SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Guj) 338

IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
VINEET KOTHARI, B.N. KARIA, JJ.
CHIEF ENGINEER UTTAR GUJARAT VIJ CO. LTD., Deputy Engineer & Executive Engineer (O&M) - Appellant
Versus
GUJARAT MICROWAX LTD. - Respondent
LETTERS PATENT APPEAL NO. 618 of 2013
In R/SPECIAL CIVIL APPLICATION NO. 6164 of 2004
Decided On : 08-06-2021

Advocates Appeared:
For the Appellant : MS LILU K BHAYA
For the Respondent: MR BHARAT T RAO

Headnote:

Companies Act, 1956 - Recalculate the amount and refund the amount - Amount of Bill - Petitioner is private Limited Company under the provisions of Companies Act, 1956 and Petitioner-Company is engaged in the manufacture of Microcrystalline Cellulose Powder at its factory situated at Survey - Petitioner is a consumer of Respondent- Gujarat Electricity Board having contracted load of 325 KVA and its consumer number - SPPL is also a consumer of Respondent -Gujarat Electricity Board in LTP category, having connected load Petitioner's Unit was checked by the Checking Squad of the Respondent-Board and everything was found upto the standard - Cable of GEB, supplies power to SPPL, was burnt and SPPL informed GEB in writing same and requested the Board to replace same forthwith as SPPL is a continuous industry and without power, SPPL would suffer loss of lacs of rupees – Held, Learned Single Judge has also observed that in earlier calculation of bill neither FCI charges or demand charges were considered nor included as per applied formula - There was substantial difference and there was no reason to hold method applied for revised bill was correct in any manner - No material was produced to the notice of the Court to show charges were not to be calculated on contracted load or FCI charges or demand charges were not recoverable or that formula applied was improper - Judgment and order passed by learned Single Judge cannot be said to be illegal or perverse – Court are of considered view there is no substance in arguments advanced by learned Advocate for the Appellants-Board to interfere in judgment and order as no error is committed - Letters Patent Appeal dismissed.

JUDGMENT :

B.N. KARIA, J.

1. Being aggrieved with the judgment and order dated 31st January, 2013 passed by the learned Single Judge in Special Civil Application No. 6164 of 2004 partly allowing the petition and directing the petitioners to charge the bill as per approved formula from 14th August, 1998 till 21st August, 1998 and to recalculate the amount and refund the amount, if the amount is deposited or recovered or in alternate, to give adjustment in the subsequent bills of the Respondent within a period of two months from passing of the order, the Appellants-original respondents (UGVC Ltd.) have preferred this Letters Patent Appeal under Clause 15 of The Letters Patent.

2. The facts leading to the present Letters Patent Appeal, in nutshell are as under :-

    2.1 The Petitioner is private Limited Company under the provisions of Companies Act, 1956 and Petitioner-Company is engaged in the manufacture of Microcrystalline Cellulose Powder at its factory situated at Survey No. 291/1 & 2, Nandasan, Taluka Kalol, Dist. Mehsana. The Petitioner is a consumer of Respondent- Gujarat Electricity Board having contracted load of 325 KVA and its consumer number is HT 19654. The Petitioner-Company entered into Lease Agreement with M/s. Shaili Polymers Pvt. Ltd. (for short “SPPL”) for lease of 6076 sq. mtrs. of land of Petitioner's ownership in the said premises at annual rent of Rs. 5,000/- .

2.2 The said SPPL is also a consumer of Respondent -Gujarat Electricity Board in the LTP category, having connected load of 125 HP. On 14.8.1998, the Petitioner's Unit was checked by the Checking Squad of the Respondent-Board and everything was found upto the standard. On 17th August, 1998, the cable of GEB, which supplies power to SPPL, was burnt and SPPL informed the GEB in writing about the same and requested the Board to replace the same forthwith as SPPL is a continuous industry and without power, SPPL would suffer loss of lacs of rupees. SPPL requested the Petitioner to supply to SPPL on temporary basis so that no further loss can be caused.

2.3 Considering the request and hardship faced by the tenant i.e. SPPL, Petitioner showed its readiness to supply 20 KW power to SPPL on temporary basis and intimated the GEB by letter dated 17th August, 1998 that the Petitioner will supply power to SPPL because of the reasons stated in the letter. Again, on 21st August, 1998, Inspection Team of GEB came and inspected the premises of the Petitioner and after inspection, inspection note was prepared alleging that the Petitioner has unauthorisedly supplied electric energy to SPPL and therefore, electric connection of the Petitioner was disconnected and the Respondent -Board had issued bill to the Petitioner for Rs. 4,74,262/- for committing breach of the conditions of electric energy by resale of energy.

2.4 Being aggrieved by the said Bill, the Petitioner filed Special Civil Application No. 6951 of 1998 before this Court. This Court was pleased to pass interim order on 29th August, 1998 and the Petitioner was asked to deposit Rs. 50,000/- with cost and Board was further directed to restore power connection to the Petitioner's unit forthwith. After lapse of more than two years, the Respondent-Board issued a revised Bill dated 20.6.2000 for Rs.17,42,344/- for the cost to the Petitioner on the ground that the Audit Department of the Government of Gujarat has raised objection and there was mistake on the part of the officers of Respondent-Board in calculating the amount of Bill issued in August, 1998. The said Bill was also objected by the Petitioner by its letter dated 27th June, 2000. Special Civil Application preferred by the petitioner was pending before this Court since 1998.

2.5 Thereafter, request was made by the Petitioner to withdraw the said petition on 12.1.2004 and the Petitioner was permitted to file Appeal before the Appellate Committee on condition that the Petitioner shall deposit Rs.4,35,585/-. The Petitioner approached the Appellate Committee and preferr

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon Back to top