SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Del) 1974

IN THE HIGH COURT OF DELHI
Amit Bansal, J.
Mehra Jewel Palace Pvt. Ltd. - Appellant
Versus
Miniso Life Style Pvt. Ltd. - Respondent
CS(COMM) 376 of 2020 & I.A. No. 8044 of 2020 (u of O-XVA CPC), I.A. No. 12139 of 2020 (for modification), I.A. No. 12216 of 2021 (u of O-XXXVIII R-1 & 5 CPC), I.A. No. 14659 of 2021 (for directions), I.A. No. 182 of 2022 (u of S 151 CPC)
Decided On : 25-05-2022

The court held that the COVID-19 pandemic constituted a force majeure event under the Lease Deed and that the defendants were entitled to the benefit of the force majeure clause insofar as payment of rent for the months of April and May 2020 was concerned. However, the court also held that the force majeure clause could not inure to the sole benefit of the lessee alone and that both the plaintiff and the defendants should equally bear the impact of the COVID-19 pandemic.

Headnote:

FORCE MAJEURE - LEASE DEED - COVID-19 PANDEMIC - RENT WAIVER - INTERPRETATION OF FORCE MAJEURE CLAUSE - SECTION 32 OF THE INDIAN CONTRACT ACT, 1872 - SECTION 56 OF THE INDIAN CONTRACT ACT, 1872 - SUMMARY JUDGMENT - INTEREST - GST - PENALTY - SET OFF.

Fact of the Case:

Plaintiff, the owner of the property, entered into a tripartite Lease Deed with defendant no.1 and Keikaku India Private Limited for running a commercial business in the demised premises. Keikaku India Private Limited withdrew from the Lease Deed and defendant no.2 was appointed as a new franchisee. Due to the COVID-19 pandemic, defendant no.1 sent an email to the plaintiff informing of the closure of the demised premises and requested a waiver of rent. Plaintiff offered a pre-approved payment plan for the rent of April and May 2020, which was not adhered to by the defendants. Plaintiff sent a legal notice calling upon defendant no.1 to make payment of outstanding rent, failing which the lease would be terminated. Defendant no.1 denied liability towards payment of rent, raising the ground of force majeure. Plaintiff filed a suit seeking recovery of possession, arrears of rent, mesne profits and interest in respect of the demised premises.

Finding of the Court:

The court held that the COVID-19 pandemic constituted a force majeure event under Clause 12 of the Lease Deed, as it was an "Act of God" and an "Embargo". The court found that the defendants were entitled to the benefit of the force majeure clause insofar as payment of rent for the months of April and May 2020 was concerned. However, the court held that the force majeure clause could not inure to the sole benefit of the lessee alone and that both the plaintiff and the defendants should equally bear the impact of the COVID-19 pandemic. The court directed the defendants to pay 50% of the lease rentals for the months of April and May 2020. The court also held that the defendants were liable to pay the lease rentals as per the Lease Deed from 1st June 2020 till 14th December 2020, when the possession of the demised premises was handed over, along with interest at the rate of 18% per annum. The court further held that the defendants were liable to pay arrears of GST on the lease rentals along with interest and any penalty or fine imposed by the GST authorities. The court also held that the defendants were liable to pay the unpaid electricity and water charges. The court allowed the defendants to claim set off in respect of the security deposit, the amount released in favor of the plaintiff, and the amount paid by the defendants in furtherance of the pre-approved payment plan.

Issues: 1. Whether the COVID-19 pandemic constituted a force majeure event under the Lease Deed? 2. Whether the defendants were entitled to a waiver of rent for the period of the COVID-19 pandemic? 3. Whether the plaintiff was entitled to recover possession of the demised premises? 4. Whether the defendants were liable to pay arrears of rent, mesne profits and interest? 5. Whether the defendants were liable to pay GST, penalty and fine on the lease rentals?

Ratio Decidendi: 1. The court held that the COVID-19 pandemic constituted a force majeure event under Clause 12 of the Lease Deed, as it was an "Act of God" and an "Embargo". 2. The court found that the defendants were entitled to the benefit of the force majeure clause insofar as payment of rent for the months of April and May 2020 was concerned. 3. The court held that the force majeure clause could not inure to the sole benefit of the lessee alone and that both the plaintiff and the defendants should equally bear the impact of the COVID-19 pandemic. 4. The court directed the defendants to pay 50% of the lease rentals for the months of April and May 2020. 5. The court held that the defendants were liable to pay the lease rentals as per the Lease Deed from 1st June 2020 till 14th December 2020, when the possession of the demised premises was handed over, along with interest at the rate of 18% per annum. 6. The court further held that the defendants were liable to pay arrears of GST on the lease rentals along with interest and any penalty or fine imposed by the GST authorities. 7. The court also held that the defendants were liable to pay the unpaid electricity and water charges.

Final Decision: The court decreed the suit in favor of the plaintiff and directed the defendants to pay the outstanding rent, mesne profits, interest, GST, penalty, fine, electricity charges and water charges, subject to set off of the security deposit, the amount released in favor of the plaintiff, and the amount paid by the defendants in furtherance of the pre-approved payment plan.

Judgement Key Points

Key Points: - The COVID-19 pandemic constitutes a force majeure event under Clause 12 of the Lease Deed (Act of God and Embargo) and affects April–May 2020 rent (!) (!) (!) (!) . - The force majeure does not benefit the lessee alone; both parties must bear the impact, with the court directing 50% rent payment for April–May 2020 and continuing rent from 1 June 2020 to 14 December 2020, plus interest at 18% (!) (!) (!) . - The court rejects a full waiver of rent beyond May 2020, noting reopenings and lack of termination by lessee; liability for post-June 2020 rent and possession handover is affirmed (!) (!) . - The plaintiff is entitled to recover arrears of rent, interest, GST, penalties/fines, electricity and water charges, with set-off against security deposits and prior payments (!) (!) (!) (!) (!) (!) (!) (!) (!) . - The court declines penal rent under Clause 14.2 due to absence of proven breach caused by defendants, given invocation of force majeure (!) (!) . - The possession was handed over on 14 December 2020; decree to be drawn for amounts due up to that date, with specified calculations and set-off rights (!) (!) (!) (!) (!) .

What is the scope and effect of the COVID-19 pandemic as a force majeure event under the Lease Deed?

What are the rights and obligations of the lessee and lessor with respect to rent payment during the force majeure period and after reopening?

What is the Court's determination on liability for arrears, interest, GST, penalties, and set-offs, and the resulting decree?


JUDGMENT

Amit Bansal, J.

I.A. No.12212/2021 (u/O-XIII-A(4) of CPC)

1. The present application has been filed on behalf of the plaintiff under Order XIII-A of the Code of Civil Procedure, 1908 (CPC), as applicable to commercial suits, seeking a summary judgment in favour of the plaintiff for a sum of Rs.3,83,09,444/- along with pendente lite and future interest.

2. Notice in the present application was issued on 20th September, 2021 and reply to the application on behalf of the defendant no.1 was filed on 27th November, 2021. Thereafter, plaintiff also filed rejoinder to the reply of the defendant no.1 in December, 2021.

3. Vide order dated 03rd March, 2022, the submission of the parties has been recorded that for deciding the issue of whether or not the defendants are entitled to the benefit of the force majeure clause, oral evidence would not be necessary.

FACTUAL MATRIX

4. Brief facts culminating into filing of the present suit are as follows.

4.1. Plaintiff is the owner of the property bearing No.C-11, Connaught Place, New Delhi-110001 consisting of the Ground Floor measuring about 2400 square feet and basement measuring about 400 square feet (demised premises).

4.2. A tripartite Lease Deed dated 04th January, 2018 (Lease Deed) was entered into by the plaintiff, being the lessor, and the defendant no.1 along with one Keikaku India Private Limited, being the lessees for running a commercial business in the demised premises. The said lease deed was duly registered. The term of the Lease Deed was for nine years running from 1st December, 2017 up to 30th November, 2026 with monthly rent being Rs.27,00,000/- for the period commencing from 30th January, 2018 to 30th November, 2020. Along with the monthly payment of rent, the defendants were also liable to pay the statutory tax, being the Goods and Service Tax applicable on the monthly rent amount. The defendants had deposited a sum of Rs.1,08,00,000/- with the plaintiff towards Interest Free Refundable Security Deposit as per Clause 7 of the Lease Deed.

4.3. Subsequently, vide communications dated 10th January, 2019 the plaintiff was informed of Keikaku India Private Limited withdrawing from the Lease Deed with effect from 01st February, 2019. Thereafter, the defendant no.2 was appointed as a new franchisee of the defendant no.1 and agreed to be bound by the terms and conditions of the Lease Deed.

4.4. On 30th March, 2020, the defendant no.1 sent an email to the plaintiff informing the plaintiff of the closure of the demised premises on account of the COVID-19 pandemic and requested the plaintiff to consider waiving off its obligation to pay rent.

4.5. Thereafter, on 03rd April, 2020, the defendant no.1 sent a notice of suspension of rent to the plaintiff, invoking the force majeure clause under the registered Lease Deed and asked for waiver of payment of rental dues till the time the demised premises became operational. Accordingly, rent was not paid by the defendants for the months of April, 2020 and May, 2020.

4.6. Vide email dated 28th May, 2020, the plaintiff informed the defendant no.1 that the force majeure clause embedded in the Lease Deed only provided for deferment of the date of paying rent and not for waiver of the rent. The plaintiff further offered the defendants a pre-approved payment plan in respect of the rent payable for the months of April, 2020 and May, 2020, whereby the defendant no.1 was given the option of making payment of Rs.48,60,000/- i.e., 50% of the amount due after deduction of Rs.5,40,000/- as Tax Deducted at Source, in two installments by 10th June, 2020 and 10th July, 2020 respectively.

4.7. Subsequently, the plaintiff reminded the defendant no.1 of the outstanding payment of rent for the months of April, 2020 and May, 2020 vide email dated 01st June, 2020.

4.8. The defendant no.1 called the plaintiff to request a waiver of the contractual rent due for the months of April, 2020 and May, 2020, which request was declined by the plaintiff vide email

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top