IN THE HIGH COURT OF DELHI AT NEW DELHI
Chandra Dhari Singh, J.
Ircon International Ltd. - Petitioner
Versus
Afcons Infrastructure Ltd. - Respondent
O.M.P. (COMM) 279 OF 2019 and I.A. 15375 OF 2019
Decided On : 26-04-2023
Arbitration and Conciliation Act, 1996 - Extension of Time - Impugned Award - [EXTENSION OF TIME] - [ARBITRATION AND CONCILIATION] - [Section 34]
Fact of the Case:
The petitioner, a Government Company, filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, seeking to set aside the impugned Award dated 5th March 2019. The dispute arose from a contract for the construction of a railway project, where the respondent sought an extension of time for delays in the work, which was granted by the Arbitral Tribunal. The petitioner challenged the award on the grounds of patently illegal and excessive extension of time.
Finding of the Court:
The Court found that the impugned Award did not exhibit any patent illegality or error apparent on the face of the record. The Arbitral Tribunal had carefully considered the facts and circumstances of the matter and analyzed it thoroughly to adjudicate the dispute. The Court held that the petitioner failed to show that any grounds stipulated under Section 34 of the Arbitration Act were being met. Consequently, the petition was dismissed, and the impugned Award was upheld.
Issues: The key grounds examined were whether the impugned Award was patently illegal and whether the Arbitrator granted an extension of more days than sought by the claimant/respondent.
Ratio Decidendi: The Court emphasized the limited scope of interference with an Arbitral Award under Section 34 of the Act, 1996, and reiterated that the Courts shall not sit in an appeal while adjudicating a challenge to an Award. The Court found that the impugned Award did not exhibit any patent illegality or error apparent on the face of the record.
Final Decision: The petition was dismissed, and the impugned Award was upheld.
JUDGMENT :
CHANDRA DHARI SINGH, J.
The instant petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter “The Act, 1996”) has been filed on behalf of the petitioner seeking the following reliefs:
b. Stay the execution, operation and implementation of the Impugned Award dated 05.03.2019 passed by the Ld. Arbitral Tribunal during the pendency of the present petition;
c. Pass ad-interim relief in terms of prayer clause ‘b’ above;
d. Cost of the proceedings may also be awarded in favour of the petitioner;
e. Pass such other or further orders as this Hon'ble Court may just deem fit and proper in the facts and circumstances of the present case.”
FACTUAL MATRIX
2. The petitioner is a Government Company incorporated by the Central Government (Ministry of Railway) under the Companies Act, 1956 on 26th April 1976, originally under the name of Indian Railway Construction Limited, having its registered office at Palika Bhawan, Sector-XII, R.K. Puram, New Delhi. It is a leading Turnkey Construction Company in the Public Sector.
3. To provide an alternative and a reliable transportation system into Jammu & Kashmir, the Government of India planned a 326 Km. long Railway Line for joining the Kashmir valley with the Indian Railways network named as Udhampur-Srinagar-Baramulla Rail Link (USBRL Project). The project was declared a ‘Project of National Importance’. From Jammu to Baramulla, the length of the new rail line is 326 Km.
4. On 25th July 2013, the petitioner invited bids for participation in tenders for the construction of Tunnel T-74R balance work from ADIT between 127/660 Km to 130/950 Km. (length 3290 meters) on the Dharam-Qazigund section of the Udhampur-Srinagar-Baramulla New BG Railway Line project, and on 7th August 2013, subsequent to the invitation of bid, the petitioner issued Corrigendum No. 1 to Tender Documents modifying the functional requirement as provided in SCC-IIA.
5. The petitioner vide letter dated 25th October 2013 informed the respondent that the cycle time calculation did not match with the geological L section provided with the tender and asked for rectification.
6. The respondent, on 29th October 2013, certified that on encountering the same rock mass as stipulated in tender documents the desired rate of progress, that is, 95 m/month in the main tunnel and 110 m/month in the escape tunnel, would be achieved. The respondent further confirmed that the mobilization in all respects would be done within 60 days.
7. The bid of the respondent was accepted on 20th January 2014 vide Letter of Recommendation, and a Contractual Agreement dated 14th March 2014 was entered into between the parties pursuant to which the petitioner engaged the respondent as a sub-contractor for construction of the said project. As per Clause 22 of the Agreement, the work was to be completed within the stipulated time mentioned under the Agreement.
8. On 23rd April 2014, during the joint site inspection, many points were observed with respect to the functioning of the shotcrete machine deployed at the project site.
9. The petitioner, on 12th May 2014, scrutinized the progress and it was observed by the petitioner that the work was delayed as per the schedule and the respondent was directed to deploy appropriate resources as per the Contractual Clauses to achieve the required progress.
10. During the meeting conducted on 22nd May 2014, it was observed by the petitioner that the works progress as of the said date was only 62m as against the required progress of 210.50m as per the Contract and as such there was a shortfall of 148.50m.
11. On 27th May 2014, the petitioner once again informed the respondent that the non-improvement of linear tunneling progress had not improved s
Delhi Airport Metro Express (P) Ltd. v. Delhi Metro Rail Corpn. Ltd.
Associate Builders v. Delhi Development Authority, (2015) 3 SCC 49
Champsey Bhara Company v. The Jivraj Balloo Spinning and Weaving Company Ltd.
ONGC Ltd. v. Western Geco International Ltd.
The main legal point established in the judgment is the limited scope of interference with an Arbitral Award under Section 34 of the Arbitration and Conciliation Act, 1996, and the requirement for th....
The limited scope of intervention by Courts in arbitral awards under Section 34 of the Arbitration and Conciliation Act, emphasizing the need to satisfy specific grounds for setting aside an arbitral....
The main legal point established in the judgment is the narrow scope of interference with an Arbitral Award under Section 34 of the Act, 1996, and the emphasis on reasonableness, natural justice, and....
Limited intervention of the Courts in arbitral proceedings is intended by the legislature. An Arbitral Award may only be set aside if it is patently illegal, against the public policy of India, based....
The scope of interference with an Arbitral Award under Section 34 of the Arbitration and Conciliation Act, 1996 is fairly limited and narrow. The Courts shall not sit in an appeal while adjudicating ....
Limited grounds for setting aside an arbitral award under Section 34 of the Arbitration Act and the Court's reluctance to re-adjudicate disputes on their merits.
The limited grounds for interference with an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, emphasize the concept of patent illegality and the criteria for setting asi....
Limited scope of interference and intervention by a Court in an Arbitral Award.
The scope of interference by courts in an Arbitral Award under Section 34 of the Arbitration Act is limited. Courts will not interfere with an award unless it is patently illegal, against public poli....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.