IN THE HIGH COURT OF DELHI
C. Hari Shankar, J.
Delhi Transport Infrastructure Development Corporation Ltd. - Appellant
Versus
Aom Advertising Pvt. Ltd. - Respondent
O.M.P. (COMM) 291 of 2021 & I.A. 12778 of 2021, I.A. 12779 of 2021, I.A. 12780 of 2021
Decided On : 07-12-2021
| Table of Content |
|---|
| 1. application under section 34 of the arbitration act. (Para 1 , 2 , 4 , 5) |
| 2. consolidation of claims in arbitration disputes. (Para 3 , 13 , 14) |
| 3. the necessity for separate arbitrations under distinct agreements. (Para 15 , 18 , 24) |
| 4. court's intervention in arbitrator's decision. (Para 31 , 32) |
| 5. quashing of the order to consolidate claims. (Para 33 , 34 , 36) |
1. This petition, under Section 34 of the Arbitration and Conciliation Act, 1996 ("1996 Act"), at the instance of the Delhi Transport Infrastructure Development Corporation Ltd. (DTIDC), assails order dated 10th September, 2021, passed by a three-member Arbitral Tribunal, rejecting the application, under Section 16 of the 1996 Act, preferred by the petitioner before it.
2. The disputes, which arise out of three Concession Agreements dated 5th December, 2017, executed between the petitioner and the respondent, are presently in seisin before the learned Arbitral Tribunal. The respondent is the claimant before the learned Arbitral Tribunal and the petitioner is the respondent before it.
3. The respondent, in its Statement of Claim before the learned Arbitral Tribunal, consolidated its claims in respect of the three Concession Agreements. The petitioner, thereupon, moved an application under Section 16 of the 1996 Act, objecting to the consolidation of the claims and contending that the learned Arbitral Tribunal would have to treat each claim as a separate arbitrable dispute, and therefore, could not consolidate the claims. It is this application that has come to be dismissed by the order impugned in the present case.
4. Mr. Amiet Andlay, learned counsel for the petitioner, submits that he has no objection to the respondent filing separate Statements of Claims before the learned Arbitral Tribunal qua its claims in respect of each Concession Agreement and the learned Arbitral Tribunal treating them as a separate dispute for the purpose of arbitration. He, however, opposes the consolidation of the claims as has been done by the learned Arbitral Tribunal and, therefore, submits that the rejection of his Section 16 application was erroneous.
5. The Concession Agreements between the petitioner and the respondent relate to marketing, operation and maintenance of various bus queue shelters (BQS). The shelters were divided into three Zones; Zone-2, Zone-4 and Zone-5. Though, initially, a consolidated Request For Proposal (RFP) was issued by the petitioner, inviting tenders for service providers for all the three Zones, thereafter, consequent on the respondent emerging as the successful bidder, three separate Concession Agreements were executed between the petitioner and the respondent, one for each Zone, all of which were dated 5th December, 2017.
6. Two Bank guarantees, for each zone, were also furnished by the respondent, as required by each Concession Agreement.
7. The petitioner alleges that the respondent was in default of licence fee payable under the Concession Agreements, whereupon the petitioner issued notices to the respondent on 6th June, 2020, 18th June, 2020 and 8th July, 2020. These notices, it is asserted, were separately issued for each Concession Agreement, i.e. for each zone.
8. Each Concession Agreement contains its own arbitration clause, though they were identical. The arbitration clause may be reproduced thus:
"23.1 Amicable Resolution
Save where expressly stated to the contrary, in this Agreement, any dispute, difference or controversy of whatever nature between the Parties, howsoever arising under, out of or in relation to this Agreement (the "Dispute") shall in the first instance be attempted to be resolved amicably in accordance with the procedure set forth in sub-clause (b) below.
(b) Either Party may require such Dispute to be referred to the Chairman DTIDCL and the Chief Executive Officer of the Concessionaire for the time being, for amicable settlement. Upon such reference, the two shall meet at the e
Separate arbitration proceedings are mandated for distinct agreements unless the parties explicitly agree to consolidate them, aligning with the precedent established in Duro Felguera.
The court's decision emphasized the limited scope of interference with arbitral awards and the prohibition on re-appreciating evidence and challenging the merits of the award under Section 34 of the ....
Disputes arising from separate contracts necessitate distinct arbitration references as mandated by rules; failure leads to award invalidation.
A single arbitration application for multiple sub-contract agreements is not maintainable when the contracts are separate and distinct, and do not arise from a single commercial project.
Point of Law : Arbitration - Concession Agreement – Maintainability of writ - Power under Article 227 of Constitution in a rare and exceptional circumstance - When an alternative and efficacious reme....
Article 20 of the Concession Agreement constitutes an arbitration agreement despite its mediation label, featuring binding decision-making attributes and fulfilling statutory requirements.
Arbitral awards may be composite if the issues relate closely, but interest must adhere to contractual terms.
(1) Construction of contract is within jurisdiction of Tribunal and merely because another view is possible, Court cannot interfere with such construction and substitute its own view.(2) If an arbitr....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.