SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Guj) 1658

IN THE HIGH COURT OF GUJARAT AT AHMEDABAD 
HEMANT M. PRACHCHHAK, J.
Jaswant Construction - Appellant
Versus
State Of Gujarat & Ors. - Respondent
First Appeal No. 564 Of 2010
Decided On : 11-06-2025

Advocates:
Advocate Appeared:
For the Appellant : Mr KG Sukhwani
For the Respondent: Ms Krishna Desai AGP, Mr. HS Munshaw

A party's entitlement to damages in breach of contract cases must correlate with actual damages suffered; security deposits can be refunded when no loss is incurred by the other party.

Headnote:(A) Civil Procedure Code - Section 96 - Contract Law - Indian Contract Act, 1872 - Sections 74 - Breach of construction contract - Appeal filed against the dismissal of the suit for damages and refund of security deposit - The appellant claimed inability to finish work due to respondents' failure to provide site access due to farmer objections - The trial Court addressed issues including entitlement to debt and interest - Dismissed the suit, ruling the work completion failure was not justified for damages. (Paras 2.2 and 8)

(B) Breach of Contract - The court discussed the implications of contractual performance failures and damages - Cited previous apex court judgments noting compensation for breach must connect to actual damages suffered - The court found the appellant had no basis for claiming damages as the respondents incurred no loss due to delay. (Paras 8, 10, and 11)

Facts of the case:
The appellant was contracted for road construction; an injunction prevented project completion, leading to a claim for damages and refund of security deposit.

Findings of Court:
The appeal was partly allowed; the trial Court correctly rejected the damage claim but entitled the appellant to the refund of the security deposit with interest.

Issues: The key issues included whether the appellant was entitled to damages and the refund of security deposit.

Ratio Decidendi: The court emphasized that entitlement to damages must align with proven actual loss, thus ruling favorably on the security deposit refund while denying damages due to lack of corresponding loss.

Result: Appeal partly allowed.

Table of Content
1. factual background of construction contract dispute. (Para 1 , 2)
2. appellant's claims and respondent's defenses. (Para 4 , 5 , 6 , 7)
3. court's observation on trial court's error. (Para 8)
4. court's decision on damages and refund of security deposit. (Para 9)
5. final order on appeal and costs. (Para 10)

JUDGMENT :

HEMANT M. PRACHCHHAK, J.

1. Present appeal is directed against the impugned judgment and order dated 15.07.2005 passed by the learned Principal Senior Civil Judge, Civil Court (S.D.), Dhrangadhra, (hereinafter be referred to as “the trial Court”) in Special Civil Suit No. 23 of 1996 whereby the trial Court has dismissed the suit filed by the appellant – original claimant.

2. Facts of the present case, in nutshell, are that the appellant has undertaken construction work of Ganjela – Ghanad Road by hot mix plant and paver finishing work and for such construction, the respondents invited tender and estimated cost was Rs.9,14,066/- and the tender of the appellant was accepted being lowest amount at Rs.10,37,464.10. It is the case of the appellant that as per the terms and conditions of the agreement, the appellant had deposited Rs.18,300/- towards requisite fixed deposit and the work order was issued and the work was to be completed within twelve months. It is also the case of the appellant that the respondents have failed to hand over the possession of the site within reasonable time, for which the appellant has drawn the attention to the respondents, however, respondent No.3 was unable to handover the site of construction because of monsoon and rainy water the road was damaged. It is alleged that some farmers raised objection towards the road and not permitted the appellant to carry out the work and obtained stay from the concerned Civil Court. That the raw material of the work was not supplied by the respondents as and when asked by the appellant and watering work was not completed by the respondents before monsoon, so the appellant was not in a position to start and complete the work as per the contract. It is the case of the appellant that as per the agreement, the appellant was not in a position to start this work because of the fault on the part of the respondents and for considerable long time, it was not started and because of delay occurred on the part of the respondents and, therefore, the appellant is entitled to get revised rates. It is the case of the appellant that the running bills were not paid within time to the appellant, so the appellant was not in a position to complete the work in time and, therefore, the appellant suffered loss in profit.

2.1 After considering the details, the trial Court framed the issues at Exhibit 19 which reads as under:-

1. Whether plaintiff proves debt as averred in plaint against defendants?

2. Whether plaintiff is entitled to get interest on suit amount? If yes, at what rate and from which date?

3. What order and decree?

2.2 The trial Court answered to aforesaid issue Nos.1 and 2 in negative and issue No.3 as per final order.

2.3 The trial Court has, after considering the documents produced by the appellant and documents produced by the respondents and after evaluating the evidence, dismissed the suit of the appellant.

3. Being aggrieved and dissatisfied with the impugned judgment and order, the present appeal is filed by the appellant.

4. Heard Mr.K. G. Sukhwani, learned counsel appearing for the appellant, Ms.Krishna Desai, learned Assistant Government Pleader appearing for the respondent No.1 and Mr.H. S. Munshaw, learned counsel appearing for respondents No.2 and 3 at length.

5. Mr.Sukhwani, learned counsel appearing for the appellant has submitted that the appellant could not complete the work for which the contract was allocated because of the dispute arose between the authority and the farmers whose lands were used for laying down the road between the Village Ganjela – Ghanad and, therefore, the appellant has prayed for the damages and the amount which is kep

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top