IN THE HIGH COURT OF GAUHATI
SUMAN SHYAM, J.
G. AND T BECKFIELD DRILLING SERVICES PVT LTD - Appellant
Versus
OIL AND NATURAL GAS CORPORATION LTD - Respondent
Arbitration Appeal No. 3 of 2007
Decided on : 08-03-2019
Beckfield Drilling Services - Arbitration and Conciliation Act, 1996 - Sections 37, 16(3), 34, 5, 29(1) and 31 - Facts are not in dispute in this case - facts essential for disposal of this appeal shorn of un-necessary details are that respondent had floated inviting offers for carrying out Horizontal Drain Hole Drilling in respect of its designated oil wells situated in Upper Assam - In response to Beckfield Drilling Services a company incorporated in United States of America had made its offer on which was accepted by respondent a Letter of Intent was issued in favour of Beckfield Drilling Services - However by letter while acknowledging acceptance of Beckfield Drilling Services had made a request to respondent for assignment of contract in favour of its Joint Venture partner in India - appellant here-in Government of India had conveyed its approval with regard to collaboration between Beckfield and appellant whereafter by communication respondent had also accepted request for assignment of LoI in favour of appellant contract agreement was signed by and in between respondent on one hand and M/s Beckfield Drilling Services as well as representatives of appellant on other hand - Thereafter execution of work commenced with effect with due approval from respondent - However on respondent had issued a notice of termination of contract giving to appellant - In meantime on appellant had raised its first invoice demanding payment for work already executed by it followed by another invoices involving a total amount – Held, Again In case of McDermott International vs - Burn Standard Co - Ltd - And Others reported in it has been held that construction of a contract agreement would be within jurisdiction of arbitrators and that conduct of parties would also be a relevant factor in matter of construction of a contract - From various judicial pronouncements noticed above it would be apparent that scope of interference with an arbitral award by court is extremely limited - While exercising jurisdiction of Act court would have to confine its considerations to grounds mentioned there-in and refrain from interfering with award unless there is an error apparent on face of award or award is found to be in conflict with - In present case in view of what has been stated above I am of considered opinion that there was no ground available for learned District Judge to set aside arbitral award - Consequently impugned judgment and order is held to be unsustainable in law and same is accordingly set aside – Order accordingly.
SUMAN SHYAM, J.
1. This appeal has been filed under Section 37 of the Arbitration and Conciliation Act, 1996( herein-after referred to as the "Act of 1996") assailing the judgment and order dated 15.11.2007 passed by the learned District Judge, Sivasagar in Misc Arb Case No.26 of 2005, setting aside the arbitral award dated 21.11.2004.
2. The basic facts are not in dispute in this case. The facts essential for disposal of this appeal, shorn of un-necessary details, are that the respondent/ ONGC had floated an NIT on 06.02.1995 inviting offers for carrying out Horizontal Drain Hole Drilling in respect of 4 (four) of its designated oil wells situated in the Upper Assam. In response to the NIT dated 06.02.1995, M/S Beckfield Drilling Services, USA, a company incorporated in the United States of America, had made its offer on 12.03.1995 which was accepted by the respondent on 23.05.1995. On 25.07.1995, a Letter of Intent (LoI) was issued in favour of M/S Beckfield Drilling Services, USA. However, by the letter dated 30.07.1995, while acknowledging the acceptance of the LoI, M/S Beckfield Drilling Services, USA had made a request to the respondent for assignment of the contract in favour of its Joint Venture (JV) partner in India viz. M/S G & T Beckfield Drilling Services (Pvt.) Ltd. i.e. the appellant here-in. On 07.08.1995, the Government of India had conveyed its approval with regard to the collaboration between Beckfield, USA and the appellant, whereafter, by the communication dated 20.10.1995, the respondent had also accepted the request for assignment of the LoI in favour of the appellant. On 17.08.1996, a contract agreement was signed by and in between the respondent on one hand and M/s Beckfield Drilling Services, USA as well as the representatives of the appellant on the other hand. Thereafter, execution of the work commenced with effect from 17.08.1996 with due approval from the respondent. However, on 14.03.1997, the respondent had issued a notice of termination of contract giving 15 days' notice to the appellant. In the meantime, on 07.10.1996, the appellant had raised its first invoice demanding payment for the work already executed by it followed by another 9 (nine) invoices involving a total amount of $11,85,939.98 (U.S. Dollar).It appears that the respondent had made payment in respect of the first 4 (four) invoices raised by the appellant for a sum of $ 4,71,754.19 (US Dollar) but it had refused to make payment in respect of the remaining 6 (six) invoices. When the legal notice dated 10.04.1998 sent on behalf of the appellant demanding payment in respect of the balance amount was not responded to nor any payment made by to the appellant, a dispute had arisen between the parties. As such, by the legal notice dated 06.06.1998, the appellant had invoked the arbitration clause seeking adjudication of its claim by an arbitral tribunal and accordingly appointed Hon'ble Justice K.N.Saikia, a former Judge of the Supreme Court of India( here-in-after referred to as the First Arbitrator for the sake of convenience ) as its arbitrator under clause 25 of the agreement dated 07.08.1995 and called upon the respondent to appoint its arbitrator. On 18.08.1998, the respondent had appointed Hon'ble Justice M.M.Dutt, a former Judge of the Supreme Court of India ( here-in-after referred to as the Second Arbitrator for the sake of convenience) to act as an arbitrator on its behalf. Both the arbitrators had thereafter, appointed Hon'ble Justice A.N.Sen, Former Judge of the Supreme Court of India ( here-in-after referred to as the Presiding Arbitrator) to act as the Presiding Arbitrator. The first sitting of the arbitral tribunal was held on 24.10.1998.
3. It appears from the record that after the filing of claims and counter-claims, the respondent had filed an application under Section 16(3) of the Act of 1996 questioning t
Anand Bros. (P) Ltd. Vs. Union of India
Associate Builders Vs. Delhi Development Authority
Konkan Rly Corpn Ltd. Vs. Mehul Construction Co.
McDermott International Inc Vs. Burn Standard Co. Ltd. And Other
SomDatt Builders Ltd. Vs. State of Kerala
Steel Authority of India Vs. Gupta Brothers Steel Tubes Limited
Sumitomo Heavy Industries Ltd. Vs. Oil and Natural Gas Commission of India
SupremeToday
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.