SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Manmohan, Asha Menon, JJ.
National Highways Authority of India - Appellant
Versus
Panipat Jalandhar NH-I Tollway Pvt. Ltd. - Respondent
FAO(OS) (COMM) 55 of 2021 & C.M. Nos. 11596-11597 of 2021
Decided On : 13-04-2021




The court established that termination rights under a Concession Agreement are active concurrently with suspension rights, allowing for termination upon failure to cure defaults without requiring a waiting period as incorrectly stated by the lower court.

Headnote:(A) Contract Law - Concession Agreement - Articles 36 and 37 - Dispute arose over the rights and obligations of parties in termination and suspension scenarios - NHAI's termination notice was challenged by PJT, claiming the process violated the agreement's provisions. (Paras 1-45)

(B) The court emphasized that both Articles 36 and 37 are not mutually exclusive, enabling the NHAI to terminate the agreement if defaults persisted after the cure period. (Paras 10, 25, 39)

(C) It highlighted issues around the 'Doctrine of Election,' clarifying that parties are not barred from taking multiple remedial steps provided under the agreement. (Paras 28-30)

Facts of the case:
The NHAI and PJT entered into a Concession Agreement concerning the highway project. Disputes arose due to alleged defaults by PJT, including failure to meet obligations leading to accidents. NHAI issued termination notices based on claimed defaults, which led to litigation.

Findings of Court:
The court found that the learned Single Judge's observations were incorrect; the NHAI could exercise its rights under Article 37 after the cure period without waiting for 180 days after invoking Article 36.

Issues: Primary issues included the interpretation of Articles 36 and 37 and the validity of the termination notice issued by NHAI.

Ratio Decidendi: The court ruled that the NHAI was entitled to terminate the Concession Agreement per its provisions after the failure to cure defaults, rejecting arguments of exclusivity between Article 36 and Article 37.

Result: Appeal allowed; the previous order was set aside.

Table of Content
1. considerations on the nature of appeals against interim orders. (Para 22 , 23 , 24 , 25 , 26)
2. court's views on applicability of election doctrine and termination rights. (Para 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42)
3. final decision and dismissal of the application. (Para 43 , 44 , 45)

JUDGMENT

Asha Menon, J. The following observations by the learned Single Judge in the order dated 12th March, 2021 passed in O.M.P.(I) (COMM.) 98/2021 has brought the appellant/National Highways Authority of India ("NHAI", for short) before us:

    "21. Mr. Mehta has laid much emphasis on the intent of the language used in Clause 37.1.2 which begins with the words "without prejudice to any other rights or remedies". There is no doubt that the Respondent could take recourse to the aforesaid provision without prejudice to other rights and remedies and proceed to suspend the Petitioner and accord it an opportunity to cure the defects. However, that does not mean that in case the Respondent has elected to exercise this remedy, it could simultaneously also proceed to terminate under Clause 37.1.2 on the basis of same set of facts. Since the Respondent has elected to go down the path of suspending the rights of the Petitioner as available under the agreement, the opportunity to cure the defects has to be necessarily given, failing which, the Clause itself would become redundant.

    22. Be that as it may, we are at the stage of admission. The Petitioner has made out a prima facie case in its favour and in case no stay is granted, it will suffer an irreparable loss. The balance of convenience also lies in favour of the Petitioner and against the Respondent. The matter certainly requires consideration. Accordingly, till the next date of hearing, the termination notice dated 5th March, 2021 is directed to be kept in abeyance. The arrangement between the parties would continue as per the orders passed in O.M.P. (I) (COMM) No. 421/2020, noted above."

2. The crux of the submissions of Sh. Tushar Mehta, learned Solicitor General of India appearing for the NHAI, is that the provisions under Article 36 and Article 37 of the Concession Agreement ("CA", for short) do not operate in separate and mutually exclusive spheres but form a "composite scheme" and both options are available to the NHAI in the event there is a concessionaire default.

3. Per contra, Dr. Abhishek Manu Singhvi and Sh.Harish Malhotra, learned senior counsel appearing for the respondent/Panipat Jalandhar NH-I Tollway Pvt. Ltd. ("PJT", for short) contended that the two Articles are mutually exclusive and if the NHAI exercised its choice of proceeding under Article 36, it could not jump to Article 37 to terminate the CA, without allowing the entire procedure provided under Article 36 to play out.

4. At this stage, it may be appropriate to briefly refer to the facts of the present case. On 9th May, 2008, the parties entered into the CA in respect of `Six-Laning of Panipat-Jalandhar Section of NH-1 From Km 96.00 to Km 387.10 (length of 291.10 Km) in the State of Haryana and Punjab to be executed on Built-Operate-Transfer (Toll) basis on Design-Build-Finance-Operate (DBFO) pattern under NHDP Phase-V' (hereinafter referred to as the "Project"). The CA was entered for a period of fifteen years from 11th May, 2009 till 11th May, 2024. The project was scheduled to be completed by 9th November, 2011 (in 910 days or 2.5 years). In terms of the CA, the parties had also executed an Escrow Agreement dated 6th May, 2009 with the Lenders, where State Bank of India ("SBI", for short) was the Escrow Agent for operation of the Escrow Account. The estimated cost of the project was Rs.2747.50 crores but the Capital Cost submitted by the respondent/PJT amounted to Rs.4518.17 crores. Disputes arose between the parties even before the Provisional Completion Certificate was issued by the Independent Engineer ("I.E.", for short) on 30th September, 2015. These disp

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top