SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Jyoti Singh, J.
Dhoot Developers Pvt. Ltd. (JV) - Appellant
Versus
Totem Infrastructure Ltd. - Respondent
O.M.P. (COMM) 256 of 2017 & IA 3532 of 2019
Decided On : 17-11-2020




The court reaffirmed the unconditional nature of bank guarantees, emphasizing that misinterpretations may necessitate judicial intervention under Section 34 of the Arbitration Act.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Setting aside an arbitral award - The award favored respondent on claims for wrongful encashment of Performance Bank Guarantees (Claim 1) and Mobilization Advance bank guarantees (Claim 2), while rejecting counterclaims of petitioner - The tribunal's stance that guarantees were conditional was overruled; unconditional interpretation was established authoritative by sovereign court precedents. (Paras 37-46)

(B) Award principle on interpretation of contractual obligations - An arbitral tribunal's misjudgment on the nature of guarantees led to conclusions lacking evidentiary support, rendering the award liable for judicial intervention. (Paras 37-49)

(C) Submission acceptance and contractor obligations - Issues concerning performance delays and invocation of guarantees tied to compensatory claims emphasize contractor accountability within contractual deadlines. The ruling clarified both parties' obligations, underscoring temporal relation and collaborative accountability. (Paras 67-71)

Facts of the case:
Petitioner filed under Section 34 to contest the arbitral tribunal's decision favoring the respondent for claims of wrongful bank guarantee encashments and rejecting counterclaims of losses incurred due to delays, non-performance, and costs not substantiated. Court examined the failure of the tribunal to accurately interpret evidence and the contract terms under which the claims were made.

Findings of Court:
The respondent's entitlement to claims was questions; determining factors include the nature of the contract, performance issues, and evidence of payment allocations.

Issues: The issues addressed were the interpretation of the contractual guarantees, entitlement to claimed amounts, and the appropriateness of performance obligations.

Ratio Decidendi: The court found that the tribunal incorrectly ruled the nature of the bank guarantees as conditional, a matter impacting the respondent’s rights, thus failing to observe essential evidence supporting the petitioner's appeals against losses incurred.

Result: The award is partly upheld while rejecting claims 1 and 2, alongside counterclaims 2 and 7; both parties are permitted recourse to uphold claims independently.

JUDGMENT

1. Present Petition has been filed under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the `Act') for setting aside the impugned Award dated 04.03.2017 passed by the Arbitral Tribunal comprising of a Sole Arbitrator whereby the Tribunal allowed some claims of the Respondent herein and rejected all the counter claims of the Petitioner herein. The Petitioner herein was the Respondent before the Tribunal and is being referred to as the Petitioner while the Respondent who was the claimant is being referred to as Respondent for the sake of convenience.

2. Before adverting to the contentions of the parties, it is necessary to give a brief narrative of the facts. Petitioner is a Joint Venture of Dhoot Developers Private Limited and Bengal Silver Spring Project Limited and both are Companies incorporated under the Companies Act, 1956 and engaged in the business of executing Civil Construction Contracts.

3. Petitioner-JV was awarded a contract by the DG-MAP (Ministry of Defence) for the work of "Construction of Dwelling Units including Allied services for Officers, JCOs/ORs at Gandhi Nagar, Chiloda and Ahmedabad on 11.11.2010 with completion period being 25 months, commencing on 11.11.2010 and ending on 10.12.2012 (hereinafter referred to as `Master Contract').

4. As per the case set out in the petition, Petitioner started the work immediately on award of the contract despite some hindrances encountered at the sites and executed preliminary mobilization work. The mobilization period was 60 days under the Master Contract. Petitioner engaged the Respondent as sub-contractor to execute the work at Chiloda and Gandhi Nagar sites and a Letter of Intent (LOI) dated 21.02.2011 was issued. Value of work was Rs.113,79,35,257.10p. Petitioner continued working at Ahmedabad site till 18.05.2011 when the work at the said site was also sub-contracted to the Respondent and second LOI dated 18.05.2011 was issued amending the first LOI, by enhancing the scope of work thereunder. The value of enhanced work was Rs.87,65,58,994.67 p.

5. Work executed by the Petitioner at the sites, before the same were handed over to the Respondent, was measured and the agreed amount was Rs.68 Lakhs. Agreement dated 25.05.2011 was executed and signed between the parties regarding both the LOIs and is being referred to hereinafter as `Agreement'. The total value of the Agreement under both LOIs was thus Rs.205,04,89,860.66p (Gross value including Cess and WCT). Respondent furnished the following Bank Guarantees (hereinafter referred to as `PBGs') towards performance of its obligations under the Agreement:

S.No.BG No.DateAmount (Rs.)
1.2521FGPER00401101.03.20115,68,96,763/-
2.25211GPER01351102.07.20115,55,89,513/-
Total11,24,86,276/-

6. Respondent was entitled to interest bearing mobilization advance against Bank Guarantee equivalent to 10% of the Agreement value and was given the said amount. However, Respondent furnished BGs only for Rs.18,52,98,466/- as follows:

S. No.BG No.DateAmount (Rs.)
1.2521GPER00411101.03.201111,37,93,526/-
2.2521GPER01311102.07.20112,00,00,000/-
3.2521GPER01321102.07.20112,00,00,000/-
4.2521GPER01331102.07.20112,00,00,000/-
5.2521GPER01341102.07.20111,15,04,940/-
Total18,52,98,466/-

7. On the request of the Respondent, Petitioner gave additional advance to the tune of Rs.1.50 Crore in December 2011/January 2012 and the Respondent furnished the following BGs for total value of Rs.3 Crores, towards additional advance.

S.No.BG No.DateAmount (Rs.)
1.5264000191122.12.20111,00,00,000/-
2.5264000201128.12.20111,00,00,000/-
3.5264000211131.12.20111,00,00,000/-
Total3,00,00,000/-

8. The Respondent being conscious of the time lines as per the Master Contract as also the time that had already lapsed, agreed to complete the entire work under the Agreement, within the time frame originally stipulated i.e. upto 10.12.2012. The Master Contract stipulated various internal Milestones to be achieved b

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top