IN THE HIGH COURT OF GAUHATI, ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH
MICHAEL ZOTHANKHUMA, J.
Satyanarayan Tea Co. (P) Ltd. – Petitioner
Versus
Assam Power Distribution Company Limited – Respondent
WP (C) No. 3977 of 2016
Decided On : 29-10-2024
(A) Electricity Act, 2003 - Section 126 and 127 - Challenge to final assessment order and bill for unauthorized use of electricity - Petitioner's connected load was found to exceed authorized load due to unreported new machinery - Court held that mere extension of load without actual use does not constitute unauthorized use - Petitioner directed to approach appellate authority under Section 127 for resolution. (Paras 21, 28)
(B) Alternative Remedy - The court emphasized the necessity of exhausting statutory remedies before invoking extraordinary jurisdiction under Article 226 of the Constitution, as established in previous Supreme Court judgments. (Paras 24, 26)
Facts of the case:
The petitioner challenged an assessment order alleging unauthorized use of electricity, claiming that the additional load was not utilized and thus did not exceed the contracted demand. (Paras 2, 18)
Findings of Court:
The court found that the petitioner should have communicated the additional load to the APDCL and that the matter involved technical issues best resolved by the appellate authority. (Paras 21, 28)
Issues: Whether the petitioner's extension of load constituted unauthorized use of electricity and the appropriateness of the court's intervention given the availability of an alternative remedy. (Paras 21, 28)
Ratio Decidendi: The court ruled that unauthorized use requires actual consumption beyond the contracted load, and emphasized the importance of utilizing statutory remedies before seeking judicial intervention. (Paras 21, 28)
Result: Writ petition dismissed, with liberty to approach the appellate authority.
JUDGMENT :
MICHAEL ZOTHANKHUMA, J.
1. Heard Mr. S.K. Kejriwal, learned counsel for the petitioner. Also heard Mr. K.P. Pathak, learned Standing Counsel for the APDCL.
2. The petitioner has put to challenge the final assessment order dated 23.06.2016 and the final electricity assessment bill dated 23.06.2016, by which it was found that the total connected load of 1507 KW was detected against the authorized load of 831.0 KW in respect of the petitioner’s Tea Factory. Hence it was saddled with the bill amounting to Rs.43,88,400/-. The petitioner’s case is that the petitioner is engaged in the business of plantation, manufacture and sale of tea. The authorized connected electricity load in the petitioner’s tea estate is 831 KW, which is equivalent to 978 KVA. The transformer capacity of the tea estate is 1000 KVA. Further, though the petitioner’s connected load was 831 KW, the petitioner’s contract related demand for consumption of electricity was limited to 783 KVA.
3. The petitioner’s case is that the petitioner purchased various equipments in the month of April, 2016 but did not utilise the same, as the petitioner had applied for release of additional electricity load. However, instead of the APDCL according necessary approval for release of the additional load, APDCL officials visited the petitioner’s tea estate for routine checking, wherein they noticed installation of various purchased machineries/ equipments.
4. Mr. S.K. Kejriwal, learned counsel for the petitioner submits that the APDCL officials, on seeing the equipments/machineries, straightway came to the conclusion that the petitioner had exceeded its authorized connected load, without verifying as to whether the said machineries were connected with the APDCL distribution mains. He submits that the officials thereafter prepared a Checking Report, showing the total connected load of the petitioner’s installation at 1507 KW, instead of the actual connected load of 831 KW, thereby alleging that the petitioner had exceeded the connected load by 676 KW. The petitioner’s counsel submits that the Inspection Report is absolutely silent as to whether the load detected was the meter connected load.
5. The petitioner’s counsel submits that in terms of Electricity Bill dated 09.06.2016 which is for the billing period from 01.05.2016 to 31.05.2016, the meter reading details showed that the Recorded Demand (RD) KVA was 0.52 which was less than the Maximum Demand (MD) KVA and Billing Demand (BD) KVA, which was 783 KVA. He accordingly submits that when the electricity bill shows that there has been no use of electricity beyond the contracted demand of 783 KVA, there was no occasion for the APDCL to have come to a finding that the petitioner was in unauthorized use of electricity beyond the petitioner’s connected load. He submits that the extension of load simpliciter, without there being any actual use of electricity, beyond the contract related demand or connected load, does not amount to unauthorized use of electricity, within the meaning of Section 126 of the Electricity Act, 2003.
6. Mr. S.K. Kejriwal submits that in terms of Clause (e) of HT Category VII – Oil and Coal of Schedule of Tariff issued by the APDCL w.e.f. 10.07.2017, if the Recorded Demand is higher than the Contracted Demand in a month, then fixed charge based on Contracted Demand can be levied, at three times the normal rate, for the portion of demand exceeding the Contracted Demand. He submits that in the present case, the Recorded Demand and the Contracted Demand is the same which is 783 KVA. As such, the electricity consumption did not exceed the connected load. He also submits that as there was no consumption of electricity in excess of the sanction/connected load, there was no unauthorized use of electricity in terms of Section 126 of the Electricity Act, 2003, as has been held by the Supreme Court in the case of Executive Engineer & Another vs. Sri Seetaram Rice Mill, reported in (2012) 2 SCC 108.
7. The learned couns
Assistant Collector of Central Excise, Chandan Nagar
M/s Shiv Alloys Steel vs. Assam Power Distribution Company Ltd. & Others
Unauthorized use of electricity requires actual consumption beyond contracted load; mere extension of load without use does not constitute violation.
Unauthorized use of electricity under Section 126 requires actual consumption beyond authorized load; mere extension of load without use does not qualify.
The assessment for unauthorized electricity use must be grounded in factual inspections and regulatory definitions, adjusting the calculation period accordingly.
Electricity - Unauthorized use of electricity - Assessment of electricity charge contemplated in this section is immediately after disconnection but before lodging complaint and that too for the purp....
The assessing officer must establish unauthorized use of electricity before issuing a final assessment order, which can be appealed under Section 127 of the Electricity Act, 2003.
Unauthorized use of electricity for a purpose other than authorized and in premises other than those for which the supply was authorized constitutes a violation of Section 126 of the Electricity Act ....
The court affirmed that unauthorized use of electricity was established through tampering with the meter, justifying the final assessment bill under the Electricity Act.
The assessment of unauthorized electricity use necessitates adherence to connected load guidelines, with special consideration given to meter tampering issues under Section 126 of the Electricity Act....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.