SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
C. Hari Shankar, J.
Faridabad Implements Private Limited - Appellant
Versus
Mypreferred Transformation and Hospitality Private Limited - Respondent
Arb. A. (COMM.) 68 of 2021 & I.A. 15104 of 2021, Arb. A. (COMM.) 71 of 2021 & I.A. 15542 of 2021, I.A. 15543 of 2021 and Arb. A. (COMM.) 72 of 2021 & I.A. 15547 of 2021, I.A. 15548 of 2021
Decided On : 03-12-2021




The court upheld an arbitrator's discretion under Section 17 for interim security but clarified the need to reconsider the amount based on specific claims presented.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 17 - Arbitration Proceedings - Dispute arose from lease agreements where the arbitrator directed Respondents to furnish a security of Rs.10 crores via bank guarantee. The Claimant disputed the amount as insufficient, arguing justification was needed for the arbitrator's decision. The arbitrator held discretion in interim measures which should not be altered lightly by the court unless exceptional circumstances are presented. (Paras 10-28)

(B) The arbitrator must consider the financial position of the parties, yet current claims against Respondents were significant. Claimant demonstrated sufficient prima facie case for security to protect the interests pending final adjudication. (Paras 29-42)

Facts of the case:
Disputes arose from two lease deeds involving a delay in rental payments, leading to the termination of the lease and subsequent arbitration. The Claimant sought Rs.15,09,80,086/- from Respondents. (Para 6)

Findings of Court:
The learned arbitrator granted a security amount of Rs.10 crores which was challenged by the parties as insufficient. The court upheld the discretion of the arbitrator while remitting the matter for reconsideration of the quantum of security specifically. (Paras 10-28)

Issues: Main issues included justification for the amount of security ordered and the nature of the claims made against the Respondents.

Ratio Decidendi: The court emphasized respect for the arbitrator's discretion in interim orders unless a significant case is made for overriding that discretion. The rationale for securing interests in arbitration is paramount and merits careful consideration. (Paras 36-39)

Result: The order of security was upheld but remitted for re-examination regarding quantum.

Table of Content
1. background of lease agreements (Para 1 , 2 , 3 , 4 , 5 , 6)
2. claims and applications before the arbitrator (Para 7 , 8 , 9 , 24)
3. discretion of arbitrator regarding security (Para 17 , 18 , 20 , 21)
4. final directions and disposition of appeals (Para 27 , 28 , 29)

JUDGMENT (Oral)

1. M/s Faridabad Implements Pvt. Ltd. (FIPL), MyPreferred Transformation And Hospitality Pvt. Ltd (MPTHPL) and OYO Hotels and Homes Pvt. Ltd. (OHHPL) were the claimant, Respondent 1 and Respondent 2 respectively, before the learned arbitrator in the proceedings from which the present appeals emanate.

2. The dispute emanated out of two lease deeds. The first lease deed dated 11th December, 2018 was executed between FIPL and OHHPL. Under the said lease deed, OHHPL leased out, to FIPL, the premises at C-18, Friends Colony East, New Delhi for a period of nine years, of which five years were to be treated as a lock in period, within which the contract could not be terminated and, if terminated, would entail penal consequences. The monthly rent of the premises was fixed at Rs.17,75,000/- for the first year, to be increased by 4% every succeeding year.

3. A second lease deed, dated 1st October, 2019, was executed between FIPL and MPTHPL. MPTHPL, the petition asserts, is a group company of OHHPL, and OHHPL had expressed its intent to transfer the lease in favour of MPTHPL, resulting in the execution of the second lease deed on 1st October, 2019. The terms of the second lease deed were the same as those of the first, except that the period of lease was five years, with the entire period being treated as a lock in period.

4. From February, 2020, MPTHPL stopped paying rent. On 24th March, 2020, the lease deed was terminated by MPTHPL.

5. The disputes which thus arose between the parties were referred, by this Court, vide order dated 5th August, 2020, to arbitration by the learned arbitrator, who happens to be a retired Judge of the Supreme Court of India. Before the arbitrator, as already noted hereinabove, FIPL was the claimant, MPTHPL was Respondent 1 and OHHPL was Respondent 2.

6. In its statement of claim before the learned arbitrator, FIPL claimed Rs.15,09,80,086/- as the principal amount due from MPTHPL and OHHPL.

7. OHHPL preferred an application, before the learned arbitrator, under Section 16 of the 1996 Act, seeking to be deleted from the proceedings, on the ground that it was not a party to the second lease deed. This application was, however, rejected by the learned arbitrator by order dated 27th January, 2021, which is not subject matter of challenge.

8. FIPL moved an application, before the learned arbitrator, under Section 17 of the 1996 Act, for securing its claim.

9. By the impugned order dated 20th September, 2021, the learned arbitrator directed furnishing, by Respondents 1 and 2, of security of Rs.10 crores by way of bank guarantee. The reasoning preceding this direction, as contained in paras 20 to 22, 24, 26, 27, 30 to 32, 34 and 36 to 42 may be reproduced thus:

    "20. The contentions urged by the learned Counsel for the parties inter-alia give rise to the points: (i) Whether the Claimant has failed to produce the documents as alleged by the Respondents and whether the Claimant has committed default in performing its obligations under the lessee deeds as contended by the Respondents; (ii) Whether the `breach and cure' notice issued by Respondent No. 1 was justified and in terms of the lease agreement; (iii) Whether the Claimant has furnished the documents as contended by the Claimant; (iv) Whether or not the Claimant furnished the documents to the Respondent thereby complying with the terms of its obligations; and (v) How the Respondents have been running the hotel from 11.10.2018 till the Respondents vacated/allegedly abandoned the premises. The above points/questions could be determined only at the time of final hearing of the matter when the parties adduce oral and further documentary evidence and adv

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top