SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Del) 210

IN THE HIGH COURT OF DELHI AT NEW DELHI
HARISH VAIDYANATHAN SHANKAR, J.
Paharpur Cooling Towers Limited –  Petitioner
Versus 
Sinnar Thermal Power Limited And Ors. – Respondents 
OMP (ENF.) (COMM.) 237 of 2025, EX.APPL.(OS). 92 of 2026 (By R-2 U/O 1 Rule 10)
Decided On : 11-02-2026

Advocates Appeared:
For the Petitioner:Mr. Siddhartha Datta, Ms. Suhani Dwivedi, Ms. Nimrah Sameen Alvi, Mr. Deepanjan Datta, Ms. Adyasha Nanda, Mr. Vishal Pathak, Advocates.
For the Respondent:Mr. Rajshekhar Rao, Senior Advocate along with Ms. Meghna Mishra, Mr. Nikhil Ratti Kapoor, Ms. Yashodhara Gupta, Advcoates Mr. Varun Chandiok, Ms. Anubhi Goyal, Advocates

Execution of an arbitral award is not maintainable during corporate insolvency proceedings as approved resolution plans render prior claims extinguished.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 36 - Code of Civil Procedure, 1908 - Order XXI Rules 10 and 11 - Enforcement of Arbitral Award - Petition dismissed due to maintenance not being tenable while undergoing Corporate Insolvency Resolution Process; finality of Resolution Plan prevents parallel execution claims despite knowledge of corporate structure during arbitration - Section 31 of the IBC renders claims extinguished upon approval. (Paras 34, 67, 70)

(B) Corporate Law - Lifting of Corporate Veil - It is permissible only in compelling cases with strong factual foundations; insufficient grounds presented by Decree Holder to pierce corporate personality amidst claims against non-parties to arbitration. (Paras 59, 66)

Facts of the case:
Petitioner sought enforcement of Arbitral Award against corporate debtor amidst ongoing CIRP, alleging undue influence by associated companies. The Decree Holder initially engaged solely with Judgment Debtor No. 1. Claims submitted during CIRP led to resolution plan approval reducing claims significantly, leading to execution confusion.

Findings of Court:
Execution petition dismissed as claims already submitted in CIRP rendered it legally untenable to pursue additional recovery outside the approved plan.

Issues: Whether the execution petition is maintainable given ongoing CIRP and resolution plan binding on stakeholders. Whether the corporate veil can be lifted for parties not involved in the arbitration.

Ratio Decidendi: The court emphasized that claims under IBC, once finalized by resolution, are binding on all stakeholders, and that pursuing additional recovery would defeat the purpose of the insolvency framework. The evidence provided was inadequate to support a claim for lifting the corporate veil.

Result: Petition dismissed with costs of Rs.1,00,000/- to be paid to Judgment Debtors.

Table of Content
1. petition under arbitration act for enforcement. (Para 1 , 2)
2. factual background involving dispute and arbitration. (Para 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16)
3. arguments against execution and maintainability. (Para 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29)
4. court's initial assessment of execution's legal basis. (Para 30 , 31 , 32 , 33 , 34)
5. recognition of execution's conflict with insolvency framework. (Para 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44)
6. rejection of corporate veil lifting in execution. (Para 45 , 46 , 48 , 49 , 50 , 51 , 52 , 53 , 54 , 55)
7. denial of execution beyond the arbitral award's bounds. (Para 56 , 57 , 58 , 59 , 60 , 61 , 62 , 63 , 64 , 65)
8. final order to dismiss the petition. (Para 66 , 67 , 68 , 69 , 70)

JUDGMENT :

HARISH VAIDYANATHAN SHANKAR, J.

1. The present petition has been filed under Section 36 of the Arbitration and Conciliation Act, 1996 , A&C Act, read with Order XXI Rules 10 and 11 of the Code of Civil Procedure, 1908, seeking enforcement of theArbitral Award dated 12.11.2021, read with the correction Order dated 20.12.2021 , Arbitral Award, against all the Judgment Debtors herein. In furtherance of the said enforcement, the Petitioner has accordingly formulated multiple prayers in the present petition.

BRIEF FACTS:

2. For the purposes of adjudication of the present lis, it is necessary to briefly set out the relevant factual background, insofar as it bears upon the controversy presently arising for consideration before this Court, which is delineated hereunder:

I. The Decree Holder was awarded a Letter of Award dated 12.08.2010, whereby it was entrusted with the work of construction, erection, commissioning and completion of five Induced Draft Cooling Towers for a thermal power project situated at Nashik, Maharashtra.

II. Pursuant thereto, a series of contracts came to be executed governing the said scope of works.

III. At the time of execution of the aforesaid Letter of Award and the underlying contracts, the contracting entity on behalf of the project owner was Indiabulls Realtech Limited.

IV. Subsequently, pursuant to a corporate reorganisation, the power generation business of Indiabulls Realtech Limited was transferred to the Rattan India Group, whereupon the said entity was rechristened as Rattan India Power Limited, and the project-specific company was renamed Rattan India Nasik Power Limited, which continued to function as a wholly-owned subsidiary of Rattan India Power Limited.

V. It is stated that the aforesaid contracts were completed by the Petitioner in June 2018.

VI. Subsequently, with effect from 05.02.2019, Rattan India Nasik Power Limited underwent a further change in its corporate name and came to be known as Sinnar Thermal Power Limited, which is arrayed as Judgment Debtor No. 1 in the present proceedings.

VII. Disputes arose between the Decree Holder and Judgment Debtor No. 1 in relation to execution of the aforesaid contracts, inter alia, concerning payments due, issuance of acceptance certificates and allied contractual obligations. Consequently, the Decree Holder issued a notice invoking arbitration dated 06.12.2019.

VIII. As the parties were unable to arrive at a consensus on the appointment of an arbitral tribunal, this Court, vide Order dated 31.01.2020 passed in ARB.P. No. 63/2020 titled as „ Paharpur Cooling Towers Ltd. vs. Sinnar Thermal Power Limited ‟, appointed Mr. Justice A.K. Pathak (Retd.), former Judge of this Court, as the Sole Arbitrator to adjudicate the disputes between the Decree Holder and Judgment Debtor No. 1.

IX. Upon completion of pleadings, recording of evidence and final hearing, the learned Sole Arbitrator rendered the Arbitral Award dated 12.11.2021, which was thereafter subjected to a Correction Order dated 20.12.2021.

X. The Award was passed in favour of the Decree Holder and solely against Judgment Debtor No. 1. Aggrieved thereby, Judgment Debtor No. 1 preferred a petition

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top