2023 Supreme(Gau) 1503

IN THE HIGH COURT OF GAUHATI, ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH
MANISH CHOUDHURY, J.
Robi Boruah S/o Late Bijay Boruah – Petitioner
Versus
Northeast Frontier Railway, Maligaon – Respondent
Writ Petition (C) No. 6700 of 2021
Decided On : 25-08-2023

Advocates:
Advocate Appeared:
For the Petitioner: P.J. Saikia, R.S. Mishra.
For the Respondent: U. Chakraborty.

IMPORTANT POINT
The acceptance of a non-responsive tender violates established tendering criteria and principles of fairness, leading to arbitrary and discriminatory treatment of compliant bidders.

Headnote:

TENDERING PROCESS - GARBAGE DISPOSAL CONTRACT - HAZARDOUS AND OTHER WASTES (MANAGEMENT AND TRANSBOUNDARY MOVEMENT) RULES, 2016; ARTICLE 14 OF THE CONSTITUTION OF INDIA - The court discussed the requirements set forth in the Notice Inviting Tender (NIT) and the Tender Document, particularly the necessity for an Authorization Certificate from the Pollution Control Board as per the Hazardous and Other Wastes Rules. The court emphasized that the tendering authority must adhere to its own established criteria, and any deviation constitutes arbitrary action. The court found that the respondent no. 3 did not meet the eligibility criteria, leading to the conclusion that the award of the contract was invalid and discriminatory against the petitioner.

Fact of the Case:

The petitioner challenged the award of a garbage disposal contract to respondent no. 3 by the North East Frontier Railway, arguing that the latter did not fulfill the necessary eligibility criteria as outlined in the NIT and Tender Document, specifically regarding the submission of an Authorization Certificate from the Pollution Control Board.

Finding of the Court:

The court found that the respondent no. 3 did not possess the required Authorization Certificate at the time of tender submission, rendering their bid non-responsive. The court held that the N.F. Railway authorities acted arbitrarily by accepting a non-compliant tender, violating the principles of fairness and equality in the tendering process.

Issues: Whether the N.F. Railway authorities violated the tendering norms by accepting a non-responsive tender and whether the petitioner was denied equal opportunity in the tender process.

Ratio Decidendi: The court established that administrative authorities must adhere to their own rules and standards in tender processes. Acceptance of a non-responsive tender undermines the principles of equality and fairness, as enshrined in Article 14 of the Constitution of India.

Final Decision: The court quashed the award of the contract to respondent no. 3 and directed the N.F. Railway authorities to revisit the tender process within one month.

JUDGMENT :

MANISH CHOUDHURY, J.

1. The writ petition under Article 226 of the Constitution of India has been instituted by the petitioner to challenge the award of a contract work, “Comprehensive Garbage Disposal from DBWS for 3 [three] years [2021-2024]” [‘the Contract-Work’ for short] made in favour of the respondent no. 3, by the respondent North East Frontier Railway.

2. The factual matrix of the case lies in a narrow compass. The necessary facts can be exposited, in brief, as follows:

    The respondent North East Frontier Railway [‘the N.F. Railway’, for short] through its Chief Workshop Manager [CWM], Mechanical Workshop, N.F. Railway, Dibrugarh [the respondent no. 2] published a Notice Inviting Tender [NIT] on 07.10.2021 for the Contract-Work vide e-Tender Notice no. DBWS-NIET-06-2021-22 dated 07.10.2021 inviting open tenders through E-Tendering System from competent firms/contractors. As per the NIT, the approximate cost of the Contract-Work was Rs. 56,07,360/-inclusive of GST @ 18%. The NIT notified that the tenders in response to the NIT, would be accepted up-to 15-00 hours, 29.10.2021 and the tenders would be opened at 15-30 hours, 29.10.2021. The NIT and the Tender Document containing the Instructions to Tenderers and Conditions of Tenders, set forth the Minimum Eligibility Criteria. As per the NIT, the Tenderers were required to fulfill the Technical Eligibility Criteria, Financial Eligibility Criteria and Special Criteria contained therein in Clause 1.1, Clause 1.2 and Clause 1.3 respectively. As per Clause 1.4 of the NIT, non-compliance of any of the conditions set forth thereinabove would result in the tender being rejected. Similar Technical Eligibility Criteria, Financial Eligibility Criteria and Special Criteria were also prescribed in Clause 10.1, Clause 10.3 and Clause 10.4 of the Tender Document containing the Instructions to Tenderers and Conditions of Tenders. Clause 10.5 therein had made it clear that non-compliance of any of the conditions set forth thereinabove would result in the tender being rejected.

2.1. In response to the NIT, 5 [five] nos. of tenders were received by the respondent N.F. Railway authorities. Apart from the petitioner, the other 4 [four] tenderers were: [i] M/s Aardi Commercial, [ii] Biswajyoti Bora [the respondent no. 3], [iii] M/s Dynamic Enterprise and [iv] M/s Maa Virasini Construction and Material Supplier. After receipt of the tenders through the e-Procurement Portal, the Techno-Commercial Bids and the Financial Bids were uploaded in the e-Procurement Portal of the N.F. Railway. On opening of the bids, the respondent no. 3 was declared as the lowest tenderer [L-1] and the petitioner herein was declared as the 5th lowest tenderer [L-5].

3. In the Techno-Commercial Bid tabulation, uploaded in the e-Procurement Portal by the respondent N.F. Railway authorities, the documents attached by the participant tenderers in respect of the Special Criteria were mentioned and they were: [i] MSME Certificate by M/s Aardi Commercial, [ii] Pollution Certificate by Biswajyoti Bora [the respondent no. 3], [iii] Undertaking letter by M/s Dynamic Enterprise, [iv] ISO Certificate and letter pad 1 by M/s Maa Virasini Construction and Material Supplier, and [v] Pollution Authorisation by the petitioner. The present writ petition has been preferred questioning the fulfillment or non-fulfilment of the Special Criteria by the other participant tenderers including the respondent no. 3.

4. It is noticed that though notice was served upon the respondent no. 3 by way of dasti, as reflected from the affidavit submitted by the petitioner, none has appeared for the respondent no. 3 and the Court, by Order dated 13.09.2022, had observed that the service of notice upon the respondent no. 3 was duly affected.

5. I have heard Mr. P.J. Saikia, learned Senior Counsel assisted by Mr. R.S. Mishra, learned counsel for the petitioner and Ms. U. Chakraborty, learned Special Senior Railway Counsel for the respondent nos. 1 & 2.

6.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top