SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Del) 865

2025:DHC:226
IN THE HIGH COURT OF DELHI AT NEW DELHI
SUBRAMONIUM PRASAD, J.
M/s Jaiprakash Associates Limited – Appellant
Versus
M/s NHPC Limited – Respondent
Arb. Pet. No. 1061 of 2023
Decided On : 14-01-2025
Advocates Appeared : 
For the Appellants : Lovkesh Sawhney, Rohit Kumar
For the Respondents : Gauhar Mirza, Hiral Gupta, Sukanya Singh, Rohit Rahar, Devarshi Mohan

Advocates:
For the Appellants/Petitioners: Mr. Lovkesh Sawhney, Mr. Rohit Kumar
For the Respondents: Mr. Gauhar Mirza, Ms. Hiral Gupta, Ms. Sukanya Singh, Mr. Rohit Rahar, Mr. Devarshi Mohan

A court under Section 11 of the Arbitration Act validates the existence of arbitration agreements but cannot allow arbitration for disputes already adjudicated without sufficient evidence, preventing legal resource wastage.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 11 and Section 28(2) - Jurisdiction of the court in referring disputes to arbitration - The court does not delve into the merits of the dispute but only determines the existence of an arbitration agreement - Arbitral Tribunal’s award requiring substantive evidence for claims - The Majority Award was set aside on grounds of lacking evidence to support an award based on good conscience. (Paras 2, 19, 30, 33)

Facts of the case:
The petitioner sought recommencement of arbitration over additional costs claims amounting to Rs. 360.56 crores based on a contract dated 09.04.1997 that was unable to complete within the stipulated time due to overruns, with an earlier award granting Rs. 60 crores being quashed by the learned Single Judge. (Paras 2, 18)

Findings of Court:
The court held that the tribunal's award was contradictory and lacked a basis for awarding Rs. 60 crores which stood contrary to public policy limitations of equity under the Act of 1996. Fresh proceedings were deemed unnecessary as no viable disputes remained. (Paras 19, 30)

Issues: Whether the court should refer a matter for arbitration on the basis of an already adjudicated issue and claims lacking substantive evidence. (Paras 19, 29)

Ratio Decidendi: The court emphasized the need for valid evidence to support claims in arbitration, determining that referring the matter again would be an improper use of the arbitration process, affirming that this constituted a manifest injustice. (Paras 19, 30, 33)

Result: Petition dismissed.

Table of Content
1. introduction of arbitration petition and factual background. (Para 1 , 2)
2. petitioner's claim for arbitration is maintainable. (Para 4 , 8 , 9)
3. referral court's role under section 11 is limited. (Para 10 , 11 , 12 , 13)
4. court cannot correct arbitrators’ errors. (Para 14 , 15)
5. majority award and its contradictions. (Para 16 , 17 , 18)
6. re-examination of evidence is unnecessary after prior adjudication. (Para 19 , 20 , 21 , 22 , 23)
7. court's duty to prevent misuse of arbitration. (Para 24 , 25 , 26 , 27 , 28)
8. dismissal of petition and public policy considerations. (Para 29 , 30 , 31 , 32 , 33 , 34)

JUDGMENT :

SUBRAMONIUM PRASAD, J.

1. The present Petition has been filed under Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter 'Act of 1996') by the Petitioner seeking recommencement of the arbitration and appointment of nominee Arbitrator on behalf of the Respondent to adjudicate upon the disputes which have arisen between the Parties.

2. Shorn of unnecessary details, the facts leading to the present petition are as under:-

i. The Respondent invited bids with regard to execution of Dulhasti Hydro Electric Project on river Chenab at Kishtwar, Jammu and Kashmir. Tenders were invited since the same had been abandoned by a previous awardee namely M/s. Dumaz-Sogea Borie SAE. The balance work was continued by the Petitioner between 1992 to 1995.

ii. Similarly, the work was done by the joint venture of M/s Jaiprakash Industries Limited and M/s Statkraft Anlegg AS. Subsequently, it was amalgamated with M/s Jaypee Cement Limited which came to be known as M/s Jaiprakash Associates Limited, the Petitioner herein and submitted its bid to the tender floated by the Respondent.

iii. It is stated that in the second phase, the work was divided into two packages, one for Upstream Area Works (Package 1) and the other for Downstream Area Works (Package 2). Both the phases were awarded to the Petitioner.

iv. It is stated that a Contract was entered into between the parties on 09.04.1997. The Contract dated 09.04.1997 stipulated that the work should be completed within 33 months but the work could not be completed within the stipulated term of 33 months. Extension was granted to complete the work. The project which was to be completed in the year 2000, was extended till 2007.

v. It is stated that on 11.05.2007, the certificate of completion was issued by the Respondent. The Petitioner raised bills for the two packages. It is stated that in the Bills of the Petitioner, certain additional costs which were said to have been incurred by the Petitioner on account of overstaying at the site were included.

vi. It is stated that the total claim amount towards these additional costs was Rs. 360.56 crores. It is stated that the claim was rejected by the Respondent herein. Since there was an Arbitration Clause in the Contract dated 09.04.1997, the Arbitration Clause, i.e., Clause 39.2, was invoked and the Arbitral Tribunal consisting of three Arbitrators was constituted.

vii. It is stated that in the majority Award, even though it was found that no evidence has been led by the Petitioner herein to substantiate the claim on the ground of cost incurred due to the delay, yet amount of Rs. 60 crore was awarded on the principle of good conscience and reasonable and proper estimate.

viii. The Award was challenged by both the Petitioner and the Respondent herein by filing O.M.P. (COMM) 505/2020 and O.M.P. (COMM) 482/2020 respectively. It is the case of the Respondent that the Award of Rs. 60 crores was unsustainable whereas, the Petitioner herein made a claim for enhancement of the said amount.

ix. The Learned Single Judge vide Judgment dated 26.05.2023 in O.M.P. (COMM) 482/2020, set aside the Majority Award and quashed the finding qua the grant of Rs 60 crores as additional compensation. It is held by the Learned Single Judge that on one hand the Tribunal had held that the Petitioner herein had failed to produce any material to subst

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top