NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
Subhash Chandra, Presiding Member and
Dr. Sadhna Shanker, Member
Avalon Rojects (A Unit of GRJ
Distributors & Developers Pvt. Ltd.) – Appellant
versus
Narender Kumar Goyal and Anr. – Respondents
First Appeal No.872 of 2021 and
First Appeal No.873 of 2021
Decided on 9.11.2023
Consumer Protection Act, 1986 – Section 19 [Consumer Protection Act, 2019 – Section 51] – Services – Real Estate – Allotment of Flat / Plot – Delayed Possession – Thus an allottee/consumer was entitled to seek refund of the amount deposited by him with the Opposite Party since the Builder had failed to fulfill his contractual obligations of obtaining the Occupancy Certificate and offering possession of the flat to the purchaser within the time stipulated in the Agreement or within a reasonable time thereafter and that the purchaser could not be compelled to take possession of the flat even if it was offered after the grace period under the Agreement expired – Thus, it is evident that the deficiency in service on the part of the Appellant qua the Respondents stands established – The Appellant shall refund the amount of Rs.35,97,440/- with interest @ 9% p.a. from the respective dates of deposits till the date of offer of possession, i.e. 01.09.2020 to the Complainant, within two months, failing which the interest payable would be 12% p.a. – Appeal allowed. [Paras 6 to 18].
Result: Appeal allowed.
ORDER
Subhash Chandra, Presiding Member—This order shall dispose of First Appeals No.872 of 2021 and 873 of 2021 since they arise from the same impugned order which pertains to the same project and have the same conspectus of facts. For convenience, facts are being taken from First Appeal No.872 of 2021.
2. This Appeal has been filed by the Appellant/Opposite Party against the order dated 21.09.2021 of the State Consumer Disputes Redressal Commission, Rajasthan (for short “the State Commission”) in Complaint No.151 of 2019 filed by the Respondent (hereinafter referred to as “the Complainant”), praying for allowing the Appeal and to set aside the impugned order and to pass any such further other, as may be deemed fit and proper.
3. Briefly, the facts are that the Complainant is an allottee in the Appellant’s project “Avalon Royal Park”, Bhiwadi, Rajasthan and was allotted plot No.101, Tower A-4, 1st Floor admeasuring 1250 sq. ft. of super area for a basic sale price of Rs.30,44,400/- along with EDC/IDC, PLC, open car parking, IFMS, power backup, club membership etc. A booking amount of Rs.6,27,696/- was paid and a Builder Buyer Agreement (BBA) was executed on 27.04.2013. As per Clause 4 A, possession was proposed to be delivered by the Appellant within 42 months subject to force majeure circumstances with a grace period of six months. The Complainant paid a sum of Rs.35,97,440/- to the Appellant in installments. However, possession was not offered by 27.04.2017 as per the provisions in the BBA. A pre-possession intimation dated 13.05.2019 was issued by the Appellant to the Complainant and thereafter, on the basis of the Occupancy Certificate dated 20.03.2020, an offer of possession was made on 01.09.2020. However, the Complainant filed Complaint before the State Commission on 02.08.2019 seeking refund of the money deposited by him with compensation in view of the delay on the part of the Appellant in not making an offer of possession as promised.
4. On contest, the State Commission held, vide the impugned order, that the Appellant was guilty of deficiency in service and was liable to refund the money received by it from the Complainant. Accordingly, it was directed that the sum of Rs.35,97,440/- be refunded within three months with simple interest @ 10% p.a., failing which the interest payable would be 12% p.a., along with Rs.2 Lakhs and Rs.50,000/- towards complaint expenses, failing which interest @ 9% p.a. would be payable on the amount of Rs.2,50,000/-.
5. This order is impugned before us.
6. We have heard learned Counsel for the parties and perused the material on record. Both the parties have filed their short synopsis of written arguments and copies of the judgments relied upon.
7. On behalf of the Appellant, it was contended that the promised date of possession within 48 months was subject to force majeure circumstances which were beyond the control of the Appellant for which it was to be entitled to a reasonable extension of time as per Clause 8 B of the BBA. The Complainant was also required to make timely payments of the installments and other charges. It was admitted that there was a delay in the offer of possession; however, the same was ascribed to certain force majeure circumstances for which the Appellant was not liable to be held responsible. It was stated that vide letter dated 13.05.2019, an intimation regarding pre-possession formalities requiring the payment of Rs.3,14,368/- had been issued to the Complainant. Thereafter, a final demand letter cum registration information was issued on 01.09.2020. However, the Complainant failed to comply with these demand letters and instead chose to prefer a Complaint before the State Commission. The order of the State Commission is challenged on the grounds that it failed to appreciate that (i) the Complainant was not a consumer since he was a resident of Bharatpur, Rajasthan and had purchased the flat for investment purpose; (ii) that the construction had been completed
Ireo Grace Realtech Pvt. Ltd. vs. Abhishek Khanna
Kavita Ahuja vs. Shipra Estates & Jai Krishna Estate Developers Pvt. Ltd. and Ors.
Pioneer Urban Land & Infrastructure Ltd. vs. Govindan Raghavan
Occupancy Certificate – Thus an allottee/consumer was entitled to seek refund of the amount deposited by him with the Opposite Party since the Builder had failed to fulfill his contractual obligation....
One-sided contractual terms - Appellant-Builder cannot seek to bind the Respondent with such one-sided contractual terms.
Delay of 5 years - There is a delay of more than 5 years in obtaining completion/ Occupancy Certificate from the promised date of delivery of possession, therefore the Complainant cannot be compelled....
Non-availability of the Occupancy/Completion Certificate points to the deficiency on the part of the Appellant.
Inordinate delay –In a timely fashion would constitute “deficiency in service” on the part of the Opposite Party/Builder.
Two parallel rights - It is a well settled position that in case of unreasonable delay beyond the agreed and assured period, two parallel rights accrue to the consumer.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.