IN THE HIGH COURT OF DELHI
V. Kameswar Rao, J.
Pacific Development Corporation Ltd. - Appellant
Versus
South Delhi Municipal Corporation - Respondent
W.P.(C) 3712 of 2019, CM Nos. 17056 of 2019 & 29137 of 2019
Decided On : 10-02-2020




Important Points

Jurisdiction over parking fee collection rests with municipal law, which mandates free public use of designated parking areas under the local development plan, despite private agreements permitting charge collection.

Subject

Administrative Law - Municipal Regulations

Act Referred

CONSTITUTION OF INDIA: Art.14, Art.19, Art.226
DELHI MASTER PLAN: Ch.17 Cl.5.0, Ch.17 Cl.8
DELHI MUNICIPAL CORPORATION ACT: S.332, S.345-a, S.347, S.491
UNIFIED BUILDING BYE-LAWS FOR DELHI: Byelaw.1.1, Byelaw.1.2, Byelaw.1.3.3, Byelaw.1.4.80, Byelaw.2.8, Byelaw.7.4, Byelaw.7.4.10, Byelaw.7.4.9, Byelaw.8.10

Headnote

(A) Delhi Municipal Corporation Act, 1957 - Section 345-A - Writ petition seeking to restrain the SDMC from prohibiting the collection of parking fees by the petitioner, a concessionaire of DMRC, for parking at Pacific Metro Mall - The SDMC ordered the petitioner to stop charging parking fees until the matter was decided due to a public notice stating such parking areas are to be free of cost. (Paras 1-6, 10-11, 37-48)

(B) Jurisdiction - SDMC's authority limited to sanctioning building plans and not regulating parking charges on private property - The court found that the petitioner could charge fees pursuant to the Concessionaire Agreement, but restrictions applied under municipal laws regarding the usage of free-from-FAR common areas. (Paras 45-49)

(C) Legal Principle - The principle of user pays must govern pricing of parking space per the Municipal Policy unless other statutory obligations exist. (Paras 32-41)

Facts of the case:
The petitioner, Pacific Development Corporation Ltd., was restrained by the SDMC from charging parking fees at the Pacific Metro Mall, asserting that the parking area was to be maintained for public use without charges as per a 2015 notice. The petitioner claimed ownership through a Concessionaire Agreement with DMRC and contended that the SDMC lacked jurisdiction to impose such restrictions.

Findings of Court:
The court found no merit in the petitioner’s claims and upheld the SDMC's prohibition on charging fees, concluding that the parking spaces were to remain free for public usage as per existing laws and notices.

Issues: The main issues addressed included the legality of the SDMC's enforcement against the petitioner charging fees based on public interest and municipal regulations.

Ratio Decidendi: The court held that while the petitioner could operate commercially under the Concessionaire Agreement, local laws governing public property use constrained the collection of parking fees, reflecting a balance between private rights and public obligations.

Result: Writ petition dismissed, maintaining the SDMC's order.

JUDGMENT

V. Kameswar Rao, J. The present writ petition has been filed by the petitioner with the following prayers:

"In the light of the facts and circumstances stated hereinabove it is most humbly prayed that this Hon'ble Court may be graciously pleased to:

(a) Issue a writ of mandamus or any other similar writ, order or direction commanding upon the Respondent no.1 to produce the entire records/file with regard to the issue of charging of parking fee by the Petitioner with regard to vehicles parked at the Pacific Metro Mall on the plot situated at Najafgarh Road, Tagore Gardens, Tilak Nagar, New Delhi;

(b) Issue a writ of mandamus or any other similar writ, order or direction commanding upon the Respondent no.1 from not interfering with the exclusive right and authority of the petitioner from charging parking fee with regard to vehicles parked at the Pacific Metro Mall on the plot situated at Najafgarh Road, Tagore Gardens, Tilak Nagar, New Delhi at the rates as fixed/determined by the Petitioner;

(bl) Issue a writ of Certiorari or any other similar writ, order or direction setting aside/quashing the order dated 14.05.2018 passed by the Executive Engineer, SDMC (Annexure P/1) directing the Petitioner not to charge any parking charges.

(c) Pass such further order(s) which this Hon'ble Court may deem fit and proper in the facts and circumstances of the present case.

2. Vide the impugned order dated May 14, 2018 issued by the Executive Engineer of respondent No.1/SDMC, petitioner was restrained from charging parking fee till the case of the petitioner based on the representations/letters preferred by the petitioner on February 23, 2018 and May 01, 2018 was decided by the respondent No.1/SDMC.

3. The case of the Petitioner is stated as herein below:

3.1. DDA vide letter dated May 07, 2003 allotted a land admeasuring 35,000 sq.m. at Khyala (between Subhash Nagar and Tagore Garden Metro Station) on perpetual leasehold basis to respondent No. 2/Delhi Metro Rail Corporation ("DMRC", for short) for the purpose of Mass Rapid Transit System ("MRTS", for short) Project. The land was handed over to respondent No. 2/DMRC on June 26, 2003.

3.2. On July 21, 2003, Ministry of Urban Development ("MoUD", for short), Govt. of India vide its letter to Municipal Corporation of Delhi ("MCD", for short) informed that the Cabinet has permitted respondent no.2/DMRC to generate revenue through property development.

3.3. Pursuant thereto respondent No.2/DMRC entered into a Concessionaire Agreement dated March 08, 2007 ("Concessionaire Agreement", for short) with the petitioner i.e. M/s Pacific Development Corporation Ltd. (formerly known as "Naman Buildcon Ltd.") for an area of 33951.5 sq.m., to develop, finance, construct, commission, operate, manage and maintain the project (built up spaces and facilities in specified area) and the project facility for a period of thirty years. This project was awarded to the petitioner on Build-Operate Transfer ("BOT", for short) basis. Petitioner's case is that in terms of the Concessionaire Agreement, the petitioner had paid a sum of Rs.60 crores upfront and has been paying Rs.2.16 cores on a quarterly basis since November 17, 2010. The quarterly payment would be escalated @ 20% after the expiry of three years from the date of first payment on a compounding basis. The petitioner, in return, is entitled to receive all receivables from the use of project and project facility after the payment of aforesaid dues to respondent No.2/DMRC.

3.4. On March 30, 2009, MoUD vide its order directed that the property development activities of respondent No. 2/DMRC undertaken to supplement the cost of project is to be considered as part of the project. The same was to increase the non-operational revenues i.e. revenues from advertisement, retailing, real estate at metro stations, parking lot revenues, etc. in lines with global examples of metro such as Hong Kong Metro.

3.5. Respondent no.1/SDMC in terms of Section 332 of