SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Cal) 1054

IN THE HIGH COURT AT CALCUTTA
SHAMPA SARKAR, J.
Shyam Indus Power Solutions Private Limited – Petitioner
Versus
Union of India and Others – Respondents
W.P.A. No. 16917 of 2024
Decided On : 11-07-2024

Advocates:
Advocate Appeared:
For the Petitioners: Debashis Kundu, Saumyen Datta, Rajendra Nath Barik, Sambu Prasad, P.K. Thakur.
For the Respondents: Soorjya Ganguli, Somdutta Bhattacharyya, Arti Bhattacharyya, Mohit Das.
For the Railway Authorities : Ms. Aparna Banerjee.

IMPORTANT POINT
The court affirmed that the interpretation of tender conditions by the authority is paramount, and minor technical deficiencies do not justify judicial intervention.

Headnote:

Tender - Bid Rejection - Clause 12.25, 2.2(c)(3) - The court upheld the tendering authority's decision to reject the bid based on non-compliance with specified documentation requirements, emphasizing the authority's discretion in interpreting tender conditions.

Fact of the Case:

The petitioner participated in a tender by the South Eastern Railway but was informed that their bid was unsuitable due to the lack of certification by a Chartered Accountant regarding bid capacity.

Finding of the Court:

The court found that the tendering authority's interpretation of the bid requirements was valid and that the petitioner failed to meet the necessary documentation standards as outlined in the tender conditions.

Issues: Whether the rejection of the petitioner's bid was justified based on the tendering authority's interpretation of the required documentation and compliance with tender conditions.

Ratio Decidendi: The court held that the tendering authority is best positioned to interpret its own documents and that the rejection of the bid, even on technical grounds, does not warrant judicial interference unless there is evidence of mala fides or arbitrariness.

Result: The writ petition is dismissed.

JUDGMENT :

SHAMPA SARKAR, J.

1. Supplementary affidavit filed by the petitioner is kept on record.

2. The petitioner participated in a tender floated by the South Eastern Railway. The Chief Engineer/Con/II/GRC, South Eastern Railway, Garden Reach, Kolkata, intimated the petitioner that the techno commercial bid of the petitioner was found unsuitable. The petitioner’s bid had failed, as the bid capacity was not certified by the Chartered Accountant.

3. Mr. Kundu, learned Senior Advocate appearing for the petitioner has assailed the cancellation of the bid on the following grounds:

    (a) The documents as specified in clause 12.25 of the tender conditions had been certified by the Chartered Accountant. According to Mr. Kundu, the format at page 78 of the writ petition was the profoma in which the information was to be given and the said proforma was duly filled in, with the signature and certification of Chartered Accountant.

(b) The authority failed to consider the documents deposited by the bidder in support of his credentials (bid capacity). The information document as per Note-(a)(i) and (ii) were duly certified by the Chartered Accountant and those documents have been produced before this Court by way of a supplementary affidavit.

(c) The authority could not have created an additional clause thereby cancelling the bid when the exact format had been annexed to the bid documents which is at page 78 of the writ petition. The authority had used a hyper-technical reason to cancel the bid of the petitioner and favour some other persons. Such arbitrary cancellation of the bid should be struck down by a writ court. The authority intentionally mis-interpreted their clause just to oust the petitioner from free and fair competition.

(d) According to Mr. Kundu, no other defect or deficiency in the bid capacity could be pointed out, save and except the absence of the Chartered Accountant’s signature and the certification was not in the manner the tendering authority had wanted the same to be. Such expectation of the railways had not been clearly stated in the bid documents. All that the tenderers was required to file was valuation of the work done in the past three years, the money received and the average annual contractual turnover for the past three years. Such information had been provided. Hence, the writ petition should be allowed by quashing the decision of the tendering authority as communicated to the petitioner on June 25, 2024 with a further direction upon the authority to open the petitioner’s financial bid.

4. The learned Advocate for the tending authority submits that clause 2.2 (c) (3) of the Notice Inviting Tender (NIT) specified that scanned copies and the copies in the PDF of the documents for evaluating the bid capacity must be produced and the bid capacity should be as per clause 12.25. The provision was made applicable in respect of all works contract having tender value of Rs.20 crores and above. As the tender value in this NIT was around Rs.43 crores, the said clause and clause 12.25 were applicable.

5. Referring to clause 12.25, it is submitted that the said clause provides the method by which the bid capacity should be calculated. Available Bid Capacity = [A x N x 2] - 0.33 x N x B.

6. Referring to the Note appended the said clause, it is submitted that the tenderers were required to submit two things; (i) maximum value of construction works executed and payment received in any one of the previous three financial years or the current financial year up to the date of inviting tender for calculating component A and (ii) existing commitments and balance amount of ongoing works with tenderer as per the prescribed proforma. It is submitted that both these calculations were required to be duly verified by a Chartered Account.

7. According to the Ms. Banerjee, Page 119 of the writ petition will indicate that the petitioner had only provided the average contractual turnover, i.e. the income received, whereas, the conditions required t

                    Click Here to Read the rest of this document
                    1
                    2
                    3
                    4
                    5
                    6
                    7
                    8
                    9
                    10
                    11
                    SupremeToday Portrait Ad
                    supreme today icon
                    logo-black

                    An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                    Please visit our Training & Support
                    Center or Contact Us for assistance

                    qr

                    Scan Me!

                    India’s Legal research and Law Firm App, Download now!

                    For Daily Legal Updates, Join us on :

                    whatsapp-icon Back to top