IN THE HIGH COURT OF DELHI AT NEW DELHI
Jyoti Singh, J.
Union of India – Appellant
Versus
M/s. Roshan Real Estate Pvt. Ltd. – Respondent
O.M.P. (COMM) 233 of 2023
Decided On : 02-08-2023
Arbitration - Challenge to Arbitral Award - Section 34 of the Arbitration and Conciliation Act, 1996 - [Arbitration] - [Arbitration and Conciliation Act, 1996, Section 34] - The court discussed the challenge to the arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, focusing on the statutory period of limitation for filing the petition and the discretion of the court to condone the delay.
Fact of the Case:
The petitioner filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996 seeking to set aside an arbitral award. The challenge was restricted to specific claims and interest awarded in favor of the respondent. The respondent raised a preliminary objection that the petition was filed beyond the statutory period of limitation and the court's discretionary period for condonation of delay.
Finding of the Court:
The court dismissed the application seeking condonation of delay and subsequently dismissed the petition under Section 34 of the Act, as it lacked the power to condone the delay in filing the petition beyond the statutory and discretionary periods of limitation.
Issues: The issues involved the challenge to the arbitral award under Section 34 of the Act, specifically focusing on the statutory period of limitation and the court's discretion to condone the delay in filing the petition.
Ratio Decidendi: The court emphasized the absolute, unextendible, and inflexible nature of the time limit prescribed under Section 34(3) of the Act, highlighting the legislative intent to minimize the supervisory role of courts in the arbitral process. The court held that it lacked the power to exercise discretion to condone the delay in filing the petition beyond the statutory and discretionary periods of limitation.
Final Decision: The application seeking condonation of delay was dismissed, and consequently, the petition under Section 34 of the Act was also dismissed.
JUDGMENT
Jyoti Singh, J. (Oral)
I.A. 12397/2023 (exemption)
1. Allowed, subject to all just exceptions.
2. Application stands disposed of.
O.M.P. (COMM) 233/2023 & I.A. 12398/2023 (delay in filing)
3. Present petition has been filed by the Petitioner under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the `Act') seeking setting aside of the impugned arbitral award dated 30.01.2023 passed by the learned sole Arbitrator with respect to Claim Nos. 1, Part K (EI 3/7) and 5 and the interest awarded.
4. Factual matrix to the extent relevant is that Petitioner issued an open tender for work at Dr. B.R. Ambedkar National Memorial Complex at 26, Alipur Road, Delhi for Civil Work, Internal and external electrical work, firefighting, D.G. Sets and Lifts, etc. The estimated cost of the work was a sum of Rs.40,27,46,531/-. On 29.03.2016, Respondent submitted its Expression of Interest, with a financial bid of Rs.41,08,01,462/-.
5. Tender was awarded to the Respondent on 07.04.2016 and an agreement was executed between the parties, with 22.04.2016 being the date of commencement of construction work and 21.07.2017 being the stipulated date of completion. Extension of time was granted by the Competent Authority on 25.05.2018, without levy of compensation. Final bill of the Respondent was passed by the Petitioner on 05.07.2018, however, on account of certain grievances, Respondent invoked the Arbitration Clause on 02.05.2020 and sought appointment of the sole Arbitrator. Sole Arbitrator was appointed by the Competent Authority on 13.04.2021 and the Award was passed on 30.01.2023.
6. Challenge to the Award is restricted to award of Claims Nos.1, Part K (EI 3/7) and 5 as well as interest awarded in favour of the Respondent. Claim No.1 was for balance payment of Rs.11,12,10,924/- from the final bill for a sum of Rs.54,98,16,190/- as Petitioner had paid only Rs.43,86,05,266/- to the Respondent. Claim No.5 was with respect to bonus under Clause 2A of the Agreement which provided that in case the contractor completed the work ahead of updated stipulated date of completion, he would be entitled to incentive/bonus @ 1% of the tender value per month computed on per day basis, subject to maximum limit of 5% of the tender value. Objection is raised to the grant of interest on the legal ground that Arbitrator has the discretion to award interest but cannot go outside the contract albeit this Court is unable to discern on what ground the challenge is laid by the Petitioner in the facts of this case.
7. Court is not delving any further into the merits of the grounds raised in the present petition, in view of the preliminary objection raised by the Respondent that the petition has been filed not only beyond the period of three months, which is the statutory period of limitation for filing a petition under Section 34 of the Act, but also beyond the 30 days period, within which Court has the power and discretion to condone the delay, if the Applicant is able to show that he was prevented by sufficient cause from making the application, invoking proviso to Section 34(3) of the Act.
8. Learned counsel for the Petitioner has urged this Court to condone the delay of 63 days for the reasons set out in the application. It is argued that after the Award was received, Petitioner requested the Government Counsel who was defending the matter on behalf of the Petitioner before the learned Arbitral Tribunal to give his legal opinion, which was received on 18.02.2023. Thereafter, the file had to be processed through various channels for examination of the Award for the purpose of deciding if the same was to be challenged. The reasons for delay as stated in the application being I.A. No.12398/2023 for condonation of delay are as follows:
"3. That thereafter the case file of the department alongwith opinion of the Govt. Counsel was submitted to the S. E..On 28.02.2023 the case file of present matter was submitted by SE & PD, DPC-1,
AI
The court emphasized the absolute nature of the time limit prescribed under Section 34(3) of the Arbitration and Conciliation Act, 1996, highlighting the legislative intent to minimize the supervisor....
The main legal point established in the judgment is the significance of adhering to the prescribed limitation period under the Arbitration Act and the requirement for parties to exercise their rights....
The judgment establishes the strict interpretation and application of the limitation period under Section 34(3) of the Arbitration Act, emphasizing the requirement for sufficient cause and the mandat....
Point of Law : Arbitration and Conciliation - Arbitral Award - Challenged - Section 34 provides that recourse to a court against an arbitral award may be made only by an application for setting aside....
Adherence to time limits stipulated under the Arbitration Act and the requirement of due diligence in seeking condonation of delay.
The Court emphasized the importance of due diligence and dispatch in exercising the right to challenge an Arbitral Award within the prescribed time, as per the provisions of the Arbitration Act.
The scope of interference in an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996 is limited and narrow. The Courts shall not sit in an appeal while adjudicating a challen....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.