IN THE HIGH COURT OF DELHI AT NEW DELHI
CHANDRA DHARI SINGH, J.
METCON INDIA REALTY AND INFRASTRUCTURE PVT. LTD. – Petitioner
Versus
DELHI METRO RAIL CORPORATION LTD. – Respondent
ARB. PET. No. 1140 of 2022
Decided On : 02-02-2023
Arbitration and Conciliation Act, 1996 – Section 11(6) – Indian Contract Act, 1872 – Section 28 – Planning and implementation of metro rail – Pertaining to construction of viaduct – Letter of Acceptance – Notice of dispute – Petition has been filed by Petitioner seeking appointment of an independent Arbitral Tribunal under Section 11(6) of Arbitration and Conciliation Act, 1996 and has inter-alia prayed for reliefs – Held, Petitioner has alleged that they were asked to submit a blanket NOC to not claim anything against extra work done by them – Additionally, as per Petitioner’s claim, it had also submitted a fresh No Claims Declaration and Respondent did not respond to same – All of these claims cannot be adjudicated by this court at this stage – Court, without going into merits of case, is prima facie of view that there is an arbitrable dispute between parties and same must be adjudicated by Arbitral tribunal which would be competent authority as per kompetenz-kompetenz principle, including on issue pertaining to whether No Claims Declaration was obtained under coercion or duress, and whether present claim is merely an afterthought – Hence, in light of foregoing discussion and analysis, Court is of opinion that if there is an arbitration agreement between parties, which is sought to be negated by a party by citing other provisions of a contract, which requires interpretation of contract, then Court, in line with letter and spirit of Act as well as doctrine of kompetenz-kompetenz, must lean towards referring matter to arbitration – Facts and circumstances of case, Court refers dispute raised herein to an Arbitral Tribunal – Petition allowed.
JUDGMENT :
CHANDRA DHARI SINGH, J.
1. The instant petition has been filed by the Petitioner seeking the appointment of an independent Arbitral Tribunal under Section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Act”) and has inter-alia prayed for the following reliefs:
(b) Pass such other or further orders as this Hon’ble Court may deem fit and proper in the facts and circumstances of the case.”
FACTUAL MATRIX
2. The Petitioner is a firm engaged in civil contracting, land and property development, and real estate sectors. The Respondent is a Centre-State Joint Venture responsible for operating the Delhi Metro and the scope of its work involves planning and implementation of metro rail, monorail, and high-speed rail projects in India and abroad.
3. The Petitioner, on 08.09.2015, submitted its bid for Contract CC-95, pertaining to the construction of the viaduct, and roof portal along with finishing the work for the automatic walk-a-way/travelators at Dhaula Kuan and Rajouri Garden Interchange Stations of Line-7, Phase III of the Delhi MTRS.
4. Subsequently, in pursuance of the submitted bid, the Respondent on 11.01.2016 issued a Letter of Acceptance (hereinafter referred to as the “LOA”) to the Petitioner for the said contract at a total cost of Rs. 55,07,87,249/-. Furthermore, the LOA stipulated the timeline for the competition of the work which was 15 months commencing from 1st February 2016.
5. The Petitioner’s contention is that the Respondent had added extra work and had changed the scope of work provided for by the contract, and the same was undertaken by them on the Respondent’s assurance that due payments will be made for the extra work. The Petitioner further submits that while it had duly executed all the work and raised timely bills, the same was not honoured by the Respondents, despite their prior understanding on the same.
6. The Petitioner invoked arbitration by its notice dated 09.06.2022 whereby the Petitioner had inter-alia sought the payment of claim amount of Rs. 55,50,91,763.36 including interest for the extra items/extra work done by the Petitioner and has accordingly, sought to refer the dispute to arbitration. However, the Respondent rejected the same on the ground that the Petitioner’s notice had exceeded the prescribed time limit under Clause 17.4 of the GCC.
7. The Respondent further stated in its notice that the Petitioner had submitted the No Claims Declaration dated 19.03.2021, as per which once the final payment under the contract is released, then the contractual agreement including the arbitration clause would be instantly discharged and rescinded. However, it is contested by the Petitioner that the No Claims Declaration had been obtained by the Respondent under economic duress and coercion by refusing to release any payment which was due to the Petitioner, and thus, the No Claim Declaration should be rejected by the court.
8. The Petitioner has preferred this instant petition under Section 11(6) of the Act pertaining to the dispute regarding extra work that was assigned to the Petitioner.
SUBMISSIONS
(ON BEHALF OF THE PETITIONER)
9. Learned counsel appearing on behalf of the Petitioner submitted that the Respondent had added extra work items and had changed the scope of the work from time to time, and the Petitioner duly completed the extra work on the Respondent’s assurance that they will make due payments for the same. It is submitted that the Petitioner had executed the extra work and had apprised the Respondent and raised bills for the extra work in a timely manner, however the same was not honoured by the Respondent and hence a due amount of Rs. 55,50,91,763.36 has arisen.
10. It is further submitted that the Respondents were intentionally avoiding the same to unjustly enrichen themselves, despite the prior
BSNL vs. Telephone Cables Ltd. (2010) 5 SCC 213 : (2010) 2 SCC (Civ) 352
BSNL vs. Nortel Networks (India) (P) Ltd. (2021) 5 SCC 738
Dresser Rand S.A. vs. Bindal Agro Chem Ltd. (2006) 1 SCC 751
Grasim Industries Ltd. vs. State of Kerala
Mayavati Trading (P) Ltd. vs. Pradyuat Deb Burman
National Agricultural Coop. Marketing Federation India Ltd. vs. Gains Trading Ltd. (2007) 5 SCC 692
National Insurance Co. Ltd. vs. Boghara Polyfab (P) Ltd. (2009) 1 SCC 267 : (2009) 1 SCC (Civ) 117
Naihati Jute Mills Ltd. vs. Khyaliram Jagannath
N.N. Global Mercantile (P) Ltd. vs. Indo Unique Flame Ltd. (2021) 4 SCC 379
PSA Mumbai Investments Pvt. Ltd. vs. Jawaharlal Nehru Port Trust
SBP & Co. vs. Patel Engg. Ltd. (2005) 8 SCC 618
Tarapore and Co. vs. Cochin Shipyard Ltd. (1984) 2 SCC 680
Union of India vs. Kishorilal Gupta and Bros. AIR 1959 SC 13
Union of India vs. Master Construction Co. (2011) 12 SCC 349 : (2012) 2 SCC (Civ) 582
Uttarakhand Purv Sainik Kalyan Nigam Limited vs. Northern Coal Field Limited
Visakha Petroleum Products Pvt. vs. B.L. Bansal (1997) 4 SCC 366
The arbitration agreement is separate and severable from the underlying contract, and the Arbitral Tribunal has the competence to rule on its own jurisdiction, including the existence or validity of ....
The court upheld the Doctrine of Severability and Kompetenz-Kompetenz principle, affirming the independence of the arbitration clause from the main contract and the competence of the arbitral tribuna....
The claims were notified within the stipulated period and submitted along with the final bill in accordance with Clause 6.6.3.0 of the GCC, making the disputes arbitrable under Clause 9.1.0.0.
The Court emphasized the importance of examining the existence and validity of an arbitration agreement at the referral stage and the rejection of manifestly non-arbitrable claims.
(1) Arbitration – Parties to arbitration agreement have autonomy to decide not only on procedural law to be followed but also substantive law – A party cannot claim anything more than what is covered....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.