IN THE HIGH COURT OF DELHI AT NEW DELHI
Rekha Palli, J.
Gail Gas Limited – Appellant
Versus
M/s Shyam Glass Works – Respondent
O.M.P. (COMM) 263 of 2023, I.A. 13483 of 2023-Ex., I.A. 13481 of 2023 Stay, I.A. 13482 of 2023-Delay 69 days
Decided On : 25-07-2023
Arbitration and Conciliation Act - Petition to set aside arbitral award - Sections 34 - Tampering of gas meter - Act Section List: Arbitration and Conciliation Act, 1996, Section 34 - The court discussed the original contract between the parties, the custody and ownership of the metering equipment, and the evidence of tampering. The court also considered the inspection reports and the responsibility of the respondent for the tampering of the meters. The key legal provisions discussed include the limited jurisdiction of the court under Section 34 of the Act and the principle that the court does not sit in appeal over an arbitral award.
Fact of the Case:
The petitioner, a Central public sector undertaking, supplied gas to the respondent, a firm engaged in manufacturing glass items. The petitioner alleged tampering of the meter by the respondent and discontinued the gas supply, leading to arbitration.
Finding of the Court:
The court found that the petitioner failed to prove tampering of the meter by the respondent, and therefore, dismissed the petition to set aside the arbitral award.
Issues: The issues revolved around the responsibility for tampering of the gas meter and the validity of the arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996.
Ratio Decidendi: The court's decision was based on the finding that the petitioner failed to prove tampering of the meter by the respondent, and the limited jurisdiction of the court under Section 34 of the Act.
Final Decision: The petition to set aside the arbitral award was dismissed.
JUDGMENT
Rekha Palli, J. (Oral)--The present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (the Act) seeks to assail the arbitral award dated 28.10.2022 passed by the learned Arbitrator as rectified on 09.02.2023.
2. Vide the impugned award, the learned Arbitral Tribunal has after coming to the conclusion that respondent could not be held liable for tampering of the meter or seals or any internal part of the metering skid installed in the respondent's premises rejected the petitioner's claim against the respondent for damages of Rs.1.62 Crores.
3. Before dealing with submissions of the learned counsel for the petitioner, the brief factual matrix as is necessary for adjudication of the present petition may be noted.
4. The petitioner, a Central public sector undertaking under the Ministry of Petroleum and Natural Gas is inter alia engaged in the business of providing natural gas through its country vide pipeline projects. On the other hand, the respondent is a firm engaged in the business of manufacturing of glass and glass items using a gas based furnace and is running a factory in District Firozabad, Uttar Pradesh.
5. On 09.10.1996, the petitioner entered into an agreement with the respondent for supply of gas to the respondent and accordingly a metering skid was installed at the premises of the respondent, for billing purpose. The agreement was extended from time to time and consequently the petitioner continued to supply gas to the respondent.
6. It is the common case of the parties that on 11.11.2004, the turbine meter in the metering skid installed at the respondent's premises was replaced by the petitioner's officials. The original turbine meter was sent to a company known M/s Rockwin Flow Meter Pvt Ltd. for inspection and calibration. A similar exercise was again carried out on 28.01.2005 when the turbine meter was again changed and sent for inspection to the aforesaid company. Based on the reports received from the said company that the turbine meter had been tampered, the petitioner after issuing a show cause notice, discontinued the supply of gas to the respondent, and also demanded a sum of Rs.1.62 Crores from the respondent on account of the tampering of the meter.
7. Being aggrieved by the disconnection of its gas connection, the respondent approached the Allahabad High Court by way of a writ petition which was disposed with a direction to the petitioner to decide the respondent's pending application for restoration of his gas connection. Upon its application being rejected, the respondent invoked arbitration raising eight claims. During arguments before the learned Arbitrator, the respondent however pressed only claim no.1 wherein it had sought a declaration that there was no tampering of the meters at its end. In response whereof, the petitioner also raised two counter claims before the learned Arbitrator seeking a direction against the respondent to pay a sum of Rs.1.62 Crores. The learned Arbitrator vide the impugned award has allowed claim no.1 raised by the respondent by holding that the respondent could not be held guilty of any tampering of the turbine meters and has consequently, rejected the petitioner's counter claim.
8. In support of the petition, learned counsel for the petitioner seeks to contend that the impugned award is perverse and against public policy as the learned Arbitrator had wrongly placed the onus of proving that the meter had been tempered by the respondent on the petitioner. He submits that once it was evident from the report of M/s Rockwin Flow Meter Pvt Ltd. that the turbine meter had been repeatedly tampered, the respondent ought to have been directed to prove that the meter was not tampered by it. He further submits that the learned Arbitrator has also ignored the terms of the agreement between the parties by rejecting the inspection reports from Rockwin Flow Meter Pvt Ltd. which clearly showed that the meters had been tampered. He, therefore, conten
The court's decision emphasizes the limited jurisdiction of the court under Section 34 of the Arbitration and Conciliation Act, 1996, and the principle that the court does not sit in appeal over an a....
The court emphasized that re-evaluation of evidence is beyond the scope of Section 34 of the A&C Act, and the arbitrator's approach on facts is final.
An arbitral award can only be annulled on limited grounds of patent illegality or violation of public policy; mere errors in evidence appreciation do not suffice.
The main legal point established in the judgment is the limited scope of interference under the Arbitration and Conciliation Act, 1996, and the interpretation of specific clauses of the Gas Supply Ag....
The court affirmed that limited judicial review under Section 34 of the Arbitration Act does not allow for re-evaluation of arbitration awards unless they are demonstrably perverse, illegal, or devoi....
The plaintiff must prove meter tampering to recover losses under the Electricity Supply Act; indemnity clauses in leases bind third parties to compensate owners for damages.
The Plaintiff must prove both the tampering of the meter and the loss of revenue; failure to do so results in dismissal of the claim.
The claimant failed to establish loss of revenue due to meter tampering, resulting in the dismissal of the case, governed by principles of limitation and burden of proof.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.