SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(SC) 1099

SUPREME COURT OF INDIA
Dr. D.Y. Chandrachud, CJI., J.B. Pardiwala, Manoj Misra, JJ.
International Seaport Dredging Pvt. Ltd. – Appellant
Versus
Kamarajar Port Ltd. – Respondent
Civil Appeal No. 12097 of 2024
Decided on : 24-10-2024

Advocates appeared:
For the Petitioner(s): Mr. Shyam Divan, Sr. Adv. Ms. Shally Bhasin, Adv. Mr. Chaitanya Safaya, Adv. Mr. Prateek Yadav, Adv. Mr. Adith Deshmukh, Adv. Mr. S. S. Shroff, AOR
For the Respondent(s): Mr. C A Sundaram, Sr. Adv. Ms. Rohini Musa, AOR

The court emphasized that the conditions for stay of an arbitral award should not differ based on whether a party is a statutory body, reinforcing the principle of equal treatment under the Arbitration Act.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 33 and Section 34 - Interim order - Appeal against stay of execution of arbitral award - High Court directed furnishing of bank guarantee instead of deposit of awarded amount - Court held that the High Court erred in not considering the entirety of the arbitral award and the status of the respondent as a statutory body should not influence the conditions for stay - The court modified the High Court's order, directing the respondent to deposit 75% of the awarded amount. (Paras 6, 10, 15, 17)

(B) Arbitration - Enforcement of arbitral awards - The sanctity of arbitration must be preserved by requiring deposit of the awarded amount as a condition for stay - The provisions of the Arbitration Act are self-contained and do not distinguish between governmental and private entities. (Paras 12, 14, 16)

Facts of the case:
The appeal arises from an interim order of the High Court granting a stay on the execution of an arbitral award of approximately Rs 21 crores in favor of the appellant, directing the respondent to furnish a bank guarantee instead of depositing the awarded amount. Disputes arose from a contract for capital dredging work at Kamarajar Port.

Findings of Court:
The High Court's order was modified, requiring the respondent to deposit 75% of the awarded amount, inclusive of interest, to stay the enforcement of the arbitral award.

Issues: The main issues were whether the High Court was justified in requiring a bank guarantee instead of a deposit of the awarded amount and the implications of the respondent's status as a statutory body on the stay conditions.

Ratio Decidendi: The court ruled that the High Court erred in its approach, emphasizing that the Arbitration Act does not provide for special treatment of governmental entities and that the conditions for stay should not be influenced by the nature of the parties involved.

Result: Appeal allowed and High Court's order modified.

JUDGMENT

Dr D.Y. Chandrachud, J.

1. Leave granted.

2. The appeal arises from an interim order dated 9 September 2024 of a Single Judge of the High Court of Judicature at Madras in A No 4236 of 2024 in Arb OP (Com Div) No 335 of 2024.

3. The respondent issued a Letter of Award for executing Capital Dredging Phase-III at Kamarajar Port to the appellant for an approximate sum of Rs 274 crores. On 12 August 2015, the parties entered into a contract for the following work to be conducted by the appellant:

    a. Capital dredging of Container Berth and Multi Cargo Berths and their

    b. Capital dredging of Coal Berth 3 & Coal Berth 4 and their approaches;

    c. Removal of onshore boulders and transportation to the designated area;

    d. Removal of offshore boulders and transportation to the designated area;

    e. Removal of offshore identified debris/wrecks; and

    f. Environmental monitoring.

4. These tasks were to be completed on or before 11 April 2017. Thereafter, disputes arose between the parties. The appellant invoked the arbitration agreement. The arbitral proceedings commenced and the three-member arbitral tribunal made an award on 7 March 2024 directing the respondent to:

    a. Pay the appellant a sum of Rs 21,07,66,621 towards the claims that were allowed in its favour;

    b. Pay the appellant interest on the amount awarded at the rate of nine per cent per annum from 15 November 2017 until the date of the award if the payment was made within three months, and, if not, at the rate of twelve per cent per annum from the date of the award till the date of payment; and

    c. Pay the appellant Rs 3,20,86,405 by way of costs.

5. Both parties filed applications under Section 33 of the Arbitration and Conciliation Act 1996 (“Arbitration Act”) for correction of the award and for additional arbitral awards. The arbitral tribunal dismissed the application filed by the respondent. It allowed the application filed by the appellant only to the extent of increasing the costs awarded to it by Rs 12,00,000 to reflect the fees paid to the arbitral tribunal subsequent to the parties filing their memo of costs.

6. The respondent challenged the arbitral award under Section 34 of the Arbitration Act and moved an application for stay of execution. The High Court, by its impugned judgment and order dated 9 September 2024, granted a stay on the execution of the award conditional on the respondent furnishing a bank guarantee in the sum of Rs 21,07,66,621 within a period of eight weeks.

7. The judgment of the High Court has been assailed by the original claimant of the arbitral proceeding (i.e., the appellant in this case) whose contention is that since the award operates as a money decree under Section 36 of the Arbitration Act, the High Court was not justified in directing merely the furnishing of a bank guarantee in relation to the principal amount. The appellant contends that the respondent ought to have instead been directed to deposit the amount awarded to it as a condition for the grant of a stay on the execution of the award.

8. Mr Shyam Divan, senior counsel appearing on behalf of the appellant, has urged that: (i) A body of precedent has emerged from this Court in terms of which the sanctity of arbitration must be preserved by requiring the deposit of the amount awarded as a condition for the stay on the enforcement of the award; (ii) The amended provisions of the Arbitration Act require that while considering an application for stay of an award for the payment of money, due regard has to be had to the provisions of the Code of Civil Procedure 1908 (“CPC”); and (iii) The award of Rs 21,07,66,621 covered ten claims of which three were awarded in full and seven in part. The High Court while ordering a stay, has essentially furnished only two reasons. The first reason pertains to the question of cess, while the only other reason is that the respondent is not “a fly by operator”.

9. Mr C A Sundaram, senior counsel appearing on behalf of the respondent, submits that: (i) The amended pr

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon Back to top