IN THE HIGH COURT OF GAUHATI, ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH
SUMAN SHYAM, J.
Dr. N. Sahewalla and Company Pvt. Ltd. - Petitioner
Versus
The Union of India, Represented By Its Secretary, Ministry of Defense, Government of India & Ors. - Respondents
W.P.(C) No. 4153 of 2022
Decided On : 04-08-2022
Companies Act, 1956 - Seeking to raise permanent construction - Petitioner company is seeking to raise permanent construction over its own land - As per the guidelines issued by Ministry of Defence, it was laid down that for any construction coming up within 100 meters of a defence installation/establishment and 500 mtrs. in case of building more than 4 stories, the 'NOC' from the Station Commander would be required as the same might pose security hazard to such defence installation - Whether boundary wall constructed by petitioner company did comply with the terms of notification - 'NOC' from defence authorities would be required only if construction is raised within limit of 10 mtrs. from outer wall of the defence establishment. (Para 8)
Findings of the Court :
Court has already held that for purpose of issuance of ‘NOC’ for raising constructions within vicinity of Defence/Army installations, notification will hold field and, therefore, all such issues would have to be considered and resolved in light of said notification - Court find from communication issued by respondent addressed to the respondent no. 5 that construction undertaken by petitioner is in between 80 meters to 100 meters away from boundary wall of defence installation, represented by respondent nos. 4 and 5 - However, there is no indication as to whether boundary wall constructed by petitioner company did comply with terms of notification - Factual verification of said aspect of matter would be called for.
Result : Writ petition disposed of.
JUDGMENT :
1. Heard Mr. G.N. Sahewalla, learned senior counsel assisted by Mr. P.K. Deka, learned counsel for the writ petitioner. Also heard Mr. S.K. Medhi, learned CGC, appearing on behalf of the respondent nos. 1, 2, 4 and 5 and Mr. S.C. Keyal, leaned counsel representing the respondent no. 3.
2. This writ petition has been filed being aggrieved by the order dated 08/06/2022 (Annexure-VII) whereby, the respondent no. 3 had kept in abeyance the building ‘NOC’ earlier issued in favour of the petitioner company for construction of a G+4 building.
3. The facts of the case, in a nutshell, may be noticed as follows:-
4. The writ petitioner herein is a company registered under the Companies Act, 1956. The petitioner company had purchased a plot of land measuring 8 Bighas 17 Lechas in Jorhat Town within the Jorhat Municipal Board area, which is situated contiguous to the land and building identified as ‘Jorhat-Lichubari Army Camp”. The petitioner company had applied for ‘NOC’ from the Jorhat Development Authority for construction of a multistoried building for setting up a multi-specialty hospital and on consideration of such application made by the petitioner, the respondent no. 3 had also granted ‘NOC’ vide building permission dated 04/03/2022. Thereafter, the petitioner had commenced construction work and a boundary wall was also constructed. The construction of the multistoried building, was for the purpose of running a super specialty hospital in the name and style “M/s. Aditya Diagnostic and Hospital”. However, when the construction of the building was under progress, the respondent no. 5 had written a letter dated 06/06/2022 to the respondent no. 3 with a request to cancel the ‘NOC’ by stating that the request for issuance of ‘NOC’ made to it by the writ petitioner had been rejected. Acting on the basis of the letter dated 06/06/2022 issued by the Army Authorities, the impugned order dated 08/06/2022 has been issued by the respondent no. 3 suspending the ‘NOC’.
5. By referring to the materials available on record, Mr. Sahewalla, learned senior counsel for the petitioner submits that the petitioner company is seeking to raise permanent construction over its own land. As per the guidelines issued by the Ministry of Defence on 18/05/2011, it was laid down that for any construction coming up within 100 meters of a defence installation/establishment and 500 mtrs. in case of building more than 4 stories, the ‘NOC’ from the Station Commander would be required as the same might pose security hazard to such defence installation. However, subsequently submits Mr. Sahewalla, the notification dated 18/05/2011 has been modified by the notification dated 21/10/2016 issued by the Government of India, Ministry of Defence, whereby, the radius of such restriction in construction has been reduced to 10 mtrs. from the outer wall of such defence installation/establishment.
6. By referring to the documents available on record, Mr. Sahewalla further submits that the construction of the multistoried building raised by the petitioner company is at-least 70 mtrs. away from the defence installation and, therefore, under the existing circular dated 21/10/2016, there was no necessity for the writ petitioner to obtain any NOC from the respondent nos. 4 and 5. Laying heavy emphasis on clause 2(a) of the notification dated 21/10/2016, Mr. Sahewalla submits that the impugned order dated 08/06/2022 is wholly arbitrary and illegal and hence, liable to be set-aside by the Court. It is also the submission of Mr. Sahewalla that the Air Force has already granted ‘NOC’ to the petitioner and therefore, there was no justifiable ground for the respondent nos. 4 and 5 to raise such objection, more so, since there are no windows in the building of the respondents towards the side of the construction raised by the writ petitioner.
7. The learned senior counsel for the petitioner has also submitted that the respondent nos. 4 and 5 had earlier approached the Court of learned Civ
Point of Law : No such 'NOC' from Defence Authority would be necessary if construction is beyond 10 meters from outer wall of defence installation.
Abeyance of superseding defence circular does not revive prior ones; construction rights crystallize under interim regime permissions; NOC not mandatory beyond 50m without statutory backing or state ....
Court clarified that height restrictions in construction near military establishments are not applicable if the construction is beyond certain distances established in guidelines. No NOC is required ....
Amendments to building rules by the State do not violate national security laws, and enforcement of the Works of Defence Act is the responsibility of the Union authorities.
NOC is not required for constructions within 500 mtrs. of Defence Establishment if they do not exceed 4 multistoreys and 15 mtrs. in height.
The court established that existing permanent constructions completed before the issuance of a restrictive Notification under the Works of Defence Act are exempt from such restrictions, permitting th....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.