IN THE HIGH COURT OF GAUHATI, ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH
MICHAEL ZOTHANKHUMA, J.
Jorehaut Tea Limited – Petitioner
Versus
Assam Power Distribution Company Limited – Respondent
WP (C) No. 4538 of 2016
Decided On : 29-10-2024
Electricity Act, 2003 - Section 126 and Section 127 - Challenge to final assessment order and bill for unauthorized use of electricity - Petitioner's authorized load was 418 KW, but connected load detected was 839.25 KW - Court held that mere extension of load without actual use does not constitute unauthorized use under Section 126 - Petitioner directed to approach appellate authority under Section 127 for resolution of factual and technical issues. (Paras 21, 28)
Facts of the case:
The petitioner challenged the assessment order and bill issued by APDCL for exceeding authorized load, claiming no actual unauthorized use of electricity occurred.
Findings of Court:
The court found that the petitioner should utilize the statutory remedy available under Section 127 of the Electricity Act, 2003.
Issues: The main issue was whether the petitioner's extension of load without actual use constituted unauthorized use of electricity.
Ratio Decidendi: The court ruled that unauthorized use must involve actual consumption beyond the authorized load, and the petitioner was entitled to appeal under Section 127.
Result: Writ petition dismissed, with liberty to approach the appellate forum.
JUDGMENT :
MICHAEL ZOTHANKHUMA, J.
1. Heard Mr. S.K. Kejriwal, learned counsel for the petitioner. Also heard Mr. K.P. Pathak, learned Standing Counsel for the APDCL.
2. The petitioner has put to challenge the final assessment order dated 21.07.2016 and the final electricity assessment bill dated 21.07.2016, by which it was found that the total connected load of 839.25 was detected against the authorized load of 418 KW in respect of the petitioner’s Tea Factory. Hence it was saddled with the bill amounting to Rs.27,37,920/-. The petitioner’s case is that the petitioner is engaged in the business of plantation, manufacture and sale of tea. The authorized connected electricity load in the petitioner’s tea estate is 418 KW, which is equivalent to 491.76 KVA. The transformer capacity of the tea estate is 500 KVA. Further, though the petitioner’s connected load was 418 KW, the petitioner’s contract related demand for consumption of electricity was limited to 320 KVA.
3. The petitioner’s case is that the petitioner purchased various equipments but did not utilise the same, as the petitioner had applied for release of additional electricity load. However, instead of the APDCL according necessary approval for release of the additional load, APDCL officials visited the petitioner’s tea estate for routine checking, wherein they noticed installation of various purchased machineries/equipments.
4. Mr. S.K. Kejriwal, learned counsel for the petitioner submits that the APDCL officials, on seeing the equipments/machineries, straightway came to the conclusion that the petitioner had exceeded its authorized connected load, without verifying as to whether the said machineries were connected with the APDCL distribution mains. He submits that the officials thereafter prepared a Checking Report, showing the total connected load of the petitioner’s installation at 839.25 KW, instead of the actual connected load of 418 KW, thereby alleging that the petitioner had exceeded the connected load by 422 KW. The petitioner’s counsel submits that the Inspection Report is absolutely silent as to whether the load detected was the meter connected load.
5. The petitioner’s counsel submits that in terms of Electricity Bill dated 11.07.2016 which is for the billing period from 01.06.2016 to 30.06.2016, the meter reading details showed that the Recorded Demand (RD) KVA was 0.28 which was less than the Maximum Demand (MD) KVA and Billing Demand (BD) KVA, which was 283 & 320 KVA respectively. He accordingly submits that when the electricity bill shows that there has been no use of electricity beyond the contracted demand of 320 KVA, there was no occasion for the APDCL to have come to a finding that the petitioner was in unauthorized use of electricity, beyond the petitioner’s connected load. He submits that the extension of load simpliciter, without there being any actual use of electricity beyond the contract related demand or connected load, does not amount to unauthorized use of electricity, within the meaning of Section 126 of the Electricity Act, 2003.
6. Mr. S.K. Kejriwal submits that in terms of Clause (e) of HT Category VII – Oil and Coal of Schedule of Tariff issued by the APDCL w.e.f. 10.07.2017, if the Recorded Demand is higher than the Contracted Demand in a month, then fixed charge based on Contracted Demand can be levied, at three times the normal rate, for the portion of demand exceeding the Contracted Demand. He submits that in the present case, the Recorded Demand and the Contracted Demand is the same which is 320 KVA. As such, the electricity consumption did not exceed the connected load. He also submits that as there was no consumption of electricity in excess of the sanction/connected load, there was no unauthorized use of electricity in terms of Section 126 of the Electricity Act, 2003, as has been held by the Supreme Court in the case of Executive Engineer & Another vs. Sri Seetaram Rice Mill, reported in (2012) 2 SCC 108.
7. The learned counsel for th
Assistant Collector of Central Excise, Chandan Nagar
M/s Shiv Alloys Steel vs. Assam Power Distribution Company Ltd. & Others
Unauthorized use of electricity under Section 126 requires actual consumption beyond authorized load; mere extension of load without use does not qualify.
Unauthorized use of electricity requires actual consumption beyond contracted load; mere extension of load without use does not constitute violation.
The assessment for unauthorized electricity use must be grounded in factual inspections and regulatory definitions, adjusting the calculation period accordingly.
The assessing officer must establish unauthorized use of electricity before issuing a final assessment order, which can be appealed under Section 127 of the Electricity Act, 2003.
The court affirmed that unauthorized use of electricity was established through tampering with the meter, justifying the final assessment bill under the Electricity Act.
Electricity - Unauthorized use of electricity - Assessment of electricity charge contemplated in this section is immediately after disconnection but before lodging complaint and that too for the purp....
The assessment of unauthorized electricity use necessitates adherence to connected load guidelines, with special consideration given to meter tampering issues under Section 126 of the Electricity Act....
Unauthorized use of electricity for a purpose other than authorized and in premises other than those for which the supply was authorized constitutes a violation of Section 126 of the Electricity Act ....
The court emphasized procedural compliance and the necessity for rigorous assessment in determining unauthorized electricity loads, highlighting arbitrariness in prior determinations.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.