SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Del) 2053

IN THE HIGH COURT OF DELHI AT NEW DELHI
Navin Chawla, J.
M/s Methodex Systems Private Limited – Appellant
Versus
Govt of NCT of Delhi – Respondent
Arb.P. 112 of 2023
Decided On : 02-02-2023

Advocates appeared:
Ms.Risha Mittal, Advocate, for the Petitioner.
Ms. Hrishika Jain, Advocate for Mr. Shadan Farasat, ASC, for the Respondents. GNCTD.

The right to invoke an arbitration agreement accrues upon the denial of a payment demand, and subsequent proceedings cannot nullify this right.

Headnote:

Arbitration - Appointment of Arbitrator - Invocation of Arbitration Agreement

Fact of the Case:

The petitioner sought appointment of an Arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996, due to disputes arising from a Tender Agreement for providing furniture in government schools.

Finding of the Court:

The court found merit in the petitioner's submission that the dispute arose upon the demand for payment and denial thereof, and that the invocation of the arbitration agreement was valid despite the later decision of the Dispute Redressal Committee (DRC). The court appointed an Arbitrator and left all objections open for final adjudication.

Issues: Dispute over the timing of invoking the arbitration agreement and the validity of the appointment of an Arbitrator.

Ratio Decidendi: The court held that the right to invoke the arbitration agreement accrued to the petitioner upon the denial of the payment demand, and the subsequent DRC decision did not nullify this right.

Final Decision: The court allowed the petition, appointed an Arbitrator, and left all objections open for final adjudication.

JUDGMENT

Navin Chawla, J. (Oral)

I.A. 1993/2023(exemption)

1. Allowed, subject to all just exceptions.

ARB.P. 112/2023

2. This petition has been filed under Section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the `Act') seeking appointment of an Arbitrator for adjudicating the disputes that have arisen between the parties in relation to Tender Agreement bearing NIT No.11/EE(Edu.)/M/C&ND/PWD/2019-20 for providing furniture in various government schools for additional classrooms under Education Zone 19,20,21,22,26,27 & 28 Distt. South West and Central New Delhi, PWD, Package 3.

3. The Arbitration Agreement between the parties is contained in Clause 25 of the General Conditions of Contract (in short, `GCC').

4. Disputes having arisen between the parties, the petitioner vide letter dated 04.05.2022, requested the Chief Engineer to refer the disputes to the Dispute Redressal Committee (in short `DRC').

5. Having failed to receive any response, the petitioner invoked the arbitration agreement vide notice dated 29.07.2022.

6. The respondent no.1, however, vide letter dated 25.08.2022 referred the dispute to the DRC. The DRC denied the claim of the petitioner in the Minutes of Meeting held on 12.09.2022 and communicated the same to the petitioner on 29.11.2022.

7. The petitioner has thereafter filed the present petition.

8. The learned counsel for the respondents submits that in terms of Clause 25, the petitioner was to raise its dispute with the DRC within a period of 15 days of the dispute having arisen between the parties. She submits that in the present case, the dispute primarily relates to the invocation of the bank guarantee on 17.02.2022. The petitioner had requested the Chief Engineer to refer the dispute to the DRC only vide letter dated 04.05.2022. The same was beyond the time prescribed.

9. She further submits that in the present case, the petitioner had invoked the arbitration agreement on 29.07.2022, that is, prior to the decision of the DRC. She submits that, therefore, the invocation is not in terms of Clause 25 of the GCC.

10. As far as the delay in requesting the Chief Engineer to refer the dispute to the DRC is concerned, the petitioner states that the petitioner had earlier filed a petition under Section 9 of the Act, being OMP(I) (COMM) 71/2022 titled as Methodex Systems Private Limited v. Public Work Department GNCTD & Anr.. As the bank guarantee stood encashed and dispute arose between the parties, the petitioner sent a notice dated 21.04.2022 to the respondent requesting for payment of the outstanding amount. It is on non-payment of the same, that the dispute arose between the parties. She submits that therefore, request for reference of the dispute to DRC was within the time stipulated.

11. As far as the objection on the invocation of the arbitration being prior to the decision of the DRC is concerned, the learned counsel for the petitioner has submitted that in terms of Clause 25 of the GCC, the DRC is to give its decision within a period of 60 days. The clause further provides that in case no decision is received, the petitioner can invoke the arbitration agreement. She submits that in the present case, as no decision was received from the DRC within the stipulated period of 60 days, the petitioner invoked the arbitration agreement vide notice dated 29.07.2022. The later participation of the petitioner in the DRC proceedings was without prejudice to such invocation and therefore, the later decision of the DRC cannot nullify the invocation of the arbitration already made.

12. I find prima facie merit in the submission made by the learned counsel for the petitioner. Dispute would arise only upon the demand being made by the petitioner vide its letter/notice dated 21.04.2022 and denial thereof by the respondent. The request for reference of the disputes to DRC was made within time vide letter dated 04.05.2022.

13. As far as the invocation being made prior to the dec

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top