IN THE HIGH COURT OF DELHI
Neena Bansal Krishna, J.
National Projects Construction Corporation Ltd. - Appellant
Versus
Konkan Railway Corporation Ltd. - Respondent
O.M.P. (T) (COMM.) 98 of 2021 & I.A. 12793 of 2021 (Stay)
Decided On : 11-11-2022
| Table of Content |
|---|
| 1. termination of arbitral tribunal's mandate (Para 1 , 2 , 3) |
| 2. disputes arising from project execution (Para 4 , 5 , 6 , 7) |
| 3. issues with co-arbitrators' eligibility (Para 8 , 9 , 10 , 11 , 12) |
| 4. challenges to tribunal composition (Para 13 , 14 , 15) |
| 5. petitioner's claim of non-functional tribunal (Para 20 , 21 , 22) |
| 6. procedure in case of inability to act (Para 25 , 26) |
| 7. distinction between mandate termination and arbitration proceedings (Para 29 , 30 , 31) |
| 8. fee structure and arbitrators' responsibilities (Para 37 , 38 , 39) |
| 9. impartiality and independence in arbitrator appointments (Para 46 , 48 , 49) |
| 10. appointment of sole arbitrator under specific conditions (Para 50 , 51 , 52 , 53) |
| 11. court's appointment of an independent arbitrator (Para 60 , 61 , 62 , 63) |
JUDGMENT
Neena Bansal Krishna, J. The petitioner has filed under Sections 14(1) and 15(2) of the Arbitration and Conciliation Act, 1996(hereinafter referred to as "A & C Act, 1996") seeking termination of the mandate of the Arbitral Tribunal and appointment of retired judge/s of the High Court as co-arbitrators and also as presiding arbitrator.
2. Facts in brief are that the petitioner-M/s. National Projects Construction Corporation Ltd. was awarded the Tender for construction of BG Single Line Tunnel No. 5 (Bakkal Tunnel) from Km. 46.040 to Km. 48.940 on the Katra - Laole Section of USBRL Project. The estimated cost of the Tender was of Rs.171,11,15,718/-. The original date of the work commencement was in March, 2004 and the completion period was 34 months i.e., 31st December, 2006. An extension of time was requested up to 31st December, 2012 and the ad hoc extensions were granted up to 31st December, 2008 and 31st July, 2010.
3. It is submitted that during the execution of work, various disputes arose between the parties and in terms of the Clauses 53, 54 and 55 of Special Conditions of Contract Agreement and Clause 64 of General Conditions of Contract. The respondent and the petitioner entered into a Supplementary Agreement of Arbitration.
4. A set of claims up to 31st January, 2008 (hereinafter referred to as "Claims Set No.1") were taken up for adjudication by the then constituted Arbitral Tribunal, comprising of Mr. Y.P. Singh, Mr. H.S. Yadav and Mr. S. Balachandran as the Arbitrators in the year of January, 2008 and an Award dated 21st February, 2012 was pronounced which was received by the petitioner on 01st March, 2012. The Award was challenged under Section 34 of A & C Act, 1996 and is pending at the stage of arguments.
5. Since January, 2008, despite the disputes having arisen between the parties and the petitioner having suffered huge losses, it continued to perform the execution of the work until the issuance of Order about the pending works on 25th July, 2008. The respondent taking note of the facts that the Contract in its present form is non-performable proceeded to foreclose the Contact w.e.f. 28th January, 2010. It re-issued NIT in May, 2010 for execution of the balance work of Tunnel T-5 works by incorporating modified methodology, new bill of quantity at an estimated cost of Rs.224.09 crores with several extra items and with a completion time of 48 months for execution of balance works.
6. In the peculiar circumstance, it was asserted that the bid floated in the year 2004 and the foreclosure of Contract was based on mis-projections of information, unrealistic quantities and impracticable methodologies and targets and the Contract in its present form, became a non-performable one.
7. The petitioner suffered losses since 01st February, 2008 which is subsequent to the foreclosure of the Contract which was found non-performable. The petitioner submitted compensation in three different groups for the consideration of the respondent, but the same was rejected.
8. Because of the differences and disputes, a Tribunal comprising of three Members was constituted for settlement of disputes and Statement of Claims was filed befor
Arbitrators must be impartial and capable of performing their duties; prolonged inaction in arbitration proceedings justifies termination of their mandate.
An arbitrator's mandate can be terminated when they fail to act without undue delay; new appointments must ensure impartiality as per updated legal standards.
Disqualified arbitrators cannot appoint successors; unilateral requests do not waive statutory disqualifications under the Arbitration and Conciliation Act.
The appointment of an arbitrator must comply with Section 12(5) of the Arbitration & Conciliation Act, ensuring independence and impartiality, regardless of when the arbitration proceedings were init....
The court affirmed that the claimant must secure the necessary Airport Entry Permits and upheld the arbitration award, ruling no breach by the respondent; consent regarding the arbitrator's appointme....
The court established that an arbitrator appointed by an ineligible individual cannot act, and waivers of objections regarding ineligibility must be expressed in writing, not inferred by conduct.
The main legal point established is the requirement to substantiate grounds for termination of the Arbitral Tribunal's mandate under Section 14 of the Arbitration & Conciliation (Amended) Act, 2015, ....
Point of law: As per the legal position settled by the Supreme Court in catena of judgments, the High Court has the jurisdiction under Section 11(6) of the said Act to nullify the appointments made b....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.