SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Delhi Buildtech Pvt. Ltd. - Appellant
Versus
Satya Developers Pvt. Ltd. - Respondent
O.M.P. (T) (COMM.) 83 of 2021 and IA No. 10800 of 2021
Decided On : 21-10-2021




The court established that an arbitrator appointed by an ineligible individual cannot act, and waivers of objections regarding ineligibility must be expressed in writing, not inferred by conduct.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 12(5), 14, and 15 - Petition for termination of arbitrator's mandate - Court found that the Managing Director who appointed the arbitrator was ineligible to act, making the appointment void ab initio. Waiver of ineligibility must be by express written agreement, not inferred by conduct. (Paras 12, 16, 21)

(B) The arbitration agreement required mutual consent for appointment; unilateral appointment breached procedural fairness. (Paras 11, 12)

Facts of the case:
Disputes arose regarding work orders, leading to a legal notice claiming excess payments. Petitioners sought termination of arbitrator's mandate alleging ineligibility due to unilateral appointment.

Findings of Court:
The court held that the unilateral aspect of the appointment violated the A&C Act, thus entitled the petitioner to have the mandate terminated.

Issues: Whether the unilateral appointment of the arbitrator was valid and if the petitioner waived its objections.

Ratio Decidendi: The court reasoned that an arbitrator appointed by an ineligible person cannot act; waiver must be express in writing per Section 12(5).

Result: Petition allowed; new arbitrator appointed.

Table of Content
1. petition for terminating arbitral mandate. (Para 2 , 7)
2. dispute background and arbitration initiation. (Para 3 , 5 , 6)
3. arguments regarding arbitrator's eligibility. (Para 8 , 9)
4. discussion on waiver of objection to arbitrator. (Para 10 , 14)
5. ineligibility of appointed arbitrator. (Para 12 , 13)
6. supreme court clarification on arbitration ineligibility. (Para 18 , 22)
7. (Para 23 , 24 , 25)

JUDGMENT

Vibhu Bakhru, J. (Oral)--The matter is taken up today as 18.10.2021 was declared a holiday.

2. The petitioner has filed the present petition under Sections 14 & 15 of the Arbitration and Conciliation Act, 1996 (hereafter the `A&C Act') praying that the mandate of the Arbitral Tribunal be terminated and an independent and impartial arbitrator be appointed in substitution of the learned Arbitrator.

3. The respondent had issued a Work Order dated 30.11.2012 in respect of Civil, Structural & Finishing Works for Tower Tl, T2, T7, Club, STP & other Non Tower Areas and other works in favour of the petitioner. Thereafter, on 04.02.2014, the respondent issued another Work Order for the balance Civil, Structural & Finishing Works for Tower T8, T6, T5, T4 and T3 & corresponding Non Tower Areas of the project known as "The Hermitage", which was being developed by the respondent. On 08.10.2014 and 19.03.2016, addendums to the Work Order were issued. In the meanwhile, the respondent issued another Work Order dated 15.02.2016.

4. Disputes arose between the parties in respect of the said Work Orders.

5. On 24.07.2018, the respondent issued a legal notice calling upon the petitioner to pay a sum of Rs.6,40,26,263/- claiming that the said amount was paid in excess of what was due to the petitioner. The petitioner responded to the said notice, whereby it disputed the assertions made by the respondent and also demanded a sum of Rs.6,23,22,425/- as the balance amount due to it. On 19.03.2019, the respondent issued another legal notice reiterating its demand as made in the notice dated 24.07.2018 and additionally, also demanded a sum of Rs.1,00,00,000/- as damages. In view of the aforesaid disputes, by a letter dated 26.04.2019, the Managing Director of the respondent appointed an Advocate as the Sole Arbitrator to adjudicate the disputes between the parties.

6. Thereafter, the learned Arbitrator entered upon reference. The respondent filed its Statement of Claims and the petitioner filed its Statement of Defence. The petitioner also filed its counter-claims.

7. On 15.02.2020, the petitioner filed an application seeking recusal of the learned Arbitrator on the ground that he was ineligible to act as such. The learned Arbitrator rejected the said application by an order dated 22.02.2021.

8. Mr Grover, learned counsel appearing for the petitioner relies on the decisions of the Supreme Court in TRF Ltd. v. Energo Engineering Projects Ltd., (2017) 8 SCC 377; Bharat Broadband Network Limited v. United Telecoms Limited, (2019) 5 SCC 755; and Perkins Eastman Architects DPC & Anr. v. HSCC (India) Ltd., 2019 SCC OnLine SC 1517 in support of his contention that the learned Arbitrator is ineligible to act as an arbitrator as he was unilaterally appointed by the Managing Director of the respondent. The petitioner has also referred to the decision of a Coordinate Bench of this Court in Proddatur Cable TV Digi Services v. Siti Cable Network Limited, (2020) 267 DLT 51.

9. Ms Kaadambari, learned counsel appearing for the respondent submitted that the petitioner acquiesced in the appointment of the Arbitrator and had also participated in the arbitration proceeding without any reservations. The petitioner did not raise any objection regarding the ineligibility of the learned Arbitrator at the material time. She submitted that in the aforesaid circumstances, it must be construed that the petitioner had waived its objection if any. She also submits that the objections raised by the petitioner is at a much belated stage and there

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top