt of payment from the SDM/Delhi Government as the reason for non-payment. The respondent-plaintiff filed a suit for recovery, and the appellant contested, citing contractual terms.
Finding of the Court:
The court found that the clauses in the work orders were unreasonable and contrary to law, emphasizing the need for reasonable time for payment and the illegality of clauses that postpone consideration indefinitely. The court also noted the appellant's attempt to neutralize previous judgments by amending the clauses.
Issues: Validity of clauses 7 and 9 of the work orders, reasonableness of payment terms, and the appellant's attempt to neutralize previous judgments by amending the clauses.
Ratio Decidendi: The clauses in the work orders were found to be unreasonable and contrary to law, and should be read in a manner to instill reasonableness. The appellant's attempt to neutralize previous judgments by amending the clauses was noted.
Final Decision: The court found no reason to interfere with the impugned order and dismissed the appeal.
JUDGMENT
Manmohan, J. - Present appeal has been filed challenging order dated 7th January, 2021 passed by learned District Judge (Commercial court-05), Central Delhi, Tis Hazari in CS(COMM) 684/2020, whereby the respondent's application under Order XII Rule 6 has been allowed and the suit has been decreed against the appellant.
2. Briefly stated, the facts of the present case are that respondentPlaintiff was awarded two work orders both dated 1/4/2016 and it completed the same within stipulated time, to the satisfaction of the appellant. The final bills for both work orders amounting to Rs. 9,95,681/- were approved by the appellant. However, the payment was not released within prescribed time. Thereafter, the respondent-plaintiff sent a legal notice to the appellant to which the appellant replied stating that the payments would be made after the amount is released by the SDM/Delhi Government. The respondent-plaintiff then filed the suit for recovery before the District Court.
3. Appellant contested the suit and admitted its liability to pay the amount of passed bills but stated that work orders were placed at the request of SDM/Delhi Govt. and due to non receipt of payment from them, the payment to the respondent-plaintiff could not be released. During the pendency of the suit, respondent-plaintiff had made an offer to the appellant to pay the principal amount by 31st December, 2020 upon which the interest and costs would be waived off. However, the appellant refused the said offer and filed an application under Order VII Rule 11. Subsequently, the respondent-plaintiff filed an application under Order XII Rule 6 in which the impugned order has been passed.
4. Learned senior counsel for the appellant submits that learned District Judge failed to appreciate that the relief sought for by the respondent under the garb of application under Order XII Rule 6 CPC was beyond the scope of the terms and conditions of the contract.
5. He states that learned District Judge failed to appreciate that the work orders were placed at the request of SDM/Delhi Government and due to non-receipt of payment from them, the payment to the contractor cannot be released.
6. He further states that there was a condition in the NIT that the payment of the Bills will depend upon availability of funds in a particular head of account and even the payments will be made on queue basis i.e. first and past liabilities to be given priorities and after those clearance, the payment to the contractor will be released after the demand of the bills is received from the concerned SDM and that no interest shall be paid on the bill amount.
7. He emphasizes that there are judgments passed by the learned Single Judge of this Court wherein the queue basis payment had been approved. In support of his contention, he relies upon the judgments of the learned Single Judges in RFA 786/2016, RFA 818/2017 and RFA 835/2017. According to him, these judgments take a contrary view to the one taken in RFA 160/2017 decided on 22nd March, 2018 by a different learned Single Judge of this Court.
8. This Court is of the view that the present appeal is liable to be dismissed inasmuch as a learned Single Judge of this Court in 'North Delhi Municipal Corporation Vs. Vipin Gupta' RFA 160/2017 has dealt with all the grounds urged herein and the same are no longer res integra. It is relevant to point out that the appellant herein had preferred an SLP against the aforesaid order of the learned Single Judge, which came to be dismissed vide order dated 03rd January, 2019.
9. The learned Judge in North Delhi Municipal Corporation Vs. Vipin Gupta (supra) was dealing with a batch of appeals passed in similar suits wherein the appellant-corporations were relying on clause 7 and clause 9 to delay payment to contractors who had executed the work as per their respective work orders. The relevant portion of the judgment dated 22nd March, 2018 in RFA 160/2017 is reproduced hereinbelow:-
"Conclusions and Findings
"56. Th
The judgment established the requirement for reasonable time for payment and the illegality of clauses that postpone consideration indefinitely.
The main legal point established in the judgment is that contractual clauses must be reasonable and not unconscionable, and contractors should be paid within a reasonable time as per Section 46 of th....
Payment terms in contracts must include reasonable timelines; indefinite delays render contractual clauses illegal and against public policy.
Indefinite payment conditions in contracts are unreasonable and violate the principle of contractual consideration, requiring clarity and a specified timeline.
The plaintiff was entitled to receive the payment for the work done and the defendants could not deny interest on delayed payments based on Clause 9 of the NIT.
The court upheld that delayed payments must be compensated with interest, emphasizing that the appellants’ claims of irregularities were unsubstantiated and did not impede the contractors' right to r....
The contractor is entitled to interest on delayed payments even when contract clauses suggest payment depends on fund availability; unreasonable delays cannot negate interest obligations.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.