IN THE HIGH COURT OF DELHI
V. Kameswar Rao, J.
Janapriya Engineerss Syndicate Pvt. Ltd. - Appellant
Versus
Union of India - Respondent
O.M.P.(MISC.)(COMM.) 377 of 2019 and O.M.P.(MISC.)(COMM.) 378 of 2019
Decided On : 05-06-2020
| Table of Content |
|---|
| 1. factual summary of arbitration proceedings. (Para 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12) |
| 2. petitioner's claim on arbitration fees. (Para 14 , 15 , 16) |
| 3. respondent's objections to petition's maintainability. (Para 18 , 19 , 20 , 21 , 22 , 23) |
| 4. argument on arbitrator's fee entitlement. (Para 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34) |
| 5. arguments reinforcing petitioner's position. (Para 35 , 36 , 37 , 38 , 39) |
| 6. court's observations on proceedings and section 39. (Para 43 , 44 , 45 , 46 , 47 , 48) |
| 7. conclusion regarding maintainability of petitions. (Para 49 , 50 , 51 , 52 , 53 , 54) |
JUDGMENT
V. Kameswar Rao, J. These petitions have been filed by the petitioner under Section 39 of the Arbitration and Conciliation Act, 1996 (`Act', for short) with the following common prayers:
"In the light of the aforementioned facts and circumstances, it is most respectfully prayed that this Hon'ble Court may be pleased to;
a) allow the present Petition by directing the sole arbitrator Mr. K.K. Gupta to pass/deliver the arbitral Award as expeditiously as possible on payment by the petitioner of the costs demanded by the sole arbitrator;
b) pass any such other and further orders as this Hon'ble Court may deem fit and proper, in the facts and circumstances of the case and in the interest of justice."
2. Before delving into the controversy in question it is pertinent to note the facts in brief. As the issue in both the petitions being identical, the facts of OMP (MISC.) (COMM) 377/2019 are being narrated. It is also clarified, the facts which are specific to OMP(MISC.) (COMM) 378/2019 shall be narrated separately. It is stated by the petitioner that on May 06, 2010, the respondent issued an NIT for a project titled "Construction on dwelling units including allied services for Officers, JCOs and Ors. at Bangalore" (`Project Bangalore', for short). The contract price for Project Bangalore was Rs. 163.27 crores and the period of completion was 25 months in five phases, from the date of handing over of the site. The scheduled date for handing over of the site and the date of commencement as per Work Order No. 1 was September 15, 2010.
3. It is stated by the petitioner that the respondent accepted the tender of the petitioner, vide Letter of Acceptance dated August 31, 2010, for a lump sum amount of Rs. 163.27 crores and allotted contract No. "CA NO. DGMAP/PH-II/PKG-21/03/04 of 2010-2011", in favour of the petitioner for Project Bangalore.
4. Owing to certain disputes that arose between the parties, the respondent terminated the contract for Project Bangalore on September 25, 2013. Thereafter, in terms of Clause 60 of the General Conditions of Contract (`GCC', for short), respondent No.1 appointed Mr. K. K. Gupta, Chief Engineer, Standing Panel of Arbitrators as the sole arbitrator to adjudicate upon the disputes between the parties vide Letter of Appointment dated December 26, 2014 (`Letter of Appointment', for short).
5. The sole arbitrator entered upon reference on January 14, 2015 and called upon the parties to submit documents as per the time scheduled laid down by him. Subsequently, the petitioner on August 12, 2015 filed its Statement of Claim, claiming an amount of Rs. 64,65,50,514/-. The petitioner on January 14, 2016 also submitted its rejoinder to Pleading in Defence. The respondent No.1 filed its Pleading in Defence to the Statement of Claim on February 16, 2016 as well as reply to the rejoinder of the petitioner was filed on August 23, 2016.
6. Later, on June 21, 2018, the sole arbitrator issued a letter to the parties stating that the arbitration proceedings were held up due to certain administrative issues with the designated appointing authority and that the sole arbitrator now intended to complete the arbitration proceedings in case both parties have no objection to it. Since respondent No.1 did not reply to the aforesaid letter, the sole arbitrator on August 06, 2018 issued another letter to the par
AI
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.