IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
BIREN VAISHNAV, J.
Madhya Gujarat Vijli Co. Ltd. – Petitioner
Versus
Appellate Authority And Electrical Inspector & Anr. – Respondents
R/Special Civil Application No. 9035 Of 2018 With R/Special Civil Application No. 11589 of 2018
Decided On : 01-02-2023
Electricity Act - Unauthorized Use of Electricity - Section 126
Fact of the Case:
The petitioner, an electricity company, challenged the orders passed by the Appellate Authority & Electrical Inspector under section 127 of the Electricity Act, 2003. The cases involved consumers using electricity in excess of the sanctioned load limits, leading to provisional and final assessment of charges for unauthorized use of electricity.
Finding of the Court:
The Court held that consumption of electricity in excess of the contracted demand/sanctioned load/contracted demand amounts to unauthorized use of electricity and is governed solely by provisions of Section 126 and 127 of the Act. The Court also quashed the orders passed by the Appellate Authority, citing inconsistency with the mandatory provision of Section 126 of the Act.
Issues: 1. Whether consumption of electricity in excess of maximum of contracted demand/sanctioned load/contracted demand amounts to unauthorized use of electricity governed by Section 126 of the Act? 2. Whether Section 4.95 of the Supply Code is applicable to cases of excessive consumption of electricity covered under Section 126 of the Act?
Ratio Decidendi: The Court established that cases of overdrawal of electricity by the consumer constitute a breach of the terms of agreement, regulations, and the provisions of the Act and are liable to be dealt with under Section 126 of the Act, unless they get covered under Section 135 of the Act. The Court also found Section 4.95 of the Supply Code to be inconsistent with the mandatory provision of Section 126 of the Act and quashed the orders passed by the Appellate Authority.
Final Decision: The Court quashed and set aside the orders passed by the Appellate Authority and allowed the petitions, making the rule absolute accordingly.
ORDER :
1. Rule returnable forthwith. Mr. Rohan Shah, learned advocate appearing for respondent – Appellate Authority and Electrical Inspector waives service of notice of rule. Though served, none appears for respondent no. 2 in Special Civil Application No. 9035 of 2018 and though served, none appears for respondent no. 1 in Special Civil Application No. 11589 of 2018. Heard Mr. Maulik Nanavati, learned advocate for the petitioner – Electricity Company and Mr. Rohan Shah, learned AGP for respondent – Appellate Authority and Electrical Inspector.
2. Challenge in these petitions is to the orders dated 29.01.2018 and 17.04.2018 passed by the Appellate Authority & Electrical Inspector, Division Office, Nadiad under section 127 of the Electricity Act, 2003.
3. The facts of Special Civil Application No. 9035 of 2018 indicate that it is the case of the petitioner electricity company that though respondent no. 2 was having a sanctioned limit of 25 KW, when the premises was checked on 25.05.2017, it was found that the respondent no. 2 was using 91.214 KW and therefore was in excess of the sanctioned load limits by 66.214 KW from the NRGP connection. The respondent no. 2 was issued a provisional bill of Rs.3,59,913.89 ps on 30.05.2017. An opportunity of hearing was given to the respondent no. 2 to file his objections and after considering the same, the petitioner company issued the final supplementary bill of Rs.3,59,913.89 on 16.06.2017. The respondent consumer filed an appeal under Section 127 of the Act before the appellate authority after deposit of 50% of assessment amount. The appellate authority allowed the appeal on the ground that in light of section 4.95 of the Supply Code, 2015, the assessment was not in accordance with Section 4.95.
3.1 Facts of Special Civil Application No. 11589 of 2018 indicate that the respondent had applied for and was granted electricity connection (NRGP) with contracted load of 9 KW. On 03.07.2017, when a surprise inspection was carried out it was noticed that the private respondent was using 18.988 KW load instead of the sanctioned load of 9 KW. The usage of the consumer was thus found to be in excess of the sanctioned load limit by 9.988 KW. The petitioner company provisionally and then finally assessed that the amount payable by the respondent consumer for unauthorized use of electricity was Rs.38,022.60 ps. On an appeal filed by the respondent consumer the appellate authority though having found that the consumer was using more than the sanctioned load, allowed the appeal by observing that there has been a breach of clause 4.95 of the Supply Code which requires a distribution licencee to issue a notice to the consumer informing such consumer that they need to prefer an application for enhancement of the sanctioned load.
4. Mr. Maulik Nanavati, learned Advocate for the petitioner would submit that the order passed by the Appellate Authority quashing and setting aside the final order of assessment passed by the Assessing Officer under Section 126 of the Act only on the ground of violation of Clause 4.95 of the Supply Code is erroneous and contrary to law. He would contend that Section 126 of the Act contains the method of computing the amount that a consumer would be liable to pay for excessive consumption of electricity, being in the nature of unauthorised use of electricity. The purpose of Section 126 is to check and prevent misuse or unauthorized of electricity, and the section is a complete code in itself in so far as it relates to the manner of dealing with cases of unauthorised use of electricity. He would submit that Regulations framed by the Commission in exercise of power under Section 50 of the Act have no play in cases of unauthorized use of electricity covered under Section 126 of the Act or theft covered under Section 135 of the Act. He would urge that in the facts of the present case once the Appellate Authority confirmed the finding of fact that there was consumption by consumer of e
Uttar Pradesh Power Corporation Limited vs. Anis Ahmad reported in (2013) 8 SCC 491
(1) Unauthorised use of electricity – Overdrawal may lead to a disastrous situation being prejudicial to public at large – Overdrawal of electricity in excess of sanctioned/connected load may disturb....
Excess electricity consumption constitutes unauthorized use under Section 126 of the Electricity Act, 2003, which prevails over conflicting provisions in the Supply Code.
The provisions of Sections 126 and 127 of the Electricity Act, 2003 are self-contained codes, and an appeal under Section 127 is only available when there is a finding of unauthorized use of electric....
Unauthorized use of electricity for a purpose other than authorized and in premises other than those for which the supply was authorized constitutes a violation of Section 126 of the Electricity Act ....
The main legal point established in the judgment is that the assessment of the bill for unauthorized use was correctly done under Section 126 of the Electricity Act, 2003, and Section 56 of the Act d....
Sections 126 and 135 of the Electricity Act, 2003 are constitutionally valid, providing distinct frameworks for civil assessments and criminal penalties for unauthorized use and theft of electricity.
Electricity users must meet defined criteria for consumer status under Section 2(15); unauthorized use triggers assessments under Section 126 of the Electricity Act, which cannot be modified or waive....
Electricity - On a reading of Section 126 of the Act, 2003 and Regulation 27A, it is clear that a clear cut procedure is prescribed for dealing with unauthorised load, and merely because the Billing ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.