SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Del) 1132

IN THE HIGH COURT OF DELHI AT NEW DELHI
Yashwant Varma, J.
ITD Cementation India Limited – Appellant
Versus
Ssjv-zvs Joint Venture & Ors. – Respondents
OMP (ENF.) (COMM.) 188 of 2021, CCP(O) 46 of 2022, EX.APPL.(OS) 1316 of 2021, EX.APPL.(OS) 1318 of 2021 (Stay), EX.APPL.(OS) 1319 of 2021 (Necessary Direction), EX.APPL.(OS) 2822 of 2022, EX.APPL.(OS) 3243 of 2022, EX.APPL.(OS) 3311 of 2022
Decided On : 07-03-2023

Advocates appeared:
Dr. Amit George, Mr. Piyo Horold, Mr. Amol Acharya, Mr. Rayadurgam Bharat and Mr. Arkaneik Bhaumik, Advocates, for the Decree Holder.
Ms. Nupoor Maharaj, Advocate, for the Judgement Debtor No. 1 & 2.
Mr. Garnishee, Advocate with Mr. Puneet Taneja, Advocate, for the NTPC.

The main legal point established in the judgment is the joint and several liability of members in a joint venture, and the binding nature of contracts executed by the joint venture.

Headnote:

JOINT VENTURE - ENFORCEMENT PETITION - 2021, 46/2022, 1316/2021, 1318/2021, 1319/2021, 2822/2022, 3243/2022 - The court discussed the concept of a joint venture and its legal implications, emphasizing the joint and several liability of the members, and the binding nature of contracts executed by the joint venture. The court held that the individual members of a joint venture cannot seek trial of disputes based on their perceived individual responsibilities and obligations, and that the joint venture itself being before the Arbitral Tribunal was sufficient for adjudication of claims. The application was dismissed.

Fact of the Case:

The enforcement petition emanated from an award in favor of the Enforcement Petitioner, entitling them to realize a specified amount along with interest and costs from a joint venture formed for the construction of a Barrage and a De-silting Chamber for a Hydroelectric Power Project.

Finding of the Court:

The court found that the joint venture, as a legal entity, was liable for the obligations arising from the contract, and the individual members could not seek separate trials based on their perceived individual responsibilities. The application was dismissed.

Issues: The key issue was the liability of the joint venture and its members in the enforcement proceedings, and whether the individual members could seek separate trials based on their perceived individual responsibilities.

Ratio Decidendi: The court emphasized the joint and several liability of the joint venture and held that the individual members could not escape liability arising from the joint venture. It further held that the joint venture itself being before the Arbitral Tribunal was sufficient for adjudication of claims.

Final Decision: The application was dismissed, and the matter was scheduled for a subsequent hearing.

ORDER

EX.APPL.(OS) 3311/2022

1. The instant application has been moved for Respondent No. 2 being struck off from the array of parties in the present petition. The execution proceedings emanate from an Award rendered on 09 March 2019 in terms of which the Enforcement Petitioner became entitled to realize an amount of Rs.6,65,55,228/- along with interest @ 12% from 07 November 2013 till the realization of the amount along with costs.

2. The first respondent is a joint venture which was constituted between M/s SSJV Projects Private Limited and M/s Zarubezhvodstroy. The aforesaid joint venture as per the Applicant's own admissions was formed for the purposes of execution of the contract relating to the construction of a Barrage and a De-silting Chamber for Tapovan-Vishnugad Hydroelectric Power Project. As is evident from the records produced in these proceedings, the Respondent had entered into a contract on 06 February 2009 for construction of an upstream cut-off wall. Consequent to disputes having arisen, the matter came to be referred to arbitration. Those proceedings ultimately culminated in the pronouncement of an Award of which execution is sought in the present petition.

3. Undisputedly, SSJV Projects, the second Respondent, was a constituent of the joint venture. It is the joint venture which was arrayed as a Respondent before the Arbitral Tribunal.

4. The Applicant Respondent No. 2 however contends that since it was not individually placed on notice by the Arbitral Tribunal, the execution proceedings as drawn against it are not maintainable. Learned counsel appearing for the Applicant would contend that since the second respondent is an entity duly incorporated and thus having a separate and distinct identity in law, no proceedings for execution can be taken against it.

5. Learned counsel had also placed reliance upon a judgment rendered by the Court in Consulting Engineers Group Limited v. National Highways Authority of India (NHAI), 2022 SCC OnLine Del 3253 in support of her aforenoted submissions. It must however, and at the outset, be noted that Consulting Engineers clearly cannot be read as an authority supporting the arguments which have been addressed on behalf of the Applicant. Consulting Engineers was considering the question whether an individual member of a consortium could have invoked arbitration or sought interim measures. While negativing the right of an individual member to move such a petition, the learned Judge had ultimately held that a constituent of a joint venture could not individually petition for interim measures. It also held that a member of the consortium cannot independently approach the Court seeking relief and that it would be the joint venture alone which would have the authority to invoke the dispute resolution clause. The judgment in Consulting Engineers thus in fact runs contrary to what was contended on behalf of the Applicant.

6. Dr. George while explaining the concept of a joint venture firstly relied upon a judgment rendered by the Division Bench of the Gujarat High Court in Asia Foundations & Constructions Ltd., Bombay v. State of Gujarat, 1985 SCC OnLine Guj 93. While rendered in the context of a tendering process that was assailed, the said High Court described the essential attributes of a joint venture in the following terms:

    "47. The different forms "A" to "G" which have been referred to in the facts narrated hereinabove containing requisite particulars to be furnished by the applicants seeking prequalification, inter alia, relate to joint venture also. The particulars which are to be furnished in form "C" relating to joint venture consist of (1) name and address of joint venture; (2) name and address of all the partners of joint, venture; (3) the responsibility of the firm leading the joint venture and the responsibility of the other joint venture partners; (4) the name of bankers and (5) the financial participation of each firm in the joint venture. Thus, it is clear tha

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top