IN THE HIGH COURT OF DELHI AT NEW DELHI
Prathiba M. Singh, J.
Royal Electrical Company – Appellant
Versus
Govt. of N. C. T. of Delhi – Respondent
W.P.(C) 834 of 2020 and CM APPL. 2596 of 2020
Decided On : 07-02-2023
Debarment - Government Contractor - Circular dated 25th November, 2019 - [Renovation of Sewage Pumping Station, Debarment] - [No specific Act-Section referenced] - The court held that the debarment order was not communicated to the petitioner and the Debarment Committee did not afford a hearing, thus the debarment would not sustain. The court set aside the debarment order and circular, allowing the DJB to take action in accordance with the law after complying with the principles of natural justice.
Fact of the Case:
The petitioner, a government contractor, challenged the circular debarment order issued by the Delhi Jal Board (DJB) based on alleged fictitious work carried out by the petitioner.
Finding of the Court:
The court found that the debarment order was not communicated to the petitioner and the Debarment Committee did not afford a hearing, thus the debarment would not sustain. The court set aside the debarment order and circular, allowing the DJB to take action in accordance with the law after complying with the principles of natural justice.
Issues: Debarment order communication, Affordance of hearing by Debarment Committee
Ratio Decidendi: The debarment order must be communicated to the petitioner, and the Debarment Committee must afford a hearing for the debarment to sustain.
Final Decision: The debarment order and circular were set aside, allowing the DJB to take action in accordance with the law after complying with the principles of natural justice.
JUDGMENT
Prathiba M. Singh, J. (Oral)--This hearing has been done through hybrid mode.
2. The Petitioner - Royal Electrical Company, A-771, Shastri Nagar, Delhi-110052, stated to be a registered government contractor, challenges the impugned circular dated 25th November, 2019 whereby the Petitioner has been debarred for a period of 5 years by the Delhi Jal Board (`DJB').
3. The work order dated 4th January, 2018 was awarded to the Petitioner for the purpose of renovation of the electrical system of the Sewage Pumping Station (SPS) at sector 17 Rohini. The total value of the work order was Rs.2,48,127/- (Rupees Two Lakh forty eight thousand one hundred and twenty seven). The DJB issued show cause notice on 2nd April, 2019 seeking reasons as to why the Petitioner ought not to be blacklisted/removed/temporarily suspended from the list of approved contractors on the ground that some of the work, which was allegedly claimed to have been carried out by the Petitioner, had turned out to be bogus/fictitious. A reply was given by the Petitioner to the said show cause notice, on 16th April, 2019 explaining that the work order was actually executed to the satisfaction of the officials of the DJB. A hearing was given by the Executive Engineer, (SDW) IX, DJB. However, thereafter, no debarment order was communicated except the impugned circular dated 25th November, 2019.
4. The submission of Ms. Mehrotra, ld. Counsel for the Petitioner is five fold-
i. That the impugned circular relies upon a debarment order dated 15th November, 2019, which had not been communicated to the Petitioner.
ii. The Debarment Committee did not give a hearing to the Petitioner. A hearing was only given by the Engineer concerned.
iii. In a connected matter, where a similarly placed party was debarred, the file noting was relied upon by the DJB, which cannot constitute an order.
iv. The work was executed to the satisfaction of the concerned engineer.
v. The allegation of bogus/fictitious work is not maintainable, inasmuch as the 12 exhaust fans, which were to be supplied, were in fact, supplied by the Petitioner.
5. She submits that under similar circumstances, ld. Single Judges of this Court have set aside the debarment order in
6. Ms. Kanika Agnihotri, ld. Counsel appearing on behalf of the DJB submits that the show cause notice clearly specifies the grounds on which the debarment was contemplated. The reply was also considered and the matter was taken up by the Debarment Committee on the recommendation of the Managing Director (MD)/CEO.
7. It is further submitted by Ms. Agnihotri, that the DJB had found that several of its own employees may have been in collusion with some contractors and when this was unearthed by the DJB, the action of debarment was undertaken by the Respondent in consultation with the vigilance department. Ld. Counsel for the Respondent submits that the circular itself would have to be treated as a debarment order, inasmuch as the Petitioner is well aware of the reasons for which the debarment has been undertaken. She further submits that the principles of natural justice have been duly complied with.
8. A perusal of this record shows that the circular dated 25th November, 2019 reads as under:
"The Competent Authority vide orders dated 15-11-2019 has approved to Debar following firms including their Proprietor/Partner(s)/Director(s) from participation in any of the tenders to be issued by the Divisions/Office(s) of Delhi Jal Board and to have any business dealing with DJB by any means for the period mentioned against each firm from the date of issued of this circular.
| S. No. | ||
Debarment orders must be communicated to the affected party, and the Debarment Committee must afford a hearing for the debarment to sustain.
The severity of the effects of blacklisting and the resultant need for strict observance of the principles of natural justice before passing an order of blacklisting.
The legal principle established is that prior to blacklisting or debarment, a show cause notice is mandatory, and debarment issued without notice and during the pandemic period is untenable.
Blacklisting decisions must adhere to principles of fairness, reasonableness, and natural justice, ensuring proper consideration of the contractor's defense.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.