IN THE HIGH COURT OF DELHI AT NEW DELHI
Suresh Kumar Kait, J.
Sap Electro Contracts (pvt) Ltd - Appellant
Versus
Reiyukai - Respondent
Arbitration Petition No. 34 of 2022
Decided On : 11-02-2022
Arbitration - Appointment of Sole Arbitrator - Disputes arising from termination of contract and non-payment of outstanding amount
Fact of the Case:
The petitioner sought the appointment of a sole arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996, due to disputes arising from the termination of a contract and non-payment of outstanding amounts by the respondent.
Finding of the Court:
The court found that the disputes between the parties were arbitrable and appointed an independent arbitrator to adjudicate the dispute.
Issues: Disputes arising from termination of contract, non-payment of outstanding amount, and appointment of sole arbitrator
Ratio Decidendi: The court's decision was influenced by the consent of both parties that the disputes were arbitrable and the appointment of an independent arbitrator was necessary to resolve the disputes.
Final Decision: The court allowed the petition and appointed Mr. R.K. Dhawan as the sole arbitrator to adjudicate the dispute between the parties.
JUDGMENT
Suresh Kumar Kait, J. - The present petition has been filed under Section 11 of the arbitration and Conciliation act, 1996 seeking appointment of sole arbitrator to adjudicate the disputes inter-se the parties.
2. according to petitioner, respondent was awarded the work order for Internal Electrical Works for Institutional Religious Building 'Eternal Oasis' for total amount of Rs.82,60,000/- inclusive of all taxes e.g. Labour Cess, WCT & GST as applicable on the basis of Schedule of Rates enclosed with the work order for supply, installation, testing and commissioning of Internal Electrical Works at the project site and a Contract agreement was signed with all terms and conditions including BOQ. Petitioner claims to have started the said work according to the specification as per BOQ and satisfaction of respondent's consulting Engineers/Project Managers and thereafter drawings were made final from respondent's side and mobilization advance received. Thereafter on 18.04.2018, respondent awarded new work order to the petitioner for supply, installation, testing and commissioning of High Side Electrical Works Institutional Religious Building 'Eternal Oasis' for total amount of Rs.44,25,000/- exclusive of GST and Labour Cess and contract agreement was also signed with all terms and conditions including BOQ. again, petitioner started the said work according to the specification as per BOQ and satisfaction of respondent's consulting Engineers/Project Managers and thereafter drawings were made final from respondent's side and mobilization advance received. after the start of work, respondent started providing fresh drawings for those work which was already completed and directed the petitioner to dismantle everything and again carry out the work order according to the new drawings. Petitioner did so for which respondent paid extra to the petitioner. Petitioner raised the running bills for both the work order and paid the GST as per applicable rate and respondent certified the payment and released part payments.
3. Suddenly, on 20.05.2021, respondent terminated the contract in violation of the terms and conditions of the GCC clause and work order. Petitioner contacted the respondent and demanded the payment of outstanding amount, however, respondent refused to pay the same. Subsequently, various disputes arose between the parties regarding illegal termination of the contract/work orders and non-payments of outstanding against the certified invoices/bills.
4. During the course of arguments, learned counsel for the petitioner submitted that petitioner sent a letter to respondent on 18.10.2021 requesting to settle the disputes and differences amicably as per clause 52 of GCC but of no avail. Thereafter, petitioner sent a legal notice dated 02.11.2021 and invoked the arbitration in terms of clause 52.1 of GCC and called upon the respondent to file application under Section 11 of the arbitration and Conciliation act, 1996 before this Court for appointment of sole arbitrator. However, respondent neither replied nor filed any application. Hence, the present petition has been filed.
5. During the course of hearing, learned counsel appearing on behalf of the respondent has not opposed the present petition and submitted that the claims raised in the present petition are disputed, however, fairly conceded that the disputes inter se parties are arbitrable. Learned counsel also submitted that respondent has no objection if disputes are referred to an independent arbitrator appointed by this Court.
6. Since counsel representing both the sides have consented that the disputes are arbitrable and an independent arbitrator be appointed by this Court, the present petition is allowed.
7. accordingly, Mr. R.K. Dhawan, advocate (Mobile: 9899775330) is appointed as the sole arbitrator to adjudicate the dispute between the parties.
8. The fee of the learned arbitrator shall be governed by the Fourth Schedule of the arbitration and Conciliation act, 1996
Court can appoint an arbitrator when both parties consent to arbitration for resolving disputes, even amidst contractual disagreements.
The court's decision highlights the importance of honoring arbitration clauses in agreements and the appointment of arbitrators to resolve disputes.
Unilateral appointment of an arbitrator is impermissible; parties must appoint an arbitrator jointly or seek court appointment to ensure unbiased dispute resolution.
Non-compliance by a party allows the court to appoint a sole Arbitrator under the Arbitration Act when arbitration notices are ignored.
The main legal point established in the judgment is the court's authority to appoint an independent arbitrator for adjudication of disputes based on the arbitration agreement.
No single party can be permitted to unilaterally appoint the Arbitrator, as it would defeat the purpose of unbiased adjudication of dispute between parties.
The court's decision emphasizes the validity of invoking arbitration in accordance with the arbitration clause of the work order and the importance of compliance with Section 12 of the Arbitration an....
The court's authority to appoint an arbitrator in cases where the parties are unable to agree, in accordance with the law laid down by the Supreme Court and the provisions of the Arbitration & Concil....
The court's decision emphasized the appointment of a sole Arbitrator to adjudicate disputes under the Arbitration and Conciliation Act, 1996.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.