SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Suresh Kumar Kait, J.
Third Wave Services - Appellant
Versus
Selene Constructions Limited - Respondent
Arb.P. 967 of 2021
Decided On : 23-11-2021




Unilateral appointment of an arbitrator is impermissible; parties must appoint an arbitrator jointly or seek court appointment to ensure unbiased dispute resolution.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 11(6) - Appointment of a Sole Arbitrator - Petition filed for appointment of an arbitrator as the respondent unilaterally appointed its arbitrator, which the court finds impermissible to ensure unbiased adjudication. (Paras 1, 7, 9)

(B) Judicial Appointment of Arbitrator - Court emphasizes that the appointment of an arbitrator must be with consensus of both parties or by the court; unilateral appointment violates principles of fair adjudication as established in prior case law. (Paras 10, 11)

Facts of the case:
The petitioner, engaged in infrastructure services, executed a work order amounting to over Rs.9 crores, faced delays, and sought arbitration due to unpaid dues and unilateral actions by the respondent.

Findings of Court:
This Court found that disputes need to be adjudicated by an appointed arbitrator, not by one party unilaterally.

Issues: The court addressed whether unilateral appointment of an arbitrator was permissible and confirmed that disputes must be resolved equitably.

Ratio Decidendi: The court concluded that unilateral appointments undermine fair dispute resolution, requiring arbitration through a mutually agreed or court-appointed arbitrator.

Result: Petition allowed; arbitrator appointed.

JUDGMENT (Oral)

1. The present petition has been filed by petitioner seeking appointment of a Sole Arbitrator under the provisions of Section 11(6) of the Arbitration and Conciliation Act, 1996.

2. Petitioner, a private limited company, claims to be registered under the Micro Small and Medium Enterprises Development (MSMED) Act, 2006, claims to be engaged in the diverse businesses pertaining to providing permanent Civil, electrical and Mechanical infrastructure.

3. According to petitioner, respondent No.1 is a public limited company engaged in real estate activities, who develops offices, housing, hotels and othr industrial projects. Respondent No.2 is also engaged in real estate development services.

4. Petitioner claims to have received a work order No. 3228105854 dated 12.07.2013 for work of internal electrical works of Building G1,2,3, K1,2,3, B & EWS at Centrum Park, Phase-ll, Gurgaon from respondent No.2 (as a sub-contractor) for a contractual amount of Rs.8,76,05,494.61/-, which was later enhanced to Rs.9,16,24,074.35/-. It is further claimed that the work was to commence on 01.07.2013 and the stipulated time for completion of work was 12 months i.e. till 30.06.2014. However, due to late handing over of site by respondent No.2, the work period had to be extended time to time i.e. from 31.03.2016 till 31.03.2017. Also, the work order was amended and enhanced on 07.06.2017 to Rs.9,33,18,103.05/-.

5. At the hearing, learned counsel for petitioner has submitted that due to implementation of the Goods and Services Tax Laws, the terms and conditions of work had to be reassessed and revised vide post GSI Work Order No. 0330110049 and under the amended contract, respondent No.1 became the employer and petitioner the contactor, instead of respondent No.2. Further submits that owing to failure on the part of respondents in adhering to the terms and conditions of the agreement, the work was delayed and time ceased to be essence of the contract and therefore, work to the tune of Rs.2,96,52,939.32, as against the awarded value of Rs.9,18,72,965.59, could be executed by the petitioner.

6. It is further submitted by learned counsel that respondent vide its email dated 22.03.2018, admitted the claim of petitioner, however, respondent has agreed to pay only Rs.70,00,000/-, whereas in the `completion certificate' issued by respondent No.1, the work executed by petitioner has been mentioned as "good". It is also averred on behalf of petitioner, that against the final bill dated 05.04.2019 amounting to Rs.1,32,50,052.21, respondent No.1 approved amount of Rs.1,05,94,359.07 and out of the said amount too, amount of Rs.56,70,074.00 only was released to petitioner till 14.02.2020 and out of the remaining amount of Rs.49,24,285.07, further amount of Rs.11,83,311/- was released by respondent No.1, leaving the balance amount of Rs.37,40,974.07 still unpaid.

7. Petitioner claims to have sent various e-mails to the respondent No.1 for clearance of outstanding dues, however, upon failure to make the payment, petitioner invoked arbitration vide notice dated 10.06.2021. In response to the aforesaid notice dated 26.06.2021, respondent unilaterally appointed its Arbitrator, which is impermissible in law and hence, the present petition has been filed.

8. To the contrary, learned counsel appearing on behalf of respondents has opposed the present petition while submitting that the claims raised by the petitioner in the present petition are frivolous and this petition deserves to be dismissed. However, learned counsel has not disputed invocation of arbitration vide Notice dated 10.06.2021 and also that any dispute inter se parties have to be resolved in terms of Clause-37(b) of the amended post GST Work Order No. 330110049.

9. Upon hearing learned counsel appearing from both the sides this Court finds that disputes between the parties are required to be adjudicated by an Arbitrator in terms of Clause-37(b) of the amended post GST Work Ord

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top