SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Del) 81

IN THE HIGH COURT OF DELHI AT NEW DELHI
AMIT BANSAL, J.
Ircon International Ltd. – Petitioner
Versus
AFCONS Infrastructure Ltd. – Respondent
O.M.P. (COMM) 279 of 2019
Decided On : 13-02-2026

Advocates Appeared:
For the Petitioner:Mr. Gaurav Pachnanda, Senior Advocate with Mr. Siddhant Goel, Mr. Mohit Goel, Mr. Karmanaya Dev Sharma, Ms. Aishna Jain and Mr. Shashwat, Advocates.
For the Respondent:Mr. Manu Sheshadri, Mr. Sahil Manganani, Ms. Prachi Jain and Mr. Siddharth Shekhar, Advocates.

Interference in arbitral awards under Section 34 is limited; courts must respect arbitrators' determinations unless found perverse or unjustifiable.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Challenge to arbitral award - Claimant granted extension of 484 days due to delays not attributable to it - Imposition of liquidated damages deemed illegal as per contract terms - Contractual provisions regarding delays and extensions upheld - Court rejects the interference with the award by the claimant. (Paras 1-56)

(B) Scope of judicial interference - Court does not sit as an appellate forum to re-evaluate evidence or findings of the tribunal - Award upheld unless found perverse or based on no evidence. (Paras 15-40)

Facts of the case:
Respondent challenged the arbitral award favoring the claimant in a construction dispute involving substantial delays in completion of the project attributed to geological issues, inclement weather, and law and order problems. Claimant sought time extensions and contested the imposition of liquidated damages while the tribunal granted significant time extensions and ruled the damages as improper. \n

Findings of Court:
The award was supported by evidence and the rationale provided was sufficient to uphold the determination of entitlement for extension and reject liquidated damages. \n

Issues: Key issues included attribution of delay, legality of liquidated damages, and whether the tribunal's decisions were perverse. \n

Ratio Decidendi: The court recognized the tribunal's findings on the critical path of project completion and properly analyzed the delays while refusing to substitute its judgment for that of the tribunal. It was ruled that the imposition of liquidated damages violated contract provisions. \n

Result: Petition dismissed.

Table of Content
1. outline of case and parties involved (Para 1 , 2)
2. details of the project and contract terms (Para 3 , 4 , 5)
3. history of disputes and arbitration process (Para 6 , 7 , 8 , 9 , 10)
4. submissions of ircon regarding contract interpretation (Para 12)
5. afcons response and justification on extensions (Para 13)
6. affirmation of limited court intervention in arbitration (Para 14 , 15 , 16)
7. assessment of the contract and extension requests (Para 18 , 19 , 20)
8. interpretation of the contractual obligations by the court (Para 21 , 22 , 23)
9. evaluation of delay claims and extensions (Para 24 , 25 , 26)
10. verification of arbitrator's reasoning and findings (Para 27 , 28 , 29 , 30)
11. guidance on evidence standard in arbitration (Para 31 , 32 , 33)
12. conditions under which liquidated damages can be applied (Para 34 , 35 , 36)
13. clarification on the court's limited scope of review (Para 38 , 38 , 39)
14. conclusion and final judgment on the case (Para 56 , 57)

JUDGMENT :

AMIT BANSAL, J.

1. The present petition has been filed under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter ‘Act’) on behalf of the respondent/ counter claimant in the arbitration proceedings challenging the Award dated 5th March 2019 (hereinafter ‘Impugned Award’) passed by the Arbitral Tribunal. The petitioner herein (respondent/ counter claimant in the arbitration proceedings) shall hereinafter be referred to as ‘IRCON’ and the respondent herein (claimant in the arbitration proceedings) shall hereinafter be referred to as ‘AFCONS’.

2. The Impugned Award was rendered while adjudicating the disputes between the parties arising out of a Contract dated 14th March 2014.

FACTUAL BACKGROUND

3. Brief facts leading to the present petition are as under:

3.1. IRCON is a leading government turnkey construction company in the public sector.

3.2. The Government of India planned a railway line for joining the Kashmir valley with the Indian Railways network. For the purpose of execution/ monitoring, the work was sub-divided into four parts, out of which execution of the Katra – Banihal (111 km) tunnel was divided among three agencies in the following manner:

- Northern Railway (5 km)

- KRCL (35 km)

- IRCON (71 km)

3.3. Accordingly, IRCON, on 25th July 2013, invited bids for participation in tenders for construction of Tunnel T-74R balance work from ADIT between km 127/660 to km 130/950 (length 3290 meters) on Dharam- Qazigund section of Udhampur-Srinagar-Baramulla New BG Railway Line project (Package T-74R-A) (hereinafter ‘Project’).

3.4. The Project was divided into five parts – construction of ADIT (585 meters), main tunnel Banihal (1940 meters), main tunnel Katra (1350 meters), escape tunnel Banihal (1940 meters) and escape tunnel Katra (1350 meters).

3.5. The Project was required to be completed within thirty-three months from the date of issuance of letter of acceptance and the milestones in the form of ‘key dates’ indicated in Appendix-XV to Instruction to Tenderer(s) (hereinafter ‘key dates’/ ‘KD’) were to be duly achieved.

3.6. The tender documents disclosed the geological and other problems which could be faced by the Contractor and detailed the provisions for requisite compensation with respect to the same.

3.7. Subsequently, IRCON issued Corrigendum no.1 to the tender documents dated 7th August 2013 modifying certain functional requirements as provided in Special Conditions of Contract – Section IIA, which was duly accepted and signed by AFCONS.

3.8. AFCONS, on 13th September 2013, offered its bid for the Project.

3.9. IRCON, vide its letter dated 25th October 2013, sought confirmation from AFCONS with respect to adherence to tender stipulated rate of progress.

3.10. AFCONS, vide its letter dated 29th October 2013, submitted progress rate and time cycle for different rock classes anticipated. The said progress rate and time cycle calculation in the said letter were not in consonance with the stipulated period of completion of the Project provid

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top