IN THE HIGH COURT OF DELHI
Neena Bansal Krishna, J.
K.B.G Engineers - Appellant
Versus
Delhi Tourism & Transportation Development Corporation Ltd. - Respondent
Arb.P. 577 of 2022
Decided On : 28-07-2022
| Table of Content |
|---|
| 1. facts surrounding the arbitration petition (Para 1 , 2 , 3 , 4 , 5 , 6 , 7) |
| 2. court's order for arbitrator appointment (Para 8 , 13 , 17 , 18) |
| 3. arguments against arbitration due to final payment and non-compliance (Para 9 , 10 , 11 , 12 , 14 , 15) |
| 4. conclusion: petition allowed for arbitration (Para 19) |
JUDGMENT
1. A petition under Section 11 of the Arbitration & Conciliation Act, 1996 has been filed for appointment of an Arbitrator.
2. The facts in brief as narrated in the petition are that the petitioner a registered partnership firm, was awarded the Tender vide Acceptance Letter bearing No. DTTDC/ENGG/I(196)/EE(PB)-III/135 dated 12th June, 2015 awarding the work to the petitioner. A Performance Guarantee of Rs.22,05,696/- in the shape of Bank Guarantee dated 17th June, 2015 and of Rs.6,35,000/- dated 18th June, 2015, were submitted. The Letter of Commencement of Work dated 19th June, 2015 was issued in favour of the petitioner. The Agreement bearing No. 02/EE(PB)-III/DTTDC/ENGG/2015-16 for execution of work for total contract amount of Rs.44,11,391/- was issued. The stipulated date of commencement of work was 27th June, 2015 and completion was 23rd December, 2015 as per the terms of the Contract.
3. The petitioner has submitted that work could not be completed within the stipulated period in view of the hindrances faced by the petitioner at site which were not attributable to it and led to delay in completion of work which could be completed ultimately on 11th April, 2016, for which a Completion Certificate was duly issued by the respondent. The petitioner wrote a Letter dated 19th December, 2019 requesting the respondent to release the amount of Rs.33,43,601/- which was withheld from the Final Bill passed on 22nd February, 2020. Having not received any response, the petitioner invoked Clause 25 of the Agreement vide his Letter dated 20th May, 2020 addressed to the respondent.
4. The CE of the respondent gave a Reply dated 19th June 2020 denying the contents of the letter of the petitioner. The respondent further directed the petitioner to invoke the Arbitration Clause by writing to the SE of the respondent in the first instance in terms of Clause 25 of GCC. The petitioner invoked the Arbitration Clause and wrote to the SE vide its Letter dated 10th August, 2020.
5. The respondent gave a Reply dated 04th September, 2020 reiterating its stand as taken in the previous correspondence. The petitioner then submitted a Letter dated 21st December, 2020 to the Chief Engineer but when no reply was received, the petitioner wrote Letter dated 21st December, 2020 requesting for appointment of the Arbitrator. When no response was received, he wrote a Letter dated 20th October, 2021 to the Managing Director and Chief Engineer requesting them to refer the matter to DRC. However, the respondent did not constitute the DRC, nor pay the claim amount with interest and failed to take any steps for appointment of the Arbitrator.
6. The petitioner then again wrote a Letter dated 29th January, 2022 requesting the Managing Director to appoint the Arbitrator within seven days for adjudication of the disputes.
7. It is submitted that disputes have arisen between the parties for release of the arrears of amount which the respondent has failed to pay despite repeated requests and letters. A prayer is, therefore, made that the Arbitrator may be appointed.
8. No formal reply nor any written submissions have been filed on behalf of the respondent.
9. Learned counsel on behalf of the respondent, however, has submitted that a full and final bill had been raised and accepted by the petitioner in April, 2022 and had also given an undertaking recording satisfaction. Having received the entire amount pursuant to the full and final bill, no arbitrable dispute remains between the parties and the present petition is liable to the dismissed.
10. Reliance has been placed on the case of Vidya Drolia vs. Durga Trading Corp., Civ
The court upheld the validity of the arbitration agreement and recognized the petitioner’s adherence to the procedural requirements for arbitration, irrespective of the respondent's claims regarding ....
The main legal point established in the judgment is that failure to follow the prescribed procedure and a claim being hopelessly barred by time can lead to the dismissal of a petition seeking the con....
The court ruled that jurisdiction under Section 11(6A) is limited to assessing the existence and validity of arbitration agreements, with unresolved factual disputes requiring arbitration.
The claims were notified within the stipulated period and submitted along with the final bill in accordance with Clause 6.6.3.0 of the GCC, making the disputes arbitrable under Clause 9.1.0.0.
The failure to constitute a Dispute Resolution Board justifies the appointment of an Arbitrator under the Arbitration and Conciliation Act, affirming the need for timely resolution of disputes arisin....
The central legal point established in the judgment is the court's authority to appoint an arbitrator to resolve disputed claims between parties in accordance with Section 11(6) of the Arbitration an....
Arbitration - Appointment of Arbitrator - Court is not required to examine any other contentious issues regarding the disputes between the parties at the stage of referring the parties to arbitration....
The main legal point established in the judgment is the application of limitation laws and the categorization of cases as dead wood in determining the eligibility for appointment of an arbitrator.
The court affirmed that when parties acknowledge disputes in a contractual agreement, an arbitrator must be appointed to resolve these disputes under the Arbitration and Conciliation Act, 1996.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.