IN THE HIGH COURT OF MEGHALAYA AT SHILLONG
SANJIB BANERJEE, CJ, W. DIENGDOH, J.
Public Works Department (National Highway) – Appellant
Versus
M/s BSC-CC & JV, 6-2-913/914 – Respondent
Arb. A. No. 6 of 2023
Decided On : 19-06-2023
| Table of Content |
|---|
| 1. arbitration challenge under section 37. (Para 1 , 2) |
| 2. details of the contractual relationship and claims. (Para 3 , 4 , 5) |
| 3. challenges to the dreb decisions. (Para 6 , 11) |
| 4. contractor's claims for delayed payments. (Para 8 , 9 , 10 , 12) |
| 5. nomination of arbitrators and acceptance of claims. (Para 13 , 15 , 16 , 17) |
| 6. constitution of the arbitral tribunal. (Para 18 , 26 , 35) |
| 7. disputes and their arbitrability. (Para 19 , 22 , 24 , 27 , 30 , 31) |
| 8. significance of contractor’s payments and obligations. (Para 29 , 32 , 33) |
| 9. conclusion on costs and dismissal of the appeal. (Para 34 , 39) |
JUDGMENT :
SANJIB BANERJEE, CJ.
1. This is a complete waste of time and a reckless exercise undertaken by an irresponsible appellant. The challenge here is under Section 37 of the Arbitration and Conciliation Act, 1996 to an order dated May 17, 2023 passed by the Commercial Court, Shillong on a plea under Section 34 of the Act challenging an arbitral award rendered on July 27, 2021.
2. The arbitral award was made on an application under Section 31 (6) of the Act. Such provision empowers an arbitral tribunal to pass an interim arbitral award in respect of any matter that may be covered by a final arbitral award.
3. The appellant herein engaged the respondent for the two-laning of the highway from Shillong to Nongstoin and beyond, possibly, up to Tura. The claims in the reference pertained to the delay, disruption and prolongation of the contract together with interest on account of delayed payments and the like. There is no dispute that there was delay in the execution of the contract and the appellant herein submits that it was for such reason that the value of the contract had been revised and claims on account of interest and the like for previous delayed payments had been subsumed in the enhanced value of the contract.
4. The contract itself provided for a two-tier mechanism for the resolution of disputes. In such context, clause 25 of the contract is of some relevance:
25.1. The Dispute Review Expert (Board) shall give a decision in writing within 28 days of receipt of a notification of a dispute.
25.2. The Dispute Review Expert (Board) shall be paid daily at the rate specified in the Contract Data together with reimbursable expenses of the types specified in the Contract Data and the cost shall be divided equally between the Employer and the Contractor, whatever decision is reached by the Dispute Review Expert. Either party may give notice to the other to refer a decision of the Dispute Review Expert to an Arbitrator within 28 days of the Dispute Review Expert’s written decision. If neither party refers the dispute to arbitration within the next 28 days, the Dispute Review Expert’s decision will be final and binding.
25.3. The arbitration shall be conducted in accordance with the arbitration procedure stated in the Special Conditions of Contract.”
5. Despite the value of the contract being enhanced, the contractor sought to assert a claim on account of delayed payments of its regular bills. In accordance with clause 25 of the contract, the Dispute Review Expert Board considered such claim and, by a reasoned decision passed on September 25, 2016, found that the contractor was entitled to a substantial sum. Upon the contractor requiring the Dispute Review Expert Board (DREB) to re-examine its claim since several aspects of the delay had not been accounted for, a revised decision was passed by the DREB on February 19, 2017 finding that the contractor was entitled to a sum in excess of Rs.117 crore on account of interest for delayed payments and on account of unpaid bills or delayed payments for bitumen.
6. In accordance with clause 25.2 of the contract, such decision of the DREB ought to have been challenged by the appellant employer within 28 days. However, even if it be accepted for argument’s sake that the abridgement of the time would fall foul of Section 28 of the CONTRACT ACT , 1872, what is evid
Setting aside arbitral award – Courts, while adjudging whether an arbitration award calls for interference has to be conscious that Arbitrator is sole Judge of facts – Unless an error of law is shown....
An arbitral award may be set aside if made after expiry of the arbitrator's mandate or due to undue delay impacting its validity, reflecting violations of natural justice.
Inconsistent findings across arbitral awards do not provide grounds for setting aside an award under Section 34 of the Arbitration & Conciliation Act, 1996.
The court upheld the award of financing charges and simple interest as per the contract, finding that the claims were not barred by limitation and that the delay in completion of works was not attrib....
The court confirmed the validity of the Arbitrator's findings regarding excess work claims and the correct application of interest, highlighting that overlapping interest claims were erroneous.
The Court's power while exercising jurisdiction under Section 37 of the Act is limited, and it cannot undertake an independent assessment on the merits of the Award.
Grant of interest – Power of Arbitrator to award pre-reference and pendente lite interest is not restricted when agreement is silent on whether interest can be awarded or does not contain a specific ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.