IN THE HIGH COURT OF GAUHATI
Suman Shyam, J.
Rsvcpl Akg Jv C/o- Ashim Kumar Ghosh - Appellant
Versus
Union Of India And Others - Respondent
W.P. (C)(Writ Petition (Civil)) No. 2806 of 2020
Decided On : 05-02-2021
Tender Committee Decision - Bid Capacity - [N.F. Railway Tender] - [Annexure-VI, Clause 2(C)] - The court upheld the Tender Committee's decision to reject the technical bid of the petitioner due to non-compliance with the prescribed format for calculating bid capacity. The court emphasized the importance of adhering to essential tender conditions and minimal judicial interference in matters of government contracts. The decision was found to be in conformity with the tender conditions and in the public interest, as the project was identified as critical.
Fact of the Case:
The petitioner's technical bid for a railway project was rejected by the Tender Committee due to negative bid capacity, as calculated based on the prescribed format in the tender document. The petitioner had previously approached the court with similar grievances, which were disposed of with directions to consider all documents submitted by the petitioner for bid capacity calculation. The petitioner raised objections regarding the respondent no. 5's bid and the registration on the IREPS portal.
Finding of the Court:
The court found that the Tender Committee's decision was justified as the petitioner failed to comply with the prescribed format for bid capacity calculation. The court also rejected the petitioner's objections regarding the respondent no. 5's bid and registration on the IREPS portal, citing lack of challenge to the LoA and substantial progress in the project execution. The court emphasized the importance of adhering to essential tender conditions and minimal judicial interference in matters of government contracts.
Issues: Non-compliance with prescribed format for bid capacity calculation, objections regarding respondent no. 5's bid and registration on the IREPS portal.
Ratio Decidendi: The court upheld the Tender Committee's decision, emphasizing the importance of adhering to essential tender conditions and minimal judicial interference in matters of government contracts. The decision was found to be in conformity with the tender conditions and in the public interest, as the project was identified as critical.
Final Decision: The writ petition was dismissed, and parties were directed to bear their own costs.
JUDGMENT
Suman Shyam, J. - Heard Mr. N. Dutta, learned senior counsel assisted by Mr. N.N.B. Choudhury, learned counsel appearing for the writ petitioner. Also heard Mr. A. Dasgupta, learned senior counsel assisted by Mr. G. Goswami, learned Standing Counsel, N.F. Railways authorities i.e. respondents Nos 2 and 3 and Mr. K.N. Choudhury, learned senior counsel assisted by Mr. R.M. Deka, learned counsel representing the respondent no. 5. None appears for the respondent no.1 Union of India. The name of the respondent no. 4 has been struck of by the order dated 10-11-2020 passed by this Court.
2. Considering the urgency expressed in this matter and as agreed to by the learned counsel for all the parties, this writ petition is being taken up for disposal at the stage of admission hearing.
3. The minutes of the Tender Committee meeting held on 18/06/2020 rejecting the technical bid submitted by the petitioner has been assailed in the present writ petition, interalia, on the ground that the decision of the Tender Committee is not only arbitrary and illegal but the same is also in violation of the order dated 03/06/2020 passed by this Court in WP(C) No. 1897/2020.
4. The facts necessary for disposal of this writ petition are briefly narrated herein below :-
(i) The North East Frontier Railway (N.F. Railway), through the respondent No. 3, had issued Tender Notice dated 17/12/2019 bearing No. Con.2019/DEC/05, inviting bids, in two parts, from reputed contractor(s)/firm(s) for executing as many as 4 (four) different contractual works. The Joint Venture (JV) of the writ petitioner had submitted its bid in respect of three tenders which were identical in nature including tender no. CE/Con/NA/EMB/2019/DEC/05/RT-I for the work "Earthwork in formation for making Railway embankment, construction of minor bridges, blanketing work, construction of RCC drain and all other connected ancillary works between Km 251.40 to 277.00 between New Bongaigaon (NBQ) Agithori (AGT) BG doubling project". The tender value of the contract was Rs. 68,61,09,256.68p and the period of completion was 18 months. The writ petitioner JV had also submitted its bid in respect of another tender bearing No. CE/CON/NA/EM/B/2019/06/RT-1, included in the Tender Notice dated 17-12-2019. However, in the present case, we are concerned only with the tender no. CE/Con/N-A/EMB/2019/DEC/05/RT-I and, therefore, it would not be necessary to refer to the particulars of the other tender.
(ii) It appears from the record that for this tender, there were four bidders in total. The technical bids were opened on 14/02/2020. After examining the technocommercial bids, the Tender Evaluation Committee had finalized the same and uploaded its decision on 28/02/2020, whereby, the technical bid submitted by the writ petitioner was shown to be non-responsive due to "negative bid capacity". It appears that the writ petitioner's technical bid was rejected on similar grounds in respect of Tender No. CE/CON/N-A/EM/B/2019/06/RT-1 as well.
(iii) Aggrieved by the aforesaid decision of the Tender Evaluation Committee, the petitioner had earler approached this Court by filing two writ petitions being WP(C) 1897/2020 and W.P.(c) No 1900/2020 pertaining to the contract Nos. "CE/Con/NA/EMB/2019/DEC/05/RT-1" and "CE/CON/N-A/EM/B/2019/06/RT-1" respectively. The basic grievance expressed in the aforesaid writ petitions was to the effect that the N.F.Railway authorities had failed to take into account all the documents submitted by the petitioner along with its tender indicating the total value of the work executed by it during the relevant period for the purpose of calculating the "bid capacity" and therefore, the decision of the Tender Committee was erroneous. It was also contended that the private respondent having failed to register itself in the IREPS portal of the department, its technical bid was also liable to be rejected on the ground of non-conformity with the mandatory condition contained in clause -8 of the Tend
Central Coal Fields Ltd. vs SLL-SML
Michigan Rubber (India)Ltd. vs. State of Karnataka
Raunaq International Ltd. vs. I.V.R. Construction Ltd. and others
Silppi Constructions Contractors vs. Union of India and others
The court emphasized the importance of adhering to essential tender conditions and minimal judicial interference in matters of government contracts, upholding the Tender Committee's decision to rejec....
The main legal point established in the judgment is the requirement for strict compliance with essential conditions in a tender, and the need for substantial compliance with the broader objectives of....
Judicial review in tender matters is limited to assessing procedural fairness, not the merits of the tender conditions, which are determined by the tendering authority.
The court upheld the tendering authority's discretion in setting eligibility criteria, emphasizing limited judicial review focused on procedural fairness rather than the merits of the decision.
Important Point – Government Contract – Tender – Public authorities have to ensure that no bias, favouritism or arbitrariness are shown during bidding process and that entire bidding process is carri....
The court affirmed that the interpretation of tender conditions by the authority is paramount, and minor technical deficiencies do not justify judicial intervention.
The court emphasized the limited scope of judicial review in tender matters, the importance of punctilious and rigid enforcement of tender terms, and the uniform application of tender requirements to....
The court upheld the authority's discretion in evaluating tender bids, emphasizing the need for compliance with mandatory conditions and the absence of arbitrariness in disqualification decisions.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.