IN THE HIGH COURT OF DELHI AT NEW DELHI
Suresh Kumar Kait, J.
M/s Ashutosh Builders Contractors And Engineers - Appellant
Versus
Union Of India & Ors. - Respondents
Arbitration Petition No. 107 of 2022
Decided On : 16-02-2022
Arbitration - Appointment of Arbitrator - Disputes between Contractor and Union of India - The court allowed the petition under Section 11(6) of the Arbitration and Conciliation Act, 1996 and appointed a sole arbitrator to adjudicate the dispute between the parties.
Fact of the Case:
The petitioner, a contractor, entered into a contract agreement with Union of India for construction work. Disputes arose regarding approval of samples, payment release, and completion certificate. The petitioner sought appointment of an arbitrator after the respondent failed to reply to a legal notice.
Finding of the Court:
The court found that the claims raised in the petition were disputed but conceded that the disputes were arbitrable. The court appointed a sole arbitrator to adjudicate the dispute between the parties.
Issues: Appointment of Arbitrator, Disputes between Contractor and Union of India, Compliance with Arbitration and Conciliation Act, 1996
Ratio Decidendi: The court analyzed the disputed claims and the arbitrability of the disputes. It relied on Section 11(6) of the Arbitration and Conciliation Act, 1996 to appoint a sole arbitrator to adjudicate the dispute.
Final Decision: The court allowed the petition and appointed Mr. Ramesh Chander as the sole arbitrator to adjudicate the dispute between the parties. The fee of the arbitrator shall be governed by the Fourth Schedule of the Arbitration and Conciliation Act, 1996.
JUDGMENT
Suresh Kumar Kait, J. - The present petition has been filed by the petitioner under Section 11 (6) of the arbitration and Conciliation act, 1996 seeking appointment of arbitrator for adjudication of disputes with respondent.
2. Petitioner claims to be a contractor, carrying out various construction related activities. Respondent No.1 is Union of India, under the Ministry of Defence; respondents No. 2 to 4 are subordinate of respondent No.1. Respondent No.4 is also the accepting authority of the contract work awarded to the petitioner. For the work Ca No. GE/DW-67/2019-20, petitioner claims to have entered into a Contract agreement dated 12.10.2019 with the respondent, which contained arbitration Clause-70 in case of any disputes between the parties.
3. after execution of the aforesaid Contract agreement, petitioner claims to have sent samples for 13 items for approval by the respondent such like LED fitting, Cable-1.5 sqmm, 2.5 sqmm, socket, switch etc. on 25.10.2019. However, respondent vide its communication dated 13.06.2020 informed the petitioner that samples of 04 items were not sent and further issued a Show Cause Notice dated 31.07.2020 stating that despite lapse of 09 months, samples for approval have not been sent. Petitioner vide letters dated 07.08.2020 and 31.08.2020 sought extension of time due to Covid pandemic, which was granted on 16.10.2020. In the meanwhile, petitioner also raised bill vide letters dated 19.09.2020 and 14.10.2020, but the payment was not released by the respondent.
4. Further, petitioner claims to have sent a legal notice dated 24.10.2020 to the respondent seeking outstanding payment, extension of time and completion certificate, yet again respondent vide letter dated 07.05.2021 pressed for early completion of the work. Petitioner sent a legal notice dated 26.11.2021 to respondent seeking appointment of an arbitrator by the respondent, but the respondent failed to reply the same. Hence, the present petition.
5. Today, respondent is represented through counsel, who submits that the claims raised in the present petition are disputed, however, fairly conceded that the disputes inter se parties are arbitrable. Learned counsel also submitted that respondent has no objection if disputes are referred to an independent arbitrator appointed by this Court.
6. accordingly, the present petition is allowed and Mr. Ramesh Chander, Retd. Chief Engineer, Delhi Vidyut Board, (Mobile: 9818245606) is appointed the sole arbitrator to adjudicate the dispute between the parties.
7. The fee of the learned arbitrator shall be governed by the Fourth Schedule of the arbitration and Conciliation act, 1996.
8. The learned arbitrator shall ensure compliance of Section 12 of arbitration and Conciliation act, 1996 before commencing the arbitration.
9. The present petition and pending application, if any, are accordingly disposed of.
The main legal point established is the court's authority to appoint a sole arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996 to adjudicate disputes between parties.
Disputes under contracts with the Union of India are arbitrable, and the appointment of an independent arbitrator is necessary for their resolution under Section 11(6) of the Arbitration and Concilia....
The central legal point established in the judgment is the court's authority to appoint an arbitrator to resolve disputed claims between parties in accordance with Section 11(6) of the Arbitration an....
The court's power to appoint an arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996 and the arbitrability of disputes under the agreement's Clause 25.
The court applied the provisions of the Arbitration and Conciliation Act, 1996 to appoint a sole arbitrator and ensure compliance before commencing the arbitration.
The court affirmed that when parties acknowledge disputes in a contractual agreement, an arbitrator must be appointed to resolve these disputes under the Arbitration and Conciliation Act, 1996.
The court's decision emphasized the appointment of a sole Arbitrator to adjudicate disputes under the Arbitration and Conciliation Act, 1996.
The court has the authority to appoint a sole Arbitrator in accordance with the Arbitration Clause forming a part of the Contract.
The court has the authority to appoint an arbitrator to resolve disputes based on the arbitration clause in the agreement and the arbitrability of the disputes.
The court's decision emphasizes the validity of invoking arbitration in accordance with the arbitration clause of the work order and the importance of compliance with Section 12 of the Arbitration an....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.