SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2016 Supreme(Guj) 657

IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
S.R. Brahmbhatt and Kaushal Jayendra Thaker, JJ.
Oil & Natural Gas Corporation Ltd. - Appellants
Vs.
Birla Techneftegas Exploration Ltd. - Respondent
First Appeal No. 3256 of 2001
Decided On : 07-04-2016

Advocates Appeared:
For the Appellant :R.R. Marshall for Trivedi & Gupta, Advocate
For the Respondents:P.C. Kavina, Learned Sr. Adv. and Anshin H. Desai, Advocate

The main legal point established in the judgment is that the court upheld the arbitration award, emphasizing the proper appreciation of facts and application of the law by the Arbitrators. The court also modified the interest rate from 15% to 9% but upheld the rest of the award.

Headnote:

Arbitration - Oil and Gas Exploration - Arbitration and Conciliation Act, 1996 - Section 96 of the Code of Civil Procedure - [Section 96 of the Code of Civil Procedure, Arbitration and Conciliation Act, 1996] - The judgment discusses the controversy between the parties regarding a contract for drilling oil wells and the subsequent arbitration award. The court examined the claims, counterclaims, and the determination of substantial increase in operating costs due to the hike in the price of High Speed Diesel. The court also considered the plea of limitation, the acceptance of unproved documents, and the award of interest. The court upheld the award with a modification to reduce the interest rate from 15% to 9%.

Fact of the Case:

The appellant, a Public Limited Company substantially owned by the Union of India, was engaged in Oil and Gas Exploration and had an office at Ankleshwar known as 'Ankleshwar Project'. The respondent was awarded a contract for drilling oil wells on a meter rate basis in the Gandhar belt in Gujarat. Disputes arose regarding payment, leading to arbitration. The Arbitrators awarded amounts against the claims and interest. The appellant challenged the award, alleging misappreciation of facts and law, negligence, and error of law. The appellant also argued that the claim for the alleged rise in the price of High Speed Diesel was time-barred and unproven. The court below confirmed the award, resulting in the present appeal.

Finding of the Court:

The court found that the Arbitrators had properly appreciated the facts and applied the law. The court rejected the appellant's challenge based on misappreciation of facts and law, negligence, and error of law. The court also held that the claim for the alleged rise in the price of High Speed Diesel was not time-barred and was proven. The court modified the interest rate from 15% to 9% but upheld the rest of the award.

Issues: The issues included the determination of substantial increase in operating costs, the plea of limitation, acceptance of unproved documents, and the award of interest.

Ratio Decidendi: The court upheld the Arbitrators' findings and rejected the appellant's challenge. The court also modified the interest rate from 15% to 9% but upheld the rest of the award.

Final Decision: The court upheld the arbitration award with a modification to reduce the interest rate from 15% to 9%.

JUDGMENT :

S.R. Brahmbhatt, J.

1. The appellant, who happen to be the applicant in Civil Misc. Application (Arbitration) No. 216 of 2000 in the Court of District Judge at Vadodara, have taken out this Appeal under Section 96 of the Code of Civil Procedure as well as under the provisions of the Arbitration and Conciliation Act, 1996, challenging the judgment, order and decree dated 5.5.2001 passed in Civil Misc. Application (Arbitration) No. 216 of 2000 for the grounds mentioned thereunder.

2. Facts in brief, as could be culled out from the proceedings deserve to be set out in brief for appreciating the controversy between the parties.

3. The appellant being a Public Limited Company substantially owned by Union of India, engaged in Oil and Gas Exploration and has one of the offices at Ankleshwar known as 'Ankleshwar Project'. The respondent was awarded contract for the work of drilling of oil wells on meter rate basis in Gandhar belt in Gujarat. The contract was executed on 18.2.1993. On account of dispute arose between the parties in respect of contract work in the payment, the same was referred to Arbitrators, who in tern, nominated the Presiding Arbitrator, who rendered the award on 28/30.6.2000, awarding an amount of Rs. 33,19,822/- against the claim No. 1 and Rs. 1,07,18,461.99ps as regards the claim No. 2 and Rs. 71,87,638.02ps as interest on both the aforesaid claims @ 15% p.a. till the date of the award. The Tribunal also awarded interest at the rate of 18% p.a. over Rs. 2,12,25,922.10ps (total of three items aforesaid), from the date of award till the date of payment in favour of the respondent and against the appellant.

4. The said award was assailed in the proceedings of Civil Misc. Application being Civil Misc. Application (Arbitration) No. 216 of 2000, which came to be rejected by the concerned Court vide its judgment, order and decree dated 5.5.2001, which also the subject matter of challenge in the present proceedings.

5. The learned Arbitrators in their Award have summarized the gist of claim and recorded that there was no counter claim which could be seen from the following:

"The claimants filed their State of Claim on 4.7.1998. Respondents filed their reply to the Statement of Claim on 3.8.1998. The Claimants filed their rejoinder on 18.8.1998. The Claimants have made four claims in their Statement of Claim. The Respondents have not made any counter claim. Claim No. 1 pertains to deduction by the Respondents of Rs. 25,36,497/- from the invoices of the Claimants for the month of February and March, 1997 and the consequent deduction of Rs. 7,83,325/- towards reimbursement of bit cost for Well No. GNOI. The second claim pertains to increase in the price of High Speed Diesel (HSD) during the execution of the contract. The third claim is relating to interest and the fourth claim is the cost of arbitration. Thus, there were two claims which required to be adjudicated on the basis of evidence led by the parties. However, claim No. 3 and 4 would follow the determination of Claim Nos. 1 and 2. Consequently, the Tribunal, after the pleadings were completed, framed only two points for determination on 22.8.1998, which were as follows:

"1. Whether the Claimants establish that the operating cost had increased substantially because of the increase in the price of High Speed Diesel Oil after the opening of the price bid?

2. Whether the respondents establish that the complications in Well GNOI that arose between 16.2.1997 and 19.3.1997 were due to the negligence of the Claimant in drilling the Well upto 3050 meters?"

6. The Arbitrators have also recorded that though in reply, there was no plea of limitation was taken so far as claim No. 2 i.e. for HSD price increase during the course of proceedings and at the time of recording of evidence, an application came to be filed taking up the said objection and Tribunal permitted the same vide its order dated 30.10.1998. The said plea and submission thereon are articulately stated by the Tribu







































































































































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top