IN THE HIGH COURT OF DELHI AT NEW DELHI
Sanjeev Sachdeva, J.
North Delhi Municipal Corporation - Appellant
Versus
IJM Corporation Berhad - Respondent
O.M.P. (Comm) 185 of 2022, I.A. 5905 of 2022 and I.A. 5906 of 2022
Decided On : 26-04-2022
Arbitration and Conciliation Act 1996 - Extension of Time - Clause 2, Clause 5.2, Clause 5.3, Clause 5.4
Fact of the Case:
The petitioner challenges the award rendered by the Arbitral Tribunal, which decided in favor of the respondent regarding the extension of time and imposition of liquidated damages for delay in a construction contract.
Finding of the Court:
The court found that the extension of time granted was not provisional and could not be retrospectively curtailed by the petitioner. The court upheld the Arbitral Tribunal's decision on issue no.3, stating that only two options were available to the competent authority regarding the extension of time.
Issues: The issues involved the interpretation of the clauses related to extension of time and imposition of liquidated damages in the construction contract.
Ratio Decidendi: The court held that once an extension of time is granted, it cannot be retrospectively reduced by the competent authority. The court also found that the issues no.3 and no.5 could be decided separately, and the decision on issue no.3 did not pre-judge issue no.5.
Final Decision: The petition was dismissed, and the Arbitral Tribunal was directed to decide the remaining issues without being influenced by the court's decision on merits.
JUDGMENT
Sanjeev Sachdeva, J. (Oral). - The petitioner by this application under Section 34 of the Arbitration and Conciliation Act 1996, impugns the award dated 03.07.2021 rendered by the Arbitral Tribunal deciding Issue no.3 in favour of the respondent and against the petitioner.
2. Issue no. 3 as framed reads as under:-
'Issue No. 3
Whether the action of the Respondent/PMC in granting provisional extension of time is in conformity with the terms of the agreement?'
3. Learned Senior Counsel appearing for the petitioner submits that issue no.3 is intrinsically connected with issue no. 5 and the Arbitral Tribunal has erred in deciding issue no.3 in isolation.
4. Issue no.5 as framed reads as under:
'Issue No. 5
'Whether the actions of the Respondent/PMC in imposing liquidated damages/compensation for delay with retrospective effect is inconformity with the terms of the agreement?'
5. Learned Senior Counsel for the petitioner further contends that the Arbitral Tribunal has erred in rejecting the contention of the petitioner that the extension of the time granted was only provisional and petitioner had reserved its rights to impose liquidated damages at the end of the work.
6. Learned Senior Counsel for the petitioner further submits that the extension of time granted was only provisional and on the conclusion of the contract, petitioners were entitled to assess the exact number of days of delay and accordingly levy compensation for the delayed period.
7. Per contra, learned Senior Counsel appearing for the respondent contends that the extension of the time was not provisional and can never be provisional and once extension of time is granted same cannot be curtailed specially after the extended period is over.
8. For purposes of determining the controversy, brief reference to the factual matrix would be required. Petitioner had awarded the subject contract to the respondent for construction of Civic Centre at JLN Marg, Minto Road, Delhi vide agreement dated 21.05.2005.
9. It is not in dispute that there were certain events which led to the delay in the execution of the contract. Respondent Contractor applied for extension of time on several occasions, which were granted.
10. Petitioner granted the requests in each case upto a specified date, however, also mentioned that it was without prejudice to the rights of the petitioner to recover liquidated damages in accordance with the provision of Clause 2 of the agreement.
11. The contention of the respondent is that the work was completed within the stipulated period of the contract by including the extended periods as sanctioned by the petitioner and the work did not extend beyond the extensions granted by the petitioner.
12. The contention of the petitioner before the Arbitral Tribunal and even before this court is that at the conclusion of the work it was open to the petitioner to re-assess the extensions granted and determine as to whether the extensions granted were correct or not and also that the number of days could be reduced.
13. In the present case, petitioner has after the conclusion of the work and after the period stipulated by the contract and the extended periods as sanctioned, have expired, re-assessed the number of days of delay and reduced the extended period and levied compensation of liquidated damages.
14. Clause 2 refers to compensation for delay in completion of the work and reads as under:
'CLAUSE 2 Compensation for Delay
If the contractor fails to maintain the required progress in terms of Clause 5 or to complete the work and clear the site on or before the contract or extended date of completion, he shall, without prejudice to any other right or remedy available under the law to the MCD on account of such breach, pay as agreed compensation the amount calculated at the rates stipulated below as the Engineer-in-Charge (whose decision in writing shall be final and binding) may decide on the amount of tendered value of the work for every completed day/month (as applicab
The main legal point established is that once an extension of time is granted, it cannot be retrospectively curtailed, and the interpretation of contract clauses is crucial in determining the rights ....
Once an extension of time is granted in a contractual relationship, it cannot be retroactively reassessed to the detriment of the contractor after the expiration of the extended period.
An arbitrator may award escalated costs due to employer delay despite prohibitory clauses, reinforcing that delays affecting contractor performance can lead to compensatory claims.
Interference in arbitral awards under Section 34 is limited; courts must respect arbitrators' determinations unless found perverse or unjustifiable.
The interpretation of the contract is within the exclusive domain of the learned Arbitrator, and the court would not interfere with such interpretation.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.