IN THE HIGH COURT OF DELHI
Prateek Jalan, J.
Supreme Panvel Indapur Tollways Private Limited - Appellant
Versus
National Highways Authority of India - Respondent
Arb. A. (COMM.) 75 of 2022 & I.A. 17778 of 2022, I.A. 18288 of 2022, I.A. 20313 of 2022
Decided On : 20-12-2022
| Table of Content |
|---|
| 1. disputes over contract completion (Para 2 , 3 , 4 , 5 , 6 , 7) |
| 2. tribunal's prima facie findings (Para 11 , 12 , 13 , 14) |
| 3. arguments on entitlement to relief (Para 15 , 16 , 17 , 18 , 19 , 20 , 21) |
| 4. determinability and implications (Para 39 , 40 , 41) |
| 5. conclusion of the appeal (Para 45 , 46) |
JUDGMENT
Prateek Jalan, J.
1. The present appeal under Section 37(2)(b) of the Arbitration and Conciliation Act, 1996 [hereinafter, "the Act"] is directed against an order dated 23.10.2022 by which a three-member Arbitral Tribunal [hereinafter, "the Tribunal"] has rejected an application of the appellant for interim measures under Section 17 of the Act.
I. Factual Background:
2. The Tribunal is in seisin of disputes between the parties under a Concession Agreement dated 21.01.2011 [hereinafter, "CA"] with regard to "Four Laning of Panvel-Indapur Section of NH-17 from KM 0.000 to KM 84.000 in the State of Maharashtra", on Build Operate Transfer [hereinafter, "BOT"] basis.1 The original period for completion of the work was 910 days, the scheduled date of completion being 16.06.2014. The CA envisaged a concession period of 21 years from 19.12.2011 and payment of an additional concession fee by the appellant. The relevant clauses of the CA, cited in the course of arguments, are set out later in this judgment.
3. The project has admittedly not achieved completion within the time originally stipulated. The substantive dispute between the parties relates to the responsibility for the delay. There is considerable material on record in this connection, of which the relevant minutes of meetings and correspondence will be referred to at the appropriate juncture. The appellant alleges that deviation from the completion schedule occurred on account of the respondent not being able to ensure Right of Way, which was its responsibility under Article 10 of the CA. Moreover, certain delays occurred as the scope of work was increased by the respondent unilaterally. One of the principal contentions of the respondent on the other hand, is that the appellant was unable to infuse sufficient funds for timely completion of the project and that the respondent was compelled to invest a sum of Rs.540 crores in the project under its One Time Fund Infusion Scheme [hereinafter, "OTFIS"].
4. The progress of the project was monitored from time to time by the OTFIS Review Committee and extensions of time for completion were also granted. The last of the extensions, granted on 11.08.2020, was until 31.03.2021.
5. The respondent issued a notice of intention to terminate dated 16.10.2020 [hereinafter, "NITT"], wherein it referred to the correspondence between the parties and contractual clauses to assert that the appellant had failed to achieve progress in the project as envisaged, that it had failed to infuse requisite funds and that the respondent was, therefore, entitled to terminate the CA under Clause 37.1.1 (c), (e) and (g) thereof. After considerable correspondence and meetings between the parties, the CA was ultimately terminated on 17.11.2021.
6. The appellant approached this Court, under Section 9 of the Act, for stay of termination of the CA in anticipation of arbitration proceedings [O.M.P.(I)(COMM) 382/2021]. Several orders were passed by this Court in the course of these proceedings, and an appeal arising therefrom [FAO(OS)(COMM) 52/2022]. It is not necessary for the purposes of the present appeal to enumerate those orders in detail. Suffice it to state that by virtue of an order of the learned Single Judge dated 08.02.2022, read with orders of the Division Bench dated 16.03.2022 and 21.03.2022, the appellant's application under Section 9 of the Act was directed to be treated as an application under Section 17 of the Act before the Tribunal, which had been constituted in the interregnum. However, as the respondent had called for fresh tenders pursuant to the impugned termination, the Division Bench directed that until the Trib
The court affirmed that the Tribunal's rejection of the appellant's request for interim measures was valid due to established insufficient funding and non-compliance, affirming limited grounds for in....
The court found that the contract in question is in the nature of a commercial contract and cannot be enforced specifically under the Specific Relief Act. The Tribunal held that NHAI's exercise of po....
The main legal point established in the judgment is that in the case of a determinable contract, no injunction against termination and enforcement of the contract can be issued.
The non-consideration of a clause in the Concession Agreement by the Arbitral Tribunal is not a ground to set aside the arbitral award, unless it is an error that goes into the root of the award and ....
The court confirmed that judicial interference in arbitral awards is limited to cases of patent illegality or perverse findings, respecting the finality of arbitration.
The court established that termination rights under a Concession Agreement are active concurrently with suspension rights, allowing for termination upon failure to cure defaults without requiring a w....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.