THE HIGH COURT OF GAUHATI (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
DEVASHIS BARUAH, J
M/s. PCI Cables Industries Pvt. Ltd. - Appellant
Versus
Assam Power Distribution Company Limited - Respondent
CRP / 7 / 2025
Decided On : 29-01-2025
(A) Arbitration and Conciliation Act, 1996 - Section 37 - Application under Article 227 of the Constitution - Challenge to ex-parte ad interim order - Court held that the Appellate Court had jurisdiction to set aside the ex-parte order and that the contract was determinable in nature; thus, injunction was not permissible under Section 41 of the Specific Relief Act. (Paras 3 , 11 , 12 )
(B) Jurisdiction of Appellate Court - The court noted that an appeal under Section 37 is maintainable against ex-parte interim measures, as established by precedent. (Paras 10 , 12 )
Facts of the case:
The petitioner was awarded a contract for construction work, which was terminated by the respondent. The petitioner sought interim measures under Section 9 of the Act, leading to an ex-parte injunction being granted, which was later set aside by the Appellate Court.
Findings of Court:
The Appellate Court's findings that the contract was determinable and the injunction was not sustainable were upheld.
Issues: Whether the Appellate Court could exercise jurisdiction against an ex-parte order and the nature of the contract.
Ratio Decidendi: The court emphasized that contracts deemed determinable do not warrant injunctions and upheld the Appellate Court's authority under Section 37.
Result: Petition dismissed.
JUDGMENT :
DEVASHIS BARUAH, J.
Heard Mr. H. Gupta, the learned counsel appearing on behalf of the petitioner. Mr. K.P. Pathak appears on behalf of the respondent.
2. This is an application under Article 227 of the Constitution of India challenging the order dated 17.01.2025 passed by the learned Court of Additional District Judge No. 1, Kamrup (M), Guwahati (hereinafter referred to as “the learned Appellate Court) in Misc. Arbitration Appeal No. 01/2025 whereby the ad interim ex-parte order dated 03.01.2025 passed in Misc (Arbitration) No. 01/2025 by the learned Court of the Civil Judge (Senior Division) No.3, Kamrup (Metro) at Guwahati was set aside and quashed.
3. The question which arises in the instant proceedings is as to whether this Court should exercise its supervisory jurisdiction against an order passed by the learned Appellate Court who had exercised jurisdiction under Section 37 of the Arbitration and Conciliation Act, 1996 (for short, “the Act of 1996”). To ascertain the said, this Court would like to briefly deal with the facts leading to the filing of the instant proceedings.
4. The petitioner herein was awarded a contract by the respondent for “Construction of New 33/11 KV Sub-Stations, Construction of 33 KV and 11 KV Lines, 33 KV Terminal Equipments & 33 KV and 11 KV Crossings for Railways/River in Tinsukia Electrical Circle on a Turnkey Basis”. Pursuant thereto, a contract agreement was entered into by and between the petitioner as well as the respondent. The petitioner herein was issued a notice of termination on 15.10.2024 by invoking Clause 42 of the General Conditions of Contract (for short, “GCC”). In response thereto, the petitioner wrote a letter dated 21.10.2024 assuring that there would be significant progress within 3 to 4 months and the contract work would be completed within the agreed date for completion of the project. At this stage, it is relevant to take note of that the completion date was 20.02.2025. Be that as it may, on 23.12.2024, the respondent terminated the contract vide an order bearing No.58. The petitioner thereupon being aggrieved, by the termination order issued a letter dated 31.12.2024 requesting for Appointment of a Dispute Board in terms of Clause 45.1 of Section 7 of the GCC.
5. While the said referral to the Dispute Board was pending, the petitioner also preferred an application under Section 9 of the Act of 1996 seeking interim measures. The said application being taken up as a commercial litigation was endorsed to the learned Court of the Civil Judge (Senior Division) No. 3, Kamrup (M) at Guwahati (hereinafter referred to as “Section 9 Court”) and was registered and numbered as Misc. (Arbitration) Case No. 01/2025. At this stage, it is further relevant to mention that the application under Section 9 of the Act of 1996 was filed on 30.12.2024. The petitioner thereafter received an e-mail dated 02.01.2025 from the respondent regarding invocation and forfeiture of the Bank Guarantee submitted by the petitioner at the time of entering into the Contract Agreement. The said application under Section 9 of the Act of 1996 was moved on 03.01.2025. Be that as it may, the petitioner did neither amend the application filed under Section 9 of the Act of 1996 to insert the cause of action pertaining to the invocation of the Bank Guarantee nor did seek any interim measures in respect to the email dated 02.01.2025.
6. The learned Section 9 Court vide an order dated 03.01.2025 passed an ex- parte ad-interim injunction restraining the respondent herein, their men, agents from giving effect to the termination Order No. 58 dated 23.12.2024 till the next date. The next date was fixed on 17.02.2025.
7. The respondent thereupon preferred an Appeal under Section 37 of the Act of 1996 before the learned Court of the Additional District Judge No. 1, Kamrup (M) at Guwahati, which was registered and numbered as Misc. Arbitratio
The Appellate Court has jurisdiction to set aside ex-parte orders under Section 37 of the Arbitration and Conciliation Act, 1996, especially when the contract in question is deemed determinable.
A petition under Article 227 of the Constitution of India is not maintainable if the conditions for appeal under the Arbitration and Conciliation Act, 1996 are not met, emphasizing the need to adhere....
Bank Guarantee – Courts should be reluctant in granting injunction against invocation of Bank Guarantee, except in cases of established fraud, or where irretrievable injury is likely to be caused to ....
The Court emphasized the importance of adhering to the statutory provisions of the Arbitration and Conciliation Act, particularly regarding the filing of Section 34 applications during the pendency o....
Doctrine of precedent is limited to the decision itself and as to what is necessarily involved in it. It does not mean, it was held, that the court was bound by the various reasons given in support o....
Orders granting or refusing ex-parte interim measures under Section 9 of the Arbitration and Conciliation Act, 1996 are appealable under Section 37, despite the Commercial Courts Act, 2015.
The main legal point established in the judgment is the arbitrator's duty to inform the claimant of their failure to communicate their claim and to provide an opportunity to show sufficient cause, an....
Grant of injunction – Wherever proceedings are under CPC and forum is Civil Court, availability of a remedy under CPC, will deter High Court from exercising its Power of Superintendence.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.