IN THE HIGH COURT OF DELHI AT NEW DELHI
HARISH VAIDYANATHAN SHANKAR, J.
Paharpur Cooling Towers Limited – Petitioner
Versus
Sinnar Thermal Power Limited And Ors. – Respondents
OMP (ENF.) (COMM.) 237 of 2025, EX.APPL.(OS). 92 of 2026 (By R-2 U/O 1 Rule 10)
Decided On : 11-02-2026
| Table of Content |
|---|
| 1. petition under arbitration act for enforcement. (Para 1 , 2) |
| 2. factual background involving dispute and arbitration. (Para 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16) |
| 3. arguments against execution and maintainability. (Para 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29) |
| 4. court's initial assessment of execution's legal basis. (Para 30 , 31 , 32 , 33 , 34) |
| 5. recognition of execution's conflict with insolvency framework. (Para 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44) |
| 6. rejection of corporate veil lifting in execution. (Para 45 , 46 , 48 , 49 , 50 , 51 , 52 , 53 , 54 , 55) |
| 7. denial of execution beyond the arbitral award's bounds. (Para 56 , 57 , 58 , 59 , 60 , 61 , 62 , 63 , 64 , 65) |
| 8. final order to dismiss the petition. (Para 66 , 67 , 68 , 69 , 70) |
JUDGMENT :
HARISH VAIDYANATHAN SHANKAR, J.
1. The present petition has been filed under Section 36 of the Arbitration and Conciliation Act, 1996 , A&C Act, read with Order XXI Rules 10 and 11 of the Code of Civil Procedure, 1908, seeking enforcement of theArbitral Award dated 12.11.2021, read with the correction Order dated 20.12.2021 , Arbitral Award, against all the Judgment Debtors herein. In furtherance of the said enforcement, the Petitioner has accordingly formulated multiple prayers in the present petition.
BRIEF FACTS:
2. For the purposes of adjudication of the present lis, it is necessary to briefly set out the relevant factual background, insofar as it bears upon the controversy presently arising for consideration before this Court, which is delineated hereunder:
I. The Decree Holder was awarded a Letter of Award dated 12.08.2010, whereby it was entrusted with the work of construction, erection, commissioning and completion of five Induced Draft Cooling Towers for a thermal power project situated at Nashik, Maharashtra.
II. Pursuant thereto, a series of contracts came to be executed governing the said scope of works.
III. At the time of execution of the aforesaid Letter of Award and the underlying contracts, the contracting entity on behalf of the project owner was Indiabulls Realtech Limited.
IV. Subsequently, pursuant to a corporate reorganisation, the power generation business of Indiabulls Realtech Limited was transferred to the Rattan India Group, whereupon the said entity was rechristened as Rattan India Power Limited, and the project-specific company was renamed Rattan India Nasik Power Limited, which continued to function as a wholly-owned subsidiary of Rattan India Power Limited.
V. It is stated that the aforesaid contracts were completed by the Petitioner in June 2018.
VI. Subsequently, with effect from 05.02.2019, Rattan India Nasik Power Limited underwent a further change in its corporate name and came to be known as Sinnar Thermal Power Limited, which is arrayed as Judgment Debtor No. 1 in the present proceedings.
VII. Disputes arose between the Decree Holder and Judgment Debtor No. 1 in relation to execution of the aforesaid contracts, inter alia, concerning payments due, issuance of acceptance certificates and allied contractual obligations. Consequently, the Decree Holder issued a notice invoking arbitration dated 06.12.2019.
VIII. As the parties were unable to arrive at a consensus on the appointment of an arbitral tribunal, this Court, vide Order dated 31.01.2020 passed in ARB.P. No. 63/2020 titled as „ Paharpur Cooling Towers Ltd. vs. Sinnar Thermal Power Limited ‟, appointed Mr. Justice A.K. Pathak (Retd.), former Judge of this Court, as the Sole Arbitrator to adjudicate the disputes between the Decree Holder and Judgment Debtor No. 1.
IX. Upon completion of pleadings, recording of evidence and final hearing, the learned Sole Arbitrator rendered the Arbitral Award dated 12.11.2021, which was thereafter subjected to a Correction Order dated 20.12.2021.
X. The Award was passed in favour of the Decree Holder and solely against Judgment Debtor No. 1. Aggrieved thereby, Judgment Debtor No. 1 preferred a petition
Cheran Properties Limited v. Kasturi and Sons Limited
Execution of an arbitral award is not maintainable during corporate insolvency proceedings as approved resolution plans render prior claims extinguished.
Once a resolution plan is approved under the IBC, all claims not part of the plan are extinguished, and the tribunal lacks jurisdiction to adjudicate on such claims.
The approved resolution plan under the IBC extinguishes claims not included, rendering any arbitral award related to such claims non-executable.
The main legal principle established in the judgment is the extinguishment of pre-existing and undecided claims upon approval of the Resolution Plan under Section 31 of the Insolvency and Bankruptcy ....
Execution of an arbitral award requires compliance with the 90-day limitation under Section 34; execution petitions filed before this period are impermissible.
Parties challenging an arbitral award must do so exclusively under Section 34 of the Arbitration Act; raising new grounds or objections in execution proceedings is impermissible.
IBC is a time bound process – Plea of not being aware of newspaper pronouncements is not one which should be available to a commercial party.
Foreign award enforceable under Sections 48-49 Arbitration Act is executable as decree; no separate executability test or prior RBI approval under FEMA required; prior objections on compliance/valuat....
Claims not part of an approved insolvency resolution plan are extinguished and cannot be executed.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.