SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Del) 982

2024:DHC:909
IN THE HIGH COURT OF DELHI AT NEW DELHI
PRATHIBA M. SINGH, J.
Larsen and Toubro Limited – Appellant
Versus
IIC Limited and Another – Respondents
O.M.P. (Misc.) (COMM.) Nos. 426, 427, 637 of 2023, O.M.P. (Misc.) (Comm.) No. 20 of 2024
Decided On : 02-02-2024
Advocates Appeared : 
For the Appellants : J.P. Singh, Subhash Gulati, Shashank Sharma
For the Respondents : Rajat Navet, Shashi Kant, Kushagra Pandit, Harshpal Singh Negi

The Court may extend the mandate of an arbitral tribunal even without consent from all parties if justified by sufficient cause, emphasizing the importance of continuity in arbitration proceedings.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 29A - Interpretation of the mandatory time limit for arbitral awards - The Court held that under Section 29A(4), the mandate of the tribunal can be extended regardless of parties' consent, especially in insolvency cases - The judgment reiterated the Court's authority to extend the mandate even post-expiration for sufficient cause, especially where arbitral proceedings are ongoing and at an advanced stage. (Paras 47-59)

(B) Arbitration - The need for timely awards - The statutory provisions do not mandate expiration of the proceedings merely due to lack of consent from one party, especially when a party is undergoing insolvency - Parties' obligations and the need for continuance of arbitral processes accentuated. (Para 58)

Facts of the case:
The petitioner sought an extension of the arbitral tribunal's mandate due to non-payment related to multiple thermal power projects. The tribunal had adjourned due to the respondent's insolvency. The petitioner contended that the ongoing proceedings were in advanced stages and required judicial intervention for extension of the arbitration mandate.

Findings of Court:
The Court affirmed the need to extend the mandate of the Arbitral Tribunal until December 31, 2024, acknowledging the progress in proceedings and the significant commercial implications involved.

Issues: Whether the mandate of the Arbitral Tribunal could be extended despite a party's lack of consent particularly under conditions of insolvency.

Ratio Decidendi: The Court concluded that insufficient party consent, especially when one is under insolvency, does not limit its power to extend the tribunal's mandate for valid cause, framing effective arbitration as a paramount importance.

Result: Petitions allowed and the tribunal's mandate extended until December 31, 2024.

JUDGMENT :

PRATHIBA M. SINGH, J.

1. This hearing has been done through hybrid mode.

2. These four petitions raise an important issue concerning the interpretation of Section 29A of the Arbitration and Conciliation Act, 1996 (hereinafter ‘1996 Act’). The parties in all the four petitions are set out in the following table:

Case NumberPetitionerRespondentsProject
O.M.P.(MISC.) (COMM.) 426/2023Larsen and Toubro LimitedIIC Ltd. & RPLEBOP Nashik
O.M.P.(MISC.) (COMM.) 427/2023Larsen and Toubro LimitedIIC Ltd. & RPLEBOP Amravati
O.M.P.(MISC.) (COMM.) 20/2024Larsen and Toubro LimitedSinnar Thermal Power Limited & RPL.CHP Nashik
O.M.P.(MISC.) (COMM.) 637/2023Larsen and Toubro LimitedElena Power and Infrastructure Limited & RPL.CHP Amravati

The facts in each of the four petitions are as under:

O.M.P.(MISC.) (COMM.) 426/2023

3. The Petitioner- Larsen & Toubro Ltd. (hereinafter, L&T) was awarded a Letter of Intent (hereinafter, ‘LoI’) dated 5th October, 2010 in respect of the Thermal Power Plant located at Sinnar, Nasik, Maharashtra, India (hereinafter, ‘Nashik Project’). The Letter of Award (hereinafter, ‘LoA’) is dated 19th October, 2010 with respect to the said Nashik Project. Further, in pursuance of LoI and LoA, two contracts were entered into between parties, i.e. a Supply Contract dated 18th February, 2011 and a Service Contract dated 18th February, 2011.

4. In the present petition, the Respondent No. 1 is M/s. IIC Limited (hereinafter, ‘IICL’), and Respondent No. 2 is M/s. Rattan India Power Limited (hereinafter, ‘RPL’). As per the petition, in 2010, RPL initiated the Nashik Project for which the IICL invited bids.

5. According to L&T, the Nashik Project was concluded and the plant was commissioned on 30th May, 2017. Thereafter, in terms of the LoI and the LoA, payments were due to L&T, which were allegedly not paid by the Respondents-IICL and RPL, due to which L&T invoked the arbitration clause on 26th February, 2020 in terms of Clause 11.0 of the General Conditions of Contact (hereinafter, ‘GCC’).

6. The Arbitral Tribunal was constituted on 19th May, 2020, headed by a retired Supreme Court Judge and two retired Delhi High Court Judges. Proceedings commenced on 8th June, 2020. During the arbitral proceedings, RPL filed an application under Section 16 of the 1996 Act on 27th October, 2020, seeking dismissal of the claims. The said application was dismissed by the Arbitral Tribunal vide order dated 1st March, 2021.

7. In the arbitral proceedings, issues were framed on 17th June, 2021. Shortly thereafter, on 20th September, 2021, IICL entered into insolvency, and a moratorium was imposed under Section 14 of the Insolvency and Bankruptcy Code, 2016, in the case titled Fidus Finance Pvt. Ltd. v. IIC Ltd. (IB) 112(ND)/2021. Consequently, the Arbitral Tribunal adjourned the proceedings sine die on 16th October, 2021, granting the parties the liberty to seek revival.

8. Vide email dated 10th January, 2022, the L&T coordinated with the Resolution Professional (hereinafter, 'RP'), and requested the RP to participate in the arbitration proceeding relating to the Nashik project and pursue its counterclaim. As per L&T, no response was received from the RP, who chose not to participate in the arbitral proceedings. On 15th February, 2022, the RP sent a communication requesting that the bank guarantees issued by L&T in favour of IICL, be maintained. Thus, according to L&T, though the RP was consistently communicating with the L&T in respect extension of the bank guarantees, there was no participation.

9. Following this, on 13th April 2022, L&T filed an application under Section 19 of the 1996 Act seeking revival of the arbitral proceedings. In the said application, a detailed order was passed by the Arbitral Tribunal on 13th July, 2022 which revived the arbitral proceedings qua RPL. The observations in the said order are set out below:

"16. It was also argued by the Ld. Counsel for Respondent No. 2 that the issues falling for determination in these proceedings ar

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top