IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
N.V.ANJARIA, J.C. DOSHI, JJ.
Shapoorji Pallonji And Co. Pvt. Ltd. – Appellant
Versus
Gujarat State Electricity Corporation Ltd. – Respondent
R/Special Civil Application No. 9590 of 2023
Decided on : 01-07-2023
Special Civil Application - Arbitration and Conciliation Act, 1996 - Section 36 (3) and (2) , 34 - Special Civil Application - Arbitration - Prayed to stay the operation and implementation of the arbitral award – Held, no reason or ground could be spelt out to omit for respondent, to deposit interest and cost awarded by the Tribunal - There is no escape for respondent, in facts of case, to deposit interest and cost part as well if it is to seek stay of operation of arbitral award - It is nobodies case that ground of fraud or corruption exist - No other consideration could weigh for not requiring deposit of entire awarded amount as part of condition of stay - Order passed by Commercial Court below stands in error - It is required to be modified by directing respondent to deposit interest and cost as awarded by Arbitral Tribunal to be necessary condition for operation of stay of award - Petition is allowed
JUDGMENT :
N.V.ANJARIA, J.
What is prayed in this Special Civil Application is to modify the order dated 02.01.2023 passed by the Additional District Judge, Bhavnagar - Commercial Court, by directing the respondent herein to deposit 100% of the amount awarded by the Arbitral Tribunal as per its award dated 20.03.2020. It is prayed to require the respondent to deposit both, principal amount as well as interest and cost.
2. The aforementioned order dated 02.01.2023, below exhibit 5, came to be passed under section 36 of the Arbitration and Conciliation Act, 1996. Thereby, the respondent prayed to stay the operation and implementation of the arbitral award. The proceedings of section 34 of the Act are pending.
2.1 The operative part of the said order, prayed to be modified, is as under,
2. Nazir is hereby ordered to invest the said amount deposited, in any nationalized bank.
3. The respondent will be free to withdraw any portion of the said amount deposited in the court, which is deemed proper by the court, with the permission of the court. That any application for withdrawal to be preferred in this regard by Respondent may be preferred, but the said application shall be preferred two months after deposit of said amount in court.
4. Until Appellant/applicant deposits the abovesald amount in court and presents in this case Corporate Bank Guarantee within the time specified above, the Operation and implementation of above mentioned Arbitral Award shall stand stayed."
2.2 Paragraph 519 of the Award mentioned in the aforesaid operative portion, related to the principal amount awarded by the Arbitral Tribunal. In the award, interest awarded as per paragraph 523 and the cost part was also subsequently dealt with by the Arbitral Tribunal.
2.3 The grievance of the present petitioner centers around the aspect that the Commercial Court below directed deposit of the principal amount only, while granting stay of the arbitral award.
3. The facts to be noted in brief are that respondent Gujarat State Electricity Corporation Ltd. invited bids on 15.03.2010 for the purpose of construction of Lignite Thermal Power Plan at Padva, Bhavnagar. It was a contract for piling and general civil work to be executed in the project at Gandhinagar. Letter of award was issued on 01.07.2010 for a total sum of Rs.236.41 crores. Over a period of time, the said sum was increased by the respondent Corporation to Rs.449.34 crores. The petitioner stated that the work, as substantially enhanced above, was completed by it on 30.07.2015 and necessary completion certificate was issued by the respondent. As the respondent refused to pay the claims of the petitioner, the disputes arose. The petitioner invoked the arbitration clause in the contract.
3.1 The three member Arbitral Tribunal allowed the majority of claims by passing award dated 20.03.2020. The petitioner was found to be entitled to Rs.249,78,31,286/- with interest at the rate of 12 % from 24.03.2017 till realisation. The Arbitral Tribunal thereafter in exercise of powers under section 33 of the Act, modified the award as per order dated 28.07.2020 at the instance of the respondent. The Tribunal recorded that the petitioner's entitlement would be Rs. 233,73,91,405/-, which was less than what was earlier determined. The award was further modified on 04.08.2020.
3.1.1 The award of
Bhaven Construction vs. Executive Engineer
Deep Industries Ltd. vs. Oil & Natural Gas Corporation [(2020) 15 SCC 706
National Aluminum Co. Ltd. V. Pressteel & Fabrications
PAM Developments Pvt. Ltd. Vs. State of West Bengal [(2019) 8 SCC 112]
The court clarified that award debtors must deposit the full awarded sum as a condition for staying enforcement, emphasizing that both public and private parties are subject to the same requirements ....
The court affirmed its jurisdiction to review its orders while highlighting that a mere filing of a review petition does not grant a stay on award enforcement unless complying with statutory requirem....
The court emphasized that the conditions for stay of an arbitral award should not differ based on whether a party is a statutory body, reinforcing the principle of equal treatment under the Arbitrati....
The court determined that a Central Government authority is not required to deposit the total arbitral award amount for stay of execution pending appeal under exceptional circumstances.
An unconditional stay of an arbitral award is impermissible unless specific statutory conditions under Section 36(3) of the Arbitration Act are fulfilled.
The pendency of an application under Section 34 of the A&C Act is no longer a bar for enforcement of an arbitral award. The court must hear the application under Section 34 of the A&C Act on its meri....
The Court emphasized the limited scope of challenge against an award under the Act and balanced the equities between the parties in granting or modifying the order.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.