IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Delhi Jal Board - Appellant
Versus
Mohini Electricals Ltd. - Respondent
O.M.P. (COMM) 22 of 2020 and IA Nos. 592 of 2020, 595 of 2020, 3632 of 2020, 7029 of 2020 & 7030 of 2020
Decided On : 04-07-2022
| Table of Content |
|---|
| 1. background of the arbitration dispute (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20) |
| 2. details of claims and arbitration award (Para 21 , 22 , 23 , 24) |
| 3. arguments presented by both parties (Para 25 , 26 , 27 , 28 , 29) |
| 4. court's evaluation of claims and limitations (Para 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46 , 47) |
| 5. analysis of financing charges and contract terms (Para 48 , 49 , 50 , 51 , 52 , 53 , 54 , 55 , 56 , 57) |
| 6. final judgment and dismissal of petition (Para 58 , 59) |
JUDGMENT
Vibhu Bakhru, J.
1. Delhi Jal Board (hereinafter `the DJB') has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter `the A&C Act') impugning an arbitral award dated 02.09.2019 (hereinafter the `impugned award') delivered by an Arbitral Tribunal comprising of Shri Anand Kumar as the Sole Arbitrator (hereinafter the `Arbitral Tribunal').
2. The impugned award was rendered in the context of disputes that had arisen between the parties in relation to the agreement dated 28.11.2003 (hereinafter the `Agreement').
Factual context
3. In April 2003, the DJB invited tenders from bidders for "Construction of various reservoirs at different location in TYA Areas, Delhi of Delhi Jal Board." (hereinafter `the Project'). The construction work included civil works, supply, installation, testing and commissioning of electrical and mechanical equipment etc.
4. Pursuant to the said notice inviting tenders, a consortium of M/s Mohini Electricals Ltd. (hereinafter `the respondent'), M/S Jes Engineering Company Pvt. Ltd. and GSJ Envo Ltd. submitted its bid for the Project with the respondent acting as the consortium leader. By a Work Order dated 30.09.2003, the work for executing the Project was awarded to the respondent on behalf of the consortium. The total contract value was agreed at Rs.28,49,72,521/-, which comprised of a sum of Rs.18,63,11,936/- for civil works and a sum of Rs.9,86,60,585/- for E&M works on turnkey basis.
5. Thereafter, on 28.11.2003, the parties entered into the formal Agreement. Under the terms of the Agreement, the Project was to commence from the 14th day of the issuance of the Work Order and was to be completed within eighteen months thereafter. Thus, the date of commencement was stipulated as 14.10.2003 and the date of completion was scheduled as 13.04.2005 with a further period of sixty months provided for operation and maintenance.
6. Further, the Agreement also provided that if the respondent failed to commence the Project on the scheduled date, for reasons other than those as provided in the Agreement, the DJB would be entitled to levy financing charges on advance payment till the time the Project commenced.
7. The DJB states that the respondent started civil works on selective sites on 19.11.2003. By a letter dated 03.12.2003, the DJB informed the respondent that the Project started only on one location on the scheduled date and the physical progress of the Project was negligible. Further, the respondent was required to obtain a number of approvals before commencement of the concrete works, which had not been obtained till date.
8. Thereafter, on 10.12.2003, the respondent gave a bank guarantee dated 06.12.2003 for a sum of Rs.1,86,31,194/- and on 29.01.2004, furnished another bank guarantee dated 09.12.2003, for a sum of Rs.98,66,059/- against mobilization advance provided by the DJB.
9. By a letter dated 21.02.2004, the respondent alleged that the DJB had breached the Agreement. The DJB responded by a letter dated 01.04.2004, countering the said allegation and asserting that the delay was attributable to the respondent as it had submitted the bank guarantee on 10.12.2003 after a significant delay.
10. By a letter dated 20.04.2004, the DJB complained about the poor arrangement at the location sites due to which, permission to commence reinforced cement c
The arbitration award was upheld as the claims were not barred by limitation, with the court confirming the Arbitral Tribunal's findings on delay responsibility and contractual obligations.
The court upheld the award of financing charges and simple interest as per the contract, finding that the claims were not barred by limitation and that the delay in completion of works was not attrib....
The arbitral award's findings on limitation are upheld, while claims lacking substantiation and unfounded financing charges are rejected as contrary to contract terms.
A party's unilateral appointment of an arbitrator is impermissible to ensure impartiality; the appointed arbitrator must not be influenced by party interests.
The main legal point established in the judgment is that the unilateral appointment of an Arbitrator by a party with an interest in the matter is impermissible, as it could compromise the impartialit....
Arbitration - Arbitral Award - Form and contents of arbitral award - DDA issued a public notice for Auction of prime plots on freehold basis for construction of Hotels in Delhi - The mandate under Se....
The main legal point established in the judgment is the importance of ensuring the independence and impartiality of arbitrators in the appointment process, as emphasized in relevant decisions of the ....
The arbitral tribunal's decision to deny claims for damages due to lack of supporting evidence is valid under Section 34 of the Arbitration and Conciliation Act, emphasizing minimal judicial interfer....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.