IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
Bela M. Trivedi, J.
Alphard Maritime Pvt. Ltd. – Petitioner
Versus
Malara Enterprises – Respondent
R/Petn. Under Arbitration Act No. 40 of 2020
Decided On : 23-04-2021
Arbitration and Conciliation Act, 1996 - Sections 11, 7, (6A) (4)(b) and 7(4) - Arbitration – Appointment of Arbitrator - Docking services for the barge - whether contractual or not - Whether Court could appoint an Arbitrator under Section 11 of the said Act as prayed for in the petition - Petitioner is a Company incorporated in India and is an owner of various tugs, barges and offshore vessels - Petitioner is the owner of barge the dry docking services were provided by the respondents, who belong to Malara firm, a proprietary firm of the Proprietor respondent No. 2 herein - Further case of petitioner, as stated in petition, is petitioner required dry docking services for barge involved in the present dispute, for respondent No.2 had approached petitioner with a quotation for the dry dock repairs of barge at Sikka Port on behalf of the respondent - Later as per instructions of the petitioner, the respondent No.1 sent quotations and contractual terms on its letterhead vide Email for dry docking services to be provided, Clause-13 of the terms and conditions thereof is reproduced.
Finding of the court : Parties had agreed to submit to jurisdiction at the High Court of Gujarat for the purpose of arbitration, the procedure for appointment of the Arbitrator was not agreed upon - It has also come on record that the petitioner had already called upon respondents by sending a Notice of Arbitration through email, calling upon them to appoint an independent and impartial Sole Arbitrator as per the provisions contained in the Act, however the respondents had refused to agree to the said request - Circumstances, in absence of any procedure having been agreed upon for appointing Arbitrator, and both the parties having failed to agree on the appointment of the Arbitrator, within thirty days from the receipt of request made by the petitioner to respondents, the case would fall under sub-Section (5) of Section 11 for appointment of Arbitrator by this Court - Court in exercise of powers conferred under sub-Section (5) read with sub-Section (4) and sub-Section (2) of Section 11, appoints Former Judge of High Court of Gujarat, to act as an Arbitrator to resolve the disputes between the parties - Learned Advocate appearing with for petitioner is directed to obtain the requisite consent and declaration of Mr. Justice as required in terms of Sixth Schedule, under Section 11(8) read with Section 12(1)(b) of the Arbitration and Conciliation Act, 1996.
Result : Petition is allowed
JUDGMENT :
1. The petitioner M/s. Alphard Maritime Pvt. Ltd., has preferred the present petition under Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the said Act”), seeking following prayer:
2. As per the case of the petitioner, the petitioner is a Company incorporated in India and is an owner of various tugs, barges and offshore vessels. The petitioner is the owner of the barge A M Abhik, on which the dry docking services were provided by the respondents, who belong to Malara firm, a proprietary firm of the Proprietor Mr.Ashish S. Joshi, the respondent No. 2 herein. The further case of the petitioner, as stated in the petition, is that the petitioner required dry docking services for the barge involved in the present dispute, for which the respondent No.2 had approached the petitioner with a quotation for the dry dock repairs of the barge at Sikka Port on behalf of the respondent No.1. Later as per the instructions of the petitioner, the respondent No.1 sent the quotations and the contractual terms on its letterhead vide Email on 26.9.2019 for the dry docking services to be provided, (Annexure-B Collectively). Clause-13 of the terms and conditions thereof is reproduced as under:
3. According to the petitioner, though it was specifically provided in the contract that the dry docking activities will be completed in a time-bound manner i.e. within 30 days of the docking, the respondents took 120 days in completing the dry docking and also made other breaches of the contract, which were noticed by the petitioner subsequently i.e. after the payments were made to the respondents for the said work. According to the petitioner, it was forced to incur an additional cost of cleaning the tanks on the barge, and on account of the delay occurred in completing the work, the petitioner also suffered a loss of freight and other losses as a result of the breaches of the contract at the instance of the respondents. The petitioner, therefore, sent a notice dated 14.4.2020 through Email calling upon the respondents to pay the damages arising out of the breach of the contract amounting to INR 5,85,00,000/-and also invoked the arbitration Clause 13 requesting the respondents to appoint an independent and impartial sole Arbitrator as per the provisions of the said Act (Annexure-C). However, the respondents responded vide the Email dated 11.5.2020 stating inter alia that the respondents did not have any such contract as mentioned in their Email and asked the petitioner not to communicate on the subject in future. Thereafter, certain correspondences were exchanged between the parties in which the respondents refuted the very existence of the contract. The petitioner therefore has filed the petition seeking appointment of Arbitrator under Section 11 of the said Act, in view of the Clause-13 of the terms and conditions of the contract quoted by the respondents in Annexure-B.
4. The respondents have resisted the petition by filing an affidavit-in-reply, challenging the very maintainability of the petition under Section 11 of the said Act and contending inter alia that a quotation could not be said to be a contract. There was no agreement between the parties for referring the dispute to the arbitration. It is also contended that even if it was assumed that there was a contract between the petitioner and the respondents, then also a passing reference to the word “Arbitration” or “Arbitrator” in a contract would not constitute a valid agreement between the parties. The respondents have further contended that the petitioner had intentionally suppressed the fact that the pur
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.