IN THE HIGH COURT OF GAUHATI
Devashis Baruah, J.
FAIZUL HAQUE BARBHUIYA — Appellant
Vs.
UNION OF INDIA AND OTHERS — Respondents
W.P. (C) No. 3472/2020
Decided On : 10-01-2022
Compensation - Land Acquisition - National Highway Act, 1956 - [Article 226, Compensation, National Highway Act, 1956]
Fact of the Case:
The petitioner sought compensation for the acquisition of his land and residential building for the extension of a highway. The authorities initially assessed the compensation at a lower amount, and despite subsequent reassessment, the petitioner had not received the revised compensation.
Finding of the Court:
The court found that the petitioner was entitled to the revised compensation amount of Rs. 5,88,773, as determined by the competent authority. The court directed the respondent authorities to verify and pay the entitled amount within two months.
Issues: Non-payment of assessed compensation, Dispossession of petitioner's land and house, Delay in receiving legitimate dues
Ratio Decidendi: The court emphasized the petitioner's right to receive the legitimate compensation for the acquisition of his land and house, noting the delay in payment despite the authorities' acknowledgment of the entitled amount.
Final Decision: The court directed the respondent authorities to verify and pay the entitled compensation amount of Rs. 5,88,773 or such other amounts within two months.
JUDGMENT :
Devashis Baruah, J.
1. Heard Mr. M.J. Quadir, learned counsel appearing on behalf of the petitioner. I have also heard Mr. K.K. Parashar, learned counsel appearing on behalf of the respondent no. 1, Mrs. S. Sarma, learned counsel appearing on behalf of the respondent nos. 2, 3, 4, 5 & 7 and Ms. M. Barman, learned counsel appearing on behalf of the respondent no. 6.
2. This is an application under Article 226 of the Constitution whereby the petitioner being aggrieved for non-payment of the admitted assessed compensation of Rs. 5,88,773/- have approached this Court.
3. The brief facts of the instant case is that the petitioner owns various new plot of land including a plot of land which had a residential Assam type RCC building bearing holding No. 241, situated at village Rajeshwarpur, P.O. Lala in the District of Hailakandi. As the petitioner's house stands on the left side of National Highway 154, in the year 2007 the high way was surveyed for extending its width to 25 meters from the existing 20 meters and resultantly, a shop house appertaining to petitioner's residential building and some trees etc had fallen within the surveyed area of extended 5 meters.
4. The officials of Deputy Commissioner, Hailakandi initially calculated the compensation of the petitioner at Rs. 1,14,577/-. The petitioner aggrieved by the determination of the compensation filed a representation before the Deputy Commissioner, Hailakandi. However, the Deputy Commissioner Hailakandi did not take any step for which the petitioner approached this Court under Article 226 of the Constitution which is registered and number as WP (C) No. 751/2010.
5. This Court vide an order dated 04.12.2014 instead of adjudicating the dispute on merits and taking into consideration that the claim made by the petitioner may require consideration of evidence closed the said writ petition with the liberty to the petitioner to approach the competent authority under the National Highway Act, 1956, so that he could adduce necessary evidence for consideration before the said authority. It may be relevant to mention that in paragraph no. 3 of the said order date 04.12.2014, it was observed that the petitioner had admitted that an amount of Rs. 1,14,577/- was already paid as compensation.
6. In view of a factual error being recorded in the order dated 04.12.2014 to the effect that the petitioner had admitted of receiving an amount of Rs. 1,14,557/- was paid to the petitioner as compensation, the petitioner approached this Court again by way of review petition which was registered and numbers as Review Petition no. 19/2015.
7. This Court vide an order dated 23.2.2015 corrected the factual error with an observation that 'it is now to be noted that although Rs. 1,14,577/- was tendered to the petitioner, he refused to accept the same.' After noting the said, this Court closed the Review Petition with the direction that in the event the higher compensation claimed by the petitioner is allowed by the competent authority the tendered amount (not received) should be adjusted with the eventual amount.
8. The petitioner thereafter, filed their representation before the respondent no. 6 for re-determination of the compensation. Pursuant thereto, the Assistant Executive Engineer, PWD Hailakandi Building Division re-assessed the valuation at Rs. 6,21,985/-. Subsequent thereto the Executive Engineer, PWD submitted the assessment of the valuation of the building on 07.07.2018 by communication to the Deputy Commissioner, Hailakandi showing that the petitioner is entitled to Rs. 5,88,773/-.
9. The Deputy Commissioner Hailakandi/competent authority accepted the said amount of Rs. 5,88,773/- as the value to which the petitioner is entitled to as the compensation and accordingly, by the communication dated 06.08.2018 submitted the revised LA estimate for the amount of Rs. 5,88,773/- and for consequential payment of compensation to the petitioner at an early date to avoid contempt proceedings.
10. Subsequ
AI
The right of a petitioner to receive legitimate compensation for land acquisition under the National Highway Act, 1956, and the obligation of the authorities to timely verify and pay the entitled amo....
Section 3-G(4) of Act stipulates that such notice shall state particulars of land and shall require all persons interested in such land to appear in person or by an agent or by a legal practitioner b....
The arbitral award on land compensation cannot be modified without participation of affected parties, ensuring rights to compensation are upheld as originally awarded.
The National Highways Act, 1956 mandates that once land is vested in the Central Government, compensation must be paid to affected landowners regardless of possession, ensuring their rights are prote....
Finality of unappealed land acquisition compensation enhancement order binds parties for payment.
when the suit is pending before the competent Civil Court, the rights can be crystallized only by the competent Civil Court not by this Court under Article 226 of the Constitution of India
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.