SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Shashank Bhagat - Appellant
Versus
Shefali Varma - Respondent
Arb.P. 737 of 2017
Decided On : 22-07-2019




Judgement Key Points

Key Points: - The doctrine of indoor management does not apply because the petitioners had constructive notice of Ms Shefali Varma's lack of authority and there were suspicious circumstances surrounding the Agreement (!) (!) (!) . - There is no arbitration agreement between the petitioners and the Companies because Ms Shefali Varma lacked authority to bind the Companies, and the petitioners failed to make necessary inquiries about her authority (!) (!) . - An arbitration agreement exists between the petitioners and Ms Shefali Varma, as the arbitration clause in the Agreement is a separate and binding agreement between them (!) (!) .

What is the scope of applicability of the doctrine of indoor management in this case?

Whether an arbitration agreement exists between the petitioners and the Companies?

What is the status of the arbitration clause between the petitioners and Ms Shefali Varma?


JUDGMENT

Vibhu Bakhru, J. The petitioners have filed the present petition under Section 11 of the Arbitration and Conciliation Act, 1996 (hereafter `the A&C Act'), inter alia, praying that an arbitrator be appointed to adjudicate the disputes that have arisen between the parties in connection with the Agreement to Develop dated 29.10.2012 (hereafter referred to as `the Agreement'). The Agreement was executed by respondent no.1 (Ms Shefali Varma) in her individual capacity claiming to be the legal beneficiary of the estate of her father, late Sh Ashok Varma. She had also signed the Agreement on behalf of respondent nos. 2 to 12 (hereafter referred to as `the Companies') as their Director. The recitals of the Agreement record that the Companies, acting through Ms Shefali Varma as a Director, had entered into an agreement dated 24.02.2011 with petitioner no.1 (Shashank Bhagat) for undertaking a group housing project under joint development on a plot of land, measuring 11.26 acres approximately, located in Sector-56 Gurgaon. The said agreement was referred to as `Agreement with SV' in the Agreement (it is hereafter referred to as `the 2011 Agreement'). Pursuant to the 2011 Agreement, petitioner no.1 had made a payment of Rs.5,00,00,000/- (Rupees Five Crores) to Ms Shefali Varma which she had admitted having received for and on behalf of the Companies. In terms of the 2011 Agreement, petitioner no.1 had agreed to pay a consideration of Rs.50 crores to the Companies for developing a housing project at his own expense. In turn, petitioner no.1 was entitled to 60% of the total built up area as well as proportionate common areas and the remaining 40% area would fall to the share of the Companies. It was also recorded that petitioner no.1 was entitled to enter into a tie-up with another developer and had, in fact, done so by entering into an agreement dated 02.03.2011 with M/s Eldeco Infrastructure and Properties Pvt. Ltd. for developing a housing project on the aforesaid land (land measuring 11.26 acres approximately, located in Sector-56, Gurgaon).

2. The Agreement also recorded that further addenda (four in number) to the 2011 Agreement had been entered and description of which was noted.

3. In terms of the Agreement, petitioner no.2 (Silverglades Holdings Private Limited) was appointed as the principal developer along with petitioner no.1 as a co-developer for developing the project on a minimum area of 10 acres, located within Ardee City in Sector-52, Gurgaon. The said land included a parcel of land measuring 5.78 acres being a part of the Group Housing Scheme known as `Residency'. In consideration of the development rights, it was agreed that petitioner no.2 shall pay an aggregate consideration of Rs.50 crores to the Companies. It was also acknowledged that Ms Shefali Varma had received an aggregate sum of Rs.9 crores on behalf of the Companies, as detailed in the Agreement and the balance amount of Rs.41 crores was agreed to be paid to the Companies in proportion of their land holding and in a manner as stipulated therein.

4. The petitioners claim that the disputes have arisen in connection with the Agreement and the same are required to be resolved by arbitration in terms of Clause 16 of the Agreement. The said clause is set out below:

    "16. Arbitration

    16.1 The Parties herein agree that any dispute or difference arising between the Parties under the Agreement shall be resolved amicably in the first instance. In case the Parties fail to arrive at a amicable settlement within 30 days of reference thereof for amicable discussions, such unresolved disputes or differences shall be settled by arbitration referred to a sole arbitrator, to be mutually appointed by the disputing Parties in accordance with the provisions of the Arbitration and Conciliation Act, 1996 and any statutory amendments thereto from time to time.

    16.2 The award of the Arbitrator/s shall be final and binding m1 the Parties to the Agreement. Neither Party shal

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top