SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Prathiba M. Singh, J.
Gaurav Enterprises - Appellant
Versus
Union of India - Respondent
W.P.(C) 8485 of 2021 & CM Appl. 26248 of 2021
Decided On : 25-08-2021




An order under Sections 7Q and 14B can be deemed composite and appealable, against the separate treatment of these orders by the authority, aligning with the principles noted in relevant court rulings.

Headnote:(A) Employees' Provident Fund & Miscellaneous Provisions Act, 1952 - Sections 7Q and 14B - Challenge against refusal to stay interest imposed under Section 7Q on employer, contended as a composite order with damages under Section 14B, requires judicial review - CGIT's failure to address whether orders are composite not tenable - The High Court emphasized that separate orders despite common proceedings under 14B and 7Q should be treated as one for appealable purposes. (Paras 1-31)

(B) Judicial Review - Courts should ensure administrative authorities' actions do not obstruct statutory remedies available to employers - The critical examination of justice requires integration of related orders for efficient legal recourse. (Paras 23-24)

JUDGMENT

Prathiba M. Singh, J. (Oral)--This hearing has been done through video conferencing.

2. The present petition has been filed challenging order dated 3rd August, 2021 passed by the CGIT, by which the CGIT has refused to grant a stay in respect of the interest component imposed under Section 7Q of the Employees' Provident Fund & Miscellaneous Provisions Act, 1952 (hereinafter, "EPF Act") on the ground that no opinion can be formed at this stage as to whether the order which was passed by the original authority, i.e., the Regional Provident Fund Commissioner (hereinafter, "RPFC"), is a composite order under Sections 14B and 7Q of the EPF Act.

3. The brief background to this petition is that vide a common show- cause notice dated 23rd May, 2019, proceedings were initiated against the Petitioner under Sections 14B and 7Q of the EPF Act. The said show-cause notice relates to alleged defaults occurring during the period from 1st November, 2013 till 31st March, 2019. The show-cause notice commences with the title - "Summons to appear for hearing u/s 14B of the EPF and MP Act, 1952 (and order for payment of interest u/s 7Q for 01/11/2013 to 31/03/2019". In response to this show-cause notice, a common reply is filed by the Petitioner on 10th June, 2019. Thereafter, further submissions have also been made in the form of letters and documents on 11th June, 2019. After receipt of the documents, including challans which showed some deposits by the Petitioner, a revised notice was issued by the RPFC on 25th September, 2019, which is again a joint notice under Sections 14B and 7Q of the EPF Act. The revised computation is as under:

Account14B7QTotal
I432920428430527172256
II278671179706458377
X218411314252433609356
XXI12702282281209303
XXII248016024082
Total6921490453188411453374

    (Rupees One Crore Fourteen Lakh Fifty Thousand Three Hundred and Seventy Four Only)

4. Common replies to the revised notice were again filed by the Petitioner on various dates between 2nd January, 2020 to 3rd June, 2021. Hearings have been held before the authority on various occasions. A perusal of the order sheets shows that they clearly mention that these are "Proceeding under Section 14B & 7Q of the EPF & MP Act, 1952". Each order sheet which has been placed on record, dated 10th June 2019, 1st July, 2019, 9th January, 2020, 24th January 2020 and 10th September, 2020, shows that a common order has been passed under Sections 14B and 7Q of the EPF Act.

5. However, thereafter, the RPFC chose to pass separate orders under Section 14B and Section 7Q. Under Section 14B, the total demand raised was to the tune of Rs.69,21,490/-. The order under Section 14B is passed on 26th May, 2021 and communicated to the Petitioner on 15th June, 2021. The order under Section 7Q is also passed on 26th May, 2021 and communicated to the Petitioner on 15th June, 2021. The total amount computed under Section 7Q is Rs.40,81,884/-. Thus, both orders bear the same date and have been communicated to the Petitioner on the same date.

6. Considering the said two orders as composite orders, the Petitioner approached the CGIT. The CGIT, while admitting the appeal, imposed a stay on the assessment of damages under Section 14B, subject to pre-deposit of 10% of the assessed amount of damages. However, insofar as the order under Section 7Q is concerned, no stay was granted. The operative portion of the CGIT's order is extracted herein below:

    "Hence in this case it is directed that there should be an interim stay on the execution of the impugned order levying damage, pending disposal of the appeal. But the said interim order cannot be unconditional. The appellant is directed to deposit 10% of the assessed amount of damage through challan within four weeks from the date of communication of this order as a precondition for stay pending disposal of the appeal. It is made clear that there would be no stay on the interest assessed by the commissioner as no opinion can be formed at this stage whether i

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top