SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Del) 54

IN THE HIGH COURT OF DELHI AT NEW DELHI
Mini Pushkarna, J.
Delhi Metro Rail Corporation Ltd. - Plaintiff
Versus
Ms Parasvnath Developers Ltd. - Defendant
CS(COMM) 463 of 2022 & I.A. 29387 of 2025
Decided On : 27-02-2026

Advocates Appeared:
For the Plaintiff : Mr. Tarun Johri, Mr. Ankur Gupta and Mr. Vishwajeet Tyagi, Advs.
For the Defendant : Mr. Rajat Joneja, Mr. Anmol Kumar and Ms. Cheshta Dalal, Advs.

The court affirmed that additional documents may be permitted if they were discovered after the initial filing and that establishing reasonable cause for non-disclosure is less stringent than for other procedural texts.

Headnote:(A) Code of Civil Procedure, 1908 - Order XI Rule 1(5) - Leave to file additional documents - Plaintiff's application to include eight additional documents to support claims regarding defective construction was allowed. Defendant contested the application citing belated filing and lack of explanation for delay. - Court determined that the plaintiff did not have certain documents at the time of filing and established reasonable cause under Order XI, thereby permitting them as relevant to adjudicate damages and liabilities. (Paras 11, 39, 41)

(B) Reasonable Cause - The court differentiated between 'reasonable cause' and 'good cause', indicating that reasonable cause requires a lower proof standard. The court aims to prioritize justice over mere procedural adherence, thus allowing the filing of documents that are discovered post-pleading. (Paras 16, 20, 31)

Facts of the case:
The plaintiff engaged the defendant for construction of quarters under a contract in 2009. Post-construction, significant structural defects and sewage issues arose, prompting legal action for costs incurred during rectification. (Paras 4, 6, 9)

Findings of Court:
The court accepted additional documents relevant for determining compensation if the plaintiff succeeds, emphasizing that these documents were not in the plaintiff's possession during initial filing. (Paras 31, 36)

Issues: Whether the plaintiff established reasonable cause for late document filing and whether the additional documents were pertinent to the case.

Ratio Decidendi: The court reasoned that allowing documents submitted after suit filing is justified when they were not initially available, and emphasized ensuring no prejudice occurs to the defendant's position. (Paras 38, 42)

Result: Plaintiff's application allowed with costs.

Table of Content
1. plaintiff's motion for additional documents contested by defendant. (Para 1 , 2 , 3)
2. background on construction project and deficiencies. (Para 4 , 5 , 6 , 7 , 8 , 9)
3. rules on disclosure of documents under cpc. (Para 10 , 11 , 12)
4. plaintiff's letters addressing construction deficiencies. (Para 13 , 14 , 15 , 16)
5. court's analysis of contract's dispute resolution clause. (Para 17 , 18 , 19 , 20)
6. subsequent report from cbri considered for admissibility. (Para 21 , 22 , 23)
7. court's stance on reasonable cause for non-disclosure. (Para 24 , 25 , 26)
8. evaluating payments and costs relative to the case. (Para 27 , 28 , 29 , 30)
9. court allows additional documents relevant to plaintiff's claims. (Para 31 , 32 , 33 , 34 , 35 , 36)
10. no prejudice to defendant; documents deemed admissible. (Para 37 , 38 , 39)
11. application to place additional documents allowed with costs. (Para 40 , 41 , 42)

JUDGMENT :

MINI PUSHKARNA, J.

I.A. 29387/2025 (Application under Order XI Rule 1(5) read with Section 151 of Code of Civil Procedure, 1908)

1. The present application has been filed on behalf of the plaintiff seeking leave of this Court to bring on record a total of eight additional documents, as filed along with the replication and Evidence Affidavits of its witnesses, PW-1 and PW-2.

2. The present application has been opposed by the defendant, thereby, raising the objection that the additional documents have been filed without seeking leave of the Court, and that the present application has been filed belatedly, after the said issue was pointed out at the time of tendering of the evidence.

3. The defendant has further averred that the plaintiff has failed to put forth any plausible explanation for seeking leave of this Court to file additional documents at such a belated stage. It is submitted that if the proposed additional documents were to be taken on record, it would relegate the proceedings to the stage of pleadings, and hamper the commencement of trial.

4. At the outset, it is to be noted that as per the facts on record, plaintiff had issued a Notice Inviting Tender in the year 2009 for the construction of three blocks of staff quarters, i.e., blocks A, B and C, with a combined capacity of 144 dwelling units at Mundka Depot for Phase II of Delhi MRTS Project. Subsequently, a Letter of Acceptance was issued to the defendant on 27th May, 2009, followed by the execution of a Contract Agreement dated 28th August, 2009, between the parties.

5. The defendant started the construction of the blocks in question in 2009, and subsequently, the three blocks, i.e., blocks A, B and C were taken over by the plaintiff on 05th October, 2012, 10th November, 2012 and 03rd December, 2012, respectively. The flats constructed by the defendant were allotted and taken over by the employees of the plaintiff between March- May, 2013 and around 140 number of families, were residing in the project in question.

6. As per the case put forth by the plaintiff, immediately after the occupation of the flats, multiple sewage problems were observed by the residents, in a number of flats in all the three blocks. On being informed about the said sewage problems, the defendant attended to few issues, however, failed to rectify most of such issues, and such problems persisted at the site in question. In addition to this, various structural cracks started appearing in the blocks in question. As per the plaintiff, the sewage problems and the cracks in the building are attributable to poor quality of construction material used by the defendant.

7. Thus, as per the plaintiff, it engaged services of various agencies for technical assistance. In particular, the plaintiff engaged the services of Shri Ram Institute for carrying out investigations, by conducting various technical tests to ascertain the strength of the structure built by defendant, and the services of M/s Epicon Consultants Pvt. Ltd., for carrying out detailed structural assessment of the project in

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top